LNG Canada announces short list firms for procurement and construction contractors

 

LNG Canada today short listed two companies, LNG BC Contractors, a partnership of TechnipFMC plc and KBR, Inc. and the partnership of JGC Corporation and Fluor Corporation on the short list to build the proposed LNG Canada facility in Kitimat.

LNG Canada said their commercial negotiations to commence immediately

LNG Canada news release:

Vancouver, British Columbia, February 2, 2018 – Following a year-long request for proposal (RFP) process, LNG Canada announced it has notified two of its four potential engineering, procurement and construction (EPC) contractors that they have been shortlisted for the chance to build the company’s proposed LNG export facility in Kitimat, British Columbia.

LNG Canada intends to select the preferred EPC contractor sometime in 2018. Negotiations will begin immediately with the two EPC contractors to determine the most commercially competitive proposal.

LNG Canada identified the finalists as the partnership of TechnipFMC plc and KBR, Inc. (LNG BC Contractors), and the partnership of JGC Corporation and Fluor Corporation.

Following a decision to delay a final investment decision in 2016, LNG Canada used the delay period to issue an RFP to identify a preferred EPC contractor willing to build the proposed LNG Canada project on a lump sum basis. LNG Canada prequalified four EPC consortia based on several criteria, including prior experience in LNG design and modularization, track record of project completion, and experience with construction in Western Canada.

“This process is critical in LNG Canada’s pursuit of the level of competitiveness required to support a future final investment decision by our joint venture participants,” said Andy Calitz, CEO of LNG Canada. “A tremendous amount of time and effort has been invested by the four EPC consortia, as well as by LNG Canada’s internal review team, and I thank them all for their contributions to the RFP process thus far.”

LNG Canada’s proposal evaluation criteria included health and safety management, financial strength, technical design, execution plans, contract price and schedule. The proposers also committed to living up to LNG Canada’s values and the commitments it has made to local communities, First Nations, as well as the company’s high standards of social and environmental performance.

“While this is a significant milestone, work remains to be done to deliver a globally cost competitive project that is well positioned to take a final investment decision,” added Calitz. “We look forward to working closely with TechnipFMC plc and KBR, Inc. and JGC Corporation and Fluor Corporation to advance our project in British Columbia that will benefit the regional, provincial and national economy.”

LNG Canada final investment decision 18 to 24 months away, CEO says. Has concerns about air shed, pipelines

LNG Banada
The LNG Canada site at the old Methanex plant in Kitimat, April 29, 2014. (Robin Rowland/Northwest Coast Energy News)

The final investment decision for the LNG Canada project is 18 to 24 months ahead,  Andy Calitz, CEO LNG Canada said Wednesday.

Calitz said that the project must go through a series of what are called “stage gates” before the respective corporate boards of the partners make that decision. Calitz said the project has already completed three stages, identifying the project, testing the idea, selecting what exactly the proponents are going to do. “Then there is the so-called design stage when all the design experts come in. We are hundred per cent certain we are tackling the next phase.” It is when the design phase is complete and then depending on world market conditions, that the final investment decision will be made.

Caltiz also pointed to one reason that while the LNG Canada project is moving ahead slowly,it appears to be moving faster than the rival Chevron-Apache Kitimat LNG project. That’s because the four investors in the LNG Canada project, Shell, PetroChina, Mitsubishi and KoGas (Korea Gas) are the customers, shipping their own product via the proposed TransCanada Coastal Gaslink pipeline, to the jointly owned terminal that will be built on the old Methanex site in Kitimat.

Caltiz’s comments came at a Vancouver news conference called to announce a joint venture agreement between the four partners. Under today’s agreement, Shell has increased its stake in the project to 50 per cent from 40 per cent; PetroChina will hold 20 per cent and each of Kogas and Mitsubishi Corporation holding 15 per cent. PetroChina and Shell increased their holdings by buying from the other partners.

