Cullen calls Clark Redford pipeline deal “a bust hand”

Skeena Bulkley Valley MP and NDP House leader is calling today’s framework deal between BC Premier Christy Clark and Alberta premier Alison Redford, “a bust hand.”

In a statement released late Tuesday, Cullen said:

MP Nathan Cullen called the BC-Alberta framework agreement struck this morning regarding Enbridge “political window-dressing” that draws a blind on truth and transparency and deals a bust hand to British Columbia.

“When it comes to the Enbridge Northern Gateway Pipeline, everything is negotiable for Christy Clark, including principals and promises made leading up to last May’s provincial election,” Cullen said.

“The reality is that none of the five conditions Ms. Clark made such a big deal about 16 months as being necessary for Enbridge to put a pipeline through our province were even remotely addressed in today’s announcement.

“The best we got after overnight negotiations and months of high drama is the ‘possibility of progress’ and a bizarre blessing that somehow allows BC to negotiate directly with Enbridge.

“Today’s agreement does absolutely zero to protect BC’s environment and economy from a bitumen disaster,” Cullen said.

“It’s a shameful political ploy that greases Ms. Clark’s real agenda, which is to pump oil through BC regardless of environmental or economic costs.

“Six months into a new mandate and Premier Clark has turned her back on promises to stand up for BC and demand a higher standard from industry.”

Cullen noted Enbridge’s social licence to operate is clearly tied to safe oil transport, effective spill response, and First Nations consent, conditions on which today’s agreement is silent.

Cullen vowed to continue fighting the Enbridge pipeline and to work toward sustainable resource development that is supported by Skeena-Bulkley Valley communities.

Ellis Ross posts development philosophy on Facebook

Haisla Chief Counsellor Ellis Ross has posted a statement on Facebook, outlining his philosophy on energy development.

 

Ellis Ross
Haisla Nation Chief Counsellor Ellis Ross at Bish Cove, June 19, 2013. (Robin Rowland/Northwest Coast Energy News)

In 2003 I was first elected to Haisla Nation Council, and I was intent on opposing just about every economic development project coming our way, from fish farms to natural gas. Fortunately experienced councilors suggested that before I took any hard and fast positions that I consider unbiased facts and the community’s social situation.

It didn’t take long before the full extent of our community’s problems hit home, angering and saddening me at the same time. Before my political career I was one of those who applauded political speeches on unemployment, poverty, independence, and the relationship between First Nations and the Crown. But it was now clear that 30 years of speeches and government programs had changed nothing for the average Haisla person who just wanted a job. Unemployment was still at 60 per cent, housing was based on hand-outs from Ottawa, and, worst of all, substance abuse and suicides were commonplace and were destroying our people’s hopes for a brighter future.

I was fortunate to have found work outside of my reserve for most of my adult life but there are only so many jobs in depressed economies and the long term jobs were kept out of our reach by organizations associated with the corporations set up in our territory. The result was our young men and women either had to leave home for employment or stay home and accept seasonal work (UIC) or welfare. Leaving ancestral homes is a hard decision for First Nations to make. The land is connected to our protocols, our culture and to our past.

Many reasons have contributed to the demise of our peoples and communities but perhaps the foremost is the culture of dependence. Dependance in our case was from the top down; from council dependant on government funding to the individual band member being dependant on council or welfare. Our people are not lazy. The culture that preceded the non haisla culture was one of hard work to bring in food, resources and wealth. That culture has not merged so well with non haisla culture but our work ethic is the same as the non haisla culture.

If poverty is the only lifestyle you know, it is very difficult to know there is a way out, much less thinking of a way to get out of it. The individual band member that is watching development in their territory and watching the wealth being generated without having an opportunity to be a part of it is going to have resentment.

Those Nations which are succeeding — strong employment levels, healthy communities, few social ills — appear to have gained a level of independence and have done it mostly through economic development. The newer discussions are those concerning shiftwork, double time, new bosses and how paychecks will go towards the next hunting trip or holidays to vancouver or elsewhere.

We have many proposals put in front of us now that we have to sift through. When we look at these proposals we have to find accurate information in terms of impacts, benefits and feasibility. Sub topics can be right of ways, fracking, logging practices, financing, permitting, corporate structures, emissions, land ownership and the list goes on and on. We do have to consider the future but we also have to consider the present and the situation we know that our membership is in and try to put them in a position where they can help themselves.

So far, the outlook has been positive. Our people have jobs. They have hope. They are confident about their futures. The despair that comes with poverty is slowly disappearing but we have more work to do to ensure their confidence can be sustained. We know that to become a strong independent Nation, we need to have strong independent members.

We will continue to look at the contentious issues that are in front of us and will try as much as we can to resolve with both the crown and the proponent but we cant lose sight of one of the biggest reasons of why we’re doing what we do. Our members need a future.

By the way, the work we have done to date has not only assisted our members but has assisted the region and non Haislas in ways that we have not yet even started to measure yet.
Ross.

Ross later posed two comments:

Ellis Ross: got some good feedback on this but also got feedback that it was unclear on the point I was trying to make so I rewrote it. the point was in light of all the issues we have to look at, we can’t lose sight of the social factor in that some Haislas (and non Haislas) deserve the employment/contract opportunity that comes with proposed projects.

Ellis Ross: fracking, emissions, land ownership, etc… are issues that are extremely important but our people living in poverty with no hope is also an extremely important issue.

BC Alberta agree on five energy conditions: Twitter reaction

BC Alberta agreement on five conditions: BC news release

VANCOUVER – After officials worked through the night, Alberta Premier Alison Redford and British Columbia Premier Christy Clark today announced a framework agreement between the two provinces on moving energy resources to new markets.

“Agreement on B.C.’s 5 conditions is a necessary first step before any proposals can be considered for approval,” said Premier Christy Clark. “It is the way we do business in B.C. and it works. By working together with Alberta through these principles we can grow our economies, and strengthen Canada’s economy overall.”

The framework will also see the Government of British Columbia endorse Premier Redford’s Canadian Energy Strategy.

“A key part of our Building Alberta Plan is getting Alberta’s resources to new markets at much fairer prices so we can keep funding the programs Albertans told us matter most to them,” said Premier Alison Redford. “Today’s agreement with B.C. is good news for Alberta, for British Columbia and for all Canadians. I welcome Premier Clark’s endorsement of the Canadian Energy Strategy and our shared commitment to create jobs, long-term growth and position Canada as a true global energy superpower. We look forward to continued constructive dialogue with B.C.”

The governments of B.C. and Alberta agree that British Columbia’s conditions are intended to ensure both the responsible production of energy as well as its safe transport to new markets, giving projects the social licence to proceed.

B.C.’s conditions 1-4 are designed to achieve both economic benefit and risk mitigation on increased shipments through B.C. They mirror Alberta’s legislated commitments on responsible energy production. Alberta and B.C. agree that only through intensive environmental review and protection, enhanced marine safeguards and First Nations support, can projects proceed.

On condition five, Alberta agrees that B.C. has a right to negotiate with industry on appropriate economic benefits. Both governments agree it is not for the governments of Alberta and B.C. to negotiate these benefits. Both provinces reaffirmed that Alberta’s royalties are not on the table for negotiation.

BC Alberta agree on Christy Clark’s five conditions: Alberta news release

Office of the Premier
Office of the Premier of Alberta

Alberta and British Columbia reach agreement on opening new markets

VANCOUVER – After officials worked through the night, Alberta Premier
Alison Redford and British Columbia Premier Christy Clark today
announced a framework agreement between the two provinces on moving
energy resources to new markets.

“Agreement on B.C.’s 5 conditions is a necessary first step before any
proposals can be considered for approval,” said Premier Christy Clark.
“It is the way we do business in B.C. and it works. By working together
with Alberta through these principles we can grow our economies, and
strengthen Canada’s economy overall.”

The framework will also see the Government of British Columbia endorse
Premier Redford’s Canadian Energy Strategy.

“A key part of our Building Alberta Plan is getting Alberta’s resources
to new markets at much fairer prices so we can keep funding the
programs Albertans told us matter most to them,” said Premier Alison
Redford. “Today’s agreement with B.C. is good