PART TWO: What the State Dept. Keystone EIS says about Kinder Morgan and Vancouver harbour

The US State Department report on the controversial Keystone XL pipeline project also looks at the Kinder Morgan Transmountain pipeline (both the existing line and the proposed second line) and, in at least one part of the report, seems to speculate that, once expansion of the Panama Canal is completed in 2014, there could be larger tankers in Vancouver harbour, something that up until now, both Kinder Morgan and Port Metro Vancouver have denied. However, the State Department report does not say how the port of Vancouver could handle larger tankers.

The State Department EIS says if larger tankers were loaded at Vancouver, it could be economic for crude from the Kinder Morgan Transmountain pipeline to be moved to the US Gulf Coast.

Using heavy crude as a basis, a present day movement via Trans Mountain to Vancouver and thence on a Panamax tanker via the Panama Canal to Houston would have a total freight cost (pipeline tariff plus tanker freight and Panama toll) of around $8.50-9.50/barrel (bbl).

Recognizing that Kinder Morgan plans to enable future shipment in larger Suezmax tankers, and that the Panama Canal Authority is expanding the Canal to take tankers of that size, the rate using a Suezmax would be approximately $1/bbl lower. These rates compare to approximately $8/bbl to move heavy crude via pipeline from Hardisty to Houston. Thus, while in normal markets, a tanker movement from Western Canada would be somewhat more costly than via pipeline, in a scenario where ability to move WCSB crudes by pipeline to the U.S. Gulf Coast were constrained, refiners in the U.S. Gulf Coast could opt for tanker transport.

(The Panama Canal expansion program began in 2006 and is scheduled for completion in 2014)

Latest progress report (pdf)

According to the progress report the current Panama Canal has the capacity for ships that are 32.3 metres wide by 304.6 metres long, This will increase to 49 metres wide by 366 metres long.

Later in the report the State Department goes on to say that bitumen and crude could, as an alternative to Keystone, go to Vancouver:

Under this option, WCSB [Western Canada Sedminetary Basin] would be shipped by existing railways or new pipelines from the Hardisty region to Vancouver or Kitimat, British Columbia for shipment by marine transport through the expanded Panama Canal and delivery to Gulf Coast area refiners. This option considers moving up to 730,000 bpd of heavy crude to the Port of Vancouver and then to the marine docks at the Westridge marine terminal in Vancouver or the port in Kitimat. Under this option, crude oil could move either via rail or by a new pipeline from the Hardisty region.

Currently, Kinder Morgan is planning an expansion of the existing Trans Mountain pipeline originating at Edmonton, increasing its capacity from 300,000 bpd (current) to up to 890,000 bpd(planned for operations in 2017).

The Trans Mountain pipeline runs into Vancouver via the existing Burnaby terminal over to the Westridge dock for loading heavy crude onto vessels. The pipeline has sufficient commitment from shippers to proceed with engineering and permitting processes. Kinder Morgan indicates that the project would significantly increase tanker traffic from about 5 to 34 cargoes per month, or up to about 400 cargoes per year . The increased marine traffic is due to increased volume to be shipped, and lack of sufficient channel draft to load larger vessels.

Kinder Morgan on its website says

The proposed expansion at Westridge Terminal is based on the loading of Aframax tankers, the same tankers currently being loaded at Westridge. Larger tankers are not permitted in the Vancouver harbour, and are not under consideration for the expansion. Proposed changes at the dock include new loading facilities, fire protection, vapour recovery, secondary containment, and emergency response equipment.

To connect the Burnaby Terminal with the Westridge Terminal, the proposed expansion includes two new, four-kilometre pipelines each with a diameter of 762 millimeters (30 inches). These two new delivery lines would provide product deliveries to tankers at two new dock berths, and provide the scheduling flexibility required for a marine operation.

Port Metro Vancouver also says on its website:

The role of Port Metro Vancouver is to conduct a rigorous project review to ensure the safe movement of goods through the Port. Kinder Morgan has yet to submit a formal project proposal to Canada’s National Energy Board. If they do, and should approval be granted, the project would then undergo several other permitting processes, one of which is a Port Metro Vancouver Project Permit Review. Vancouver is a very low volume tanker port. Currently, there are about 100 crude oil and chemical tankers calling the port each year. If the Kinder Morgan project receives approval, that number could increase to approximately 400 tankers a year. Other well-run ports such as the Port of Rotterdam handles 8,206 tankers a year, while Singapore handle 22,280 tankers a year.

Will larger tankers be calling at Port Metro Vancouver as a result of the Kinder Morgan Proposal?

There are no plans to exceed the current maximum size of tankers calling at Port Metro Vancouver. Due to depth restrictions in the Burrard Inlet, the largest dimension of tanker that can be handled is the Aframax, a medium-sized tanker with a maximum capacity of 120,000 tonnes. Even then, these vessels can load to only around 80% of capacity due to draft restrictions.

 

The State Department EIS was cautious about the Kinder Morgan project and did not do the same deailed analysis as it did for Prince Rupert.

The substantial increase in tanker traffic from the proposed Kinder Morgan expansion has raised safety and environmental concerns. Moving additional volumes of crude oil from the proposed Project into the Vancouver market by either a new pipeline or rail would result in 400 or more additional vessels loading at Vancouver each year and would require considerably more storage to be built than the current Kinder Morgan operations. The expansion of storage capacity, potential rail off-loading facilities and logistics, and increased marine traffic may make this option logistically challenging in a relatively compressed and populated geographical area.

Moreover, even if a separate pipeline from Hardisty could be planned, mapped, engineered, designed, and permitted starting today, it would likely not be available as an option until well after the proposed [Keytsone] Project’s planned start date. As a result of the logistical challenges in increasing the amounts of heavy Canadian grades of crude oil coming into the Vancouver/Burnaby region over and above the volumes from the Kinder Morgan expansion, this option was deemed to be less viable than movements from Kitimat and Prince Rupert and was eliminated from detailed analysis.

It’s not clear from the Keystone EIS, if the State Department was simply speculating on larger tankers in Vancouver harbour or if it was made of aware of possible hopes for a deep water tanker port elsewhere in the Vancouver harbour area.

 

Port Metro Vancouver tanker diagram
Port Metro Vancouver diagram showing the tankers that are permitted and not allowed in Vancouver harbour. (Port Metro Vancouver)

 

The State Department EIS goes on to note:

While no new additional pipeline capacity has been added from Canada into the United States or to the Canadian West Coast since the Final EIS in 2011, a number of projects are proposed, including this proposed Project. The 300,000 bpd Kinder Morgan Trans Mountain pipeline that runs from Edmonton to the British Columbia coast at Vancouver, with a spur to Washington State refineries, has been over-subscribed for some time. A successful open season led the Kinder Morgan to announce and file for expansion to 750,000 bpd by potentially 2017. After a
second open season, Kinder Morgan has increased the expansion to 890,000 bpd. The bulk of the incremental crude moved on the line would potentially be destined for Asia. The review process for this project is continuing, but there is significant opposition based on concerns over environmental impacts associated with the oil sands and with additional tanker movements in the Port Vancouver harbor.

As noted above, both of these proposed pipeline projects to Canada’s West Coast face significant resistance and uncertainty, but there are strong cost advantages when compared with moving WCSB crude to the Gulf Coast even if rail were used to access the Canadian West Coast... In fact, using rail and tanker to ship crude oil from the WCSB via the West Coast to China is comparable to the pipeline rate to reach the U.S. Gulf Coast. An increase in the transport costs to the Gulf Coast (utilizing alternative transport options such as rail) would have a tendency to increase the economic incentive to utilize any West Coast export options, if they are available.

 

Northwest Coast Energy News Special report links

What the Keystone Report says about Kitimat and Northern Gateway
What the Keystone Report says about the Kinder Morgan pipeline to Vancouver.
What the Keystone Report says about CN rail carrying crude and bitumen to Prince Rupert.
The State Department Environmental Impact Study of the railway to Prince Rupert scenario.

State Department news release

State Department Index to Supplemental Environmental Impact Study on the Keystone XL pipeline

 

TransCanada agrees to reroute Keystone XL around sensitive areas

Energy Environment Politics

TransCanada Corporation announced Monday that it will reroute the controversial bitumen pipeline around environmentally sensitive areas in Nebraska.

At a news conference, in the state capital, Lincoln and in a news release, posted on its website, the company said that it supports proposed Nebraska state legislation that would ensure a pipeline route will be developed in Nebraska that avoids the environmentally sensitive Sandhills region.

Alex Pourbaix, TransCanada president for Energy and Oil Pipelines said, “”I am pleased to tell you that the positive conversations we have had with Nebraska leaders have resulted in legislation that respects the concerns of Nebraskans and supports the development of the Keystone XL pipeline…I can confirm the route will be changed and Nebraskans will play an important role in determining the final route.”

The company says it will work with the US State Department and Nebraska’s Department of Environmental Quality will conduct an environmental assessment to define the best location for Keystone XL in Nebraska. “We will cooperate with these agencies and provide them with the information they need to complete a thorough review that addresses concerns regarding the Sandhills region.”

TransCanada said.

The decision comes just four days after last Thursday’s decision by the State Department to postpone consideration of the pipeline project to allow the agency to look at alternative routes.

The 2013 decision date would also avoid the US presidential election cycle which is beginning to ramp up at this time.

In the news release,

TransCanada emphasized the safety measures it is taking on the project.

Construction of the pipeline in Nebraska would consist of five or six new pump stations and over 275 miles of new pipeline. The project is expected to employ over 2,200 construction workers in the state.

Keystone XL will be safe, built with high strength steel and with the highest safety standards of any pipeline in North America. 21,000 sensors monitor the length of the pipeline by satellite 24 hours a day, 365 days a year, with data refreshed every five seconds. If there is a problem, automatic shut-off valves can be activated in minutes – shutting off the flow of oil.

“The U.S. Department of State announced last Thursday that further assessment of alternative routes for Keystone XL was needed in Nebraska to move forward with the National Interest Determination. Today’s proposed legislation is a critical step in making this happen,” Pourbaix added. “The safe and reliable operation of our pipelines and all of our infrastructure has been TransCanada’s priority for 60 years. This commitment will continue to guide us toward a positive outcome in Nebraska.”

The pipeline would carry bitumen from the Alberta bitumen sands to refineries in Texas.

Keystone “too important not to proceed” TransCanada CEO says

Energy Environment Politics

622-tc_logo-thumb-110x27-621.jpgThe CEO of TransCanada,  Russ Girling, reacting to news that the US State Dept. has delayed approval of the Keystone XL pipeline said Thursday, Nov. 10, 2011, “This project is too important to the U.S. economy, the Canadian economy and the national interest of the United States for it not to proceed.”

While Girling also said, “”We remain confident Keystone XL will ultimately be approved,” but the news release from TransCanada also acknowledged:

… while Keystone XL remains the best option for American and Canadian producers to get their oil to the U.S. Gulf Coast, today’s announcement by the DOS could have potential negative ramifications, especially where shippers and U.S. refiners are concerned.

“Supplies of heavy crude from Venezuela and Mexico to U.S. refineries will soon end,” said Girling. “If Keystone XL is continually delayed, these refiners may have to look for other ways of getting the oil they need. Oil sands producers face the same dilemma – how to get their crude oil to the Gulf Coast.”

In the release, TransCanada says the company will be discussing its next steps with the U.S. Department of State after it said further analysis of route options for the Keystone XL pipeline need to be investigated, with a specific focus on the Sandhills in Nebraska.

TransCanada said the company has already studied 14 different routes for Keystone XL, eight in Nebraska. The earlier studies included one potential alternative route in Nebraska that would have avoided the entire Sandhills region and Ogallala aquifer and six alternatives that would have reduced pipeline mileage crossing the Sandhills or the aquifer. TransCanada said the company hopes this work will serve as a starting point for the additional review and help expedite the review process.

“If Keystone XL dies, Americans will still wake up the next morning and continue to import 10 million barrels of oil from repressive nations, without the benefit of thousands of jobs and long term energy security,” concluded Girling. “That would be a tragedy.”

TransCanada said it has held more than 100 open houses and public meetings in six states since 2008, The company said thousands of pages of supplemental information and responses to questions were submitted to state and federal agencies. The State Department received over 300,000 comments on the project.

US State Department delays Keystone approval until 2013, new route likely if approved

Energy Environment Politics

 Updated 1915 Nov. 10, with link to TransCanada statement, 1940 with more reaction.

The United States Department of State has delayed approval of the controversial Keystone XL pipeline until 2013.

A news release posted on the State Department’s website confirmed earlier media speculation about a delay in the pipeline project approval until after the current US presidential election cycle.

Based on the Department’s experience with pipeline project reviews and the time typically required for environmental reviews of similar scope by other agencies, it is reasonable to expect that this process including a public comment period on a supplement to the final EIS [Environmental Impact Statement]…  could be completed as early as the first quarter of 2013. After obtaining the additional information, the Department would determine, in consultation with the eight other agencies…  whether the proposed pipeline was in the national interest, considering all of the relevant issues together. Among the relevant issues that would be considered are environmental concerns (including climate change), energy security, economic impacts, and foreign policy.

The State Department release also indicates that,if the Keystone XL pipeline is approved, it will likely be rerouted around environmentally sensitive areas, further delaying construction and likely raising costs for TransCanada, the company that wants to build the pipeline. The release says that the State Department has been “conducting a transparent, thorough and rigorous review of TransCanada’s application.”

As a result of this process, particularly given the concentration of concerns regarding the environmental sensitivities of the current proposed route through the Sand Hills area of Nebraska, the Department has determined it needs to undertake an in-depth assessment of potential alternative routes in Nebraska…

During this time, the Department also received input from state, local, and tribal officials. We received comments on a wide range of issues including the proposed project’s impact on jobs, pipeline safety, health concerns, the societal impact of the project, the oil extraction in Canada, and the proposed route through the Sand Hills area of Nebraska, which was one of the most common issues raised….

The concern about the proposed route’s impact on the Sand Hills of Nebraska has increased significantly over time, and has resulted in the Nebraska legislature convening a special session to consider the issue.

The CEO of TransCanada, Russ Girling, reacting to news that the US State Dept. has delayed approval of the Keystone XL pipeline said Thursday, Nov. 10, 2011, “This project is too important to the U.S. economy, the Canadian economy and the national interest of the United States for it not to proceed.”

 
Girling also said, “”We remain confident Keystone XL will ultimately be approved.

The premier of Alberta, Alison Redford called the decision “disappointing,” saying in a news release:

“It is disappointing that after more than three years of exhaustive
analysis and consultation on this critical project, we find out that a
decision will be delayed until early 2013. Our position has always been
clear that we respect and understand that approval of the pipeline is a
U.S. domestic matter, but the fact remains that Keystone XL is a key
piece of infrastructure for our province. I sincerely hope that the
State Department made this decision based on science and evidence and
not rhetoric and hyperbole from very well-organized interest groups.


Alberta is steadfastly committed to this project and my government will
continue to advocate that we are the safest, most secure and responsible
source of oil for the United States. I will seek immediate answers
from U.S. officials to determine why this decision was made and how the
process will unfold going forward.


The industry group the American Petroleum Institute was less diplomatic than Redford, in its own words, the API “blasted” the decision and directly blaming what it called “radicals.”

This decision is deeply disappointing and troubling. 
Whether it will help the president retain his job is unclear, but it
will cost thousands of shovel-ready opportunities for American workers,”
said API President and CEO Jack Gerard.


“There is no real issue about
the environment that requires further investigation, as the president’s
own State Department has recently concluded after extensive project
reviews that go back more than three years.  This is about politics and
keeping a radical constituency opposed to any and all oil and gas
development in the president’s camp in November 2012.

There has been speculation that cancellation or delay of the Keystone XL project would increase pressure to build the Enbridge Northern Gateway pipeline.