Calitz said, “They each bring their own gas, they each put their own capacity in the pipeline to be transported by Transcanada, they together own the energy plant, then they lift the cargo in the same proportion, taking in to their own potrfolios, for every cargo that is produced, say for every 100,000 cubic metres, 15 will go Kogas 15 to Mitsubishi 20 will go Petrochina and 50 will go to Shell.”

One reason, along with the volatility and uncertainty of the liquified natural gas market that the Chevron Apache Kitmat LNG project appears to have stalled is a lack of customers. Kitimat LNG has said it is looking for equity partners similar to what was said today about the LNG Canada project.

Air shed

Asked a general question about environmental concerns, Calitz singled out local concerns about the air shed quality in the Kitimat valley and similar concerns up in Prince Rupert, saying, “We are at all times very sensitive to our environmental impact… In the case of the airshed around the LNG plant, it is being quantified, it;s being looked at cumulatively in Prince Rupert, in Kitimat. We also make sure that we work with the government about the sensitivity of air shed impact to the communities of Terrace and Kitimat. I can confirm your point it is high on our agenda. We understand the issues we all developed energy projects before and will continue to be vigilant.”

He said there were three main concerns that would affect the final investment decision: “Where does the Asian gas price go? Two will we have enough labor and what will the labor rates and labor productivity be and three between the various companies that have a lot of experience in Canada specifically TransCanada pipelines into Kitimat, and the other pipeline company going into Prince Rupert, we need to get those pipelines through the mountains.”

While it may be reading too much into one statement, it appears that LNG Canada and its partners are taking a more careful approach to pipeline construction than the Enbridge Northern Gateway project where that company was always certain its plans for crossing the rugged northwest BC mountains would yield few problems.

Russia crisis

The other major factor governing any decision on LNG plants in British Columbia is the volatile marketplace.

Reporters at the Vancouver news conference asked Caltiz about reported talks between China and Russia where Russia, now facing economic sanctions for its actions against Ukraine, would ship natural gas to China and if that would affect BC plans to export LNG to China.

“One can always draw linkages between any two subjects but I would say the linkage is between very weak and non existant,” Calitz said. “The closeest that anyone can come to a linkage is do the events in Europe and Ukraine increase the likelihood of a major pipeline between Russia and China, that’s for Russia and China to decide, but apart from that very very weak linkage.”

That state of prices remains a concern among reports that several Asian nations including the giants India and China plan to form a sort of buyers club, to drive down the high price of natural gas, which in Asia is a percentage of the price of crude oil, while in North America, market conditions have driven the price of natural gas much lower.

“There is a very active daily debate about prices paid for LNG in Asia. That debate, I am sure, will continue as long as the Henry Hub [the North America market price] is at $4 and Europe is at $8 and Asia based is somewhat from 12 to 18 dollars, depending on whether its contract or spot.

“If you ask is that of concern, then every project here will be affected by changes in price, whether the price goes up or down. will impact the final investment decision and it will impact in the way say the Pacific Northwest or the Kitimat LNG project.

“We as an energy project in British Columbia, like all other energy projects, like even from East Africa are looking at production costs and what the Asian prices are. So by 2015, what happens to that price and what happens in those negotiations will feature in the decisions of all the players.”

In a prepared statement, Calitz said,”“While we are in the early evaluation process and a decision to build the project is still a while away, this agreement reinforces our commitment to developing an LNG facility in British Columbia and allows us to proceed with the next steps in our project assessment, We will need to continue to work closely with the provincial and federal government to ensure that the project is economically viable, as well as working closely with First Nations, the local communities, and regulatory agencies, and move forward on a number of commercial agreements and contracts. We remain cautiously enthusiastic about the potential opportunity in B.C. and look forward to exploring it further.”

Premier Christy Clark, who made a brief appearance at the news conference before leaving to a prepare for another sales trip to Asia, was more optimistic, saying: “The private sector doesn’t make billion dollar investment decisions if they don’t think there isn’t going to be a return on it. It’s not for me … to determine what the market looks like, it’s the private sector that does that and I think the answer to them is you would not see those major companies taking the next step signing a joint venture agreement today if they didn’t think there was a market for BC gas.

“The other advantage that BC has that we will never sacrifice is our reputation as a dependable, reliable, honourable trading partner. When people do business in British Columbia on natural gas, they know we won’t play politics with them.They know we will keep our promises about where the tax levels will be and how they’re going to be treated as trading partners. That is a tremendous advantage for us in an unstable world.”

 

Temporary foreign workers

Asked by a reporter about LNG projects using temporary foreign workers, Clark replied. “The thing about temporary foreign workers is that temporary workers should come for temporary jobs, And in the process of building these huge facilities and pipelines with peaks in construction that we will not be able to meet within British Columbia or even Canada. There’s no question about that.
“Our view is very much British Columbians first, and the way to do that is to make sure people have all the skills training that they need to take advantage of those jobs, second reach out to the rest of the country and then third work with the unions and other organizations when needed to support temporary foreign workers coming in.

“We’ve had remarkable consensus with the trade unions, recognizing the need for some temporary foreign workers at some point in the construction of these projects. That’s why we’ve gone about planning it so carefully because we want to make sure when we will need workers in what skill set in what month and what years. We’re really breaking it down so we can be sure we have exhausted British Colunbia’s potential to fill those jobs before we start to look across the country or around the world.”

LNG Canada signing
LNG Canada joint venture agreement signing cermony in Vancouver, April 30, 2014, left to right, Jorge Santos Silva, Executive Vice President Shell Upstream Americas Commercial, Bi Jingshuang, Director – Legal Department of China National Oil and Gas Exploration and Development Corporation (CNODC), representing PetroChina, Andy Calitz, CEO, LNG Canada, Hiroki Haba, Vice President, Natural Gas Business Division, Mitsubishi and Jongkook Lim, Vice President, LNG Business Department, Korea Gas. Standing wathc are Christy Clark, Premier of British Columbia and Rich Coleman, Minister of Natural Gas Development. (LNG Canada)

Projects on the go

The news release listed the many LNG projects under way from the four partners.

Shell currently has ten LNG projects in operation with approximately 26.1 million tonnes per annum (mtpa) operational LNG capacity, in nine countries, and two projects
with an additional 7.5 mtpa under construction. Shell is also one of the largest LNG vessel operators in the world, with interests in around a quarter of the LNG vessels in operation.

Phoenix Energy Holdings Limited (an affiliate of Petro-China Investment (Hong Kong) Limited) (“PetroChina”) is China’s largest oil and gas producer and supplier, as well as
one of the world’s major oilfield service providers and a contractor in engineering construction. PetroChina officially launched three LNG projects in June 2004, two of
which started operations in the first half of 2011.

Kogas Canada LNG is the world’s largest LNG importer. As the nation’s sole LNG provider, KOGAS currently operates three LNG terminals and a nationwide pipeline network, supplying natural gas fromaround the world to power generation plants, gas-utility companies and city gas companies throughout the country.

Since pioneering the first LNG import to Japan from Alaska in 1969, Mistubishi handles 40 per cent of Japan’s LNG imports and has successfully built a portfolio of LNG export investments across Australia, Indonesia, Malaysia, Brunei, Oman, Russia and North America.

With the joint venture agreement, the group has incorporated a new federal corporation, LNG Canada Development Inc. The project’s corporate offices will continue to be located in Vancouver and Calgary, with the project office based in Kitimat.

Although pegged as a “major milestone” in the development of LNG Canada, the Kitimat social media rumour mill was correct in speculation Tuesday that the news conference concerned a corporate name change and sale of assets.   The event was probably more a kickoff for Christy Clark’s upcoming tour of Asia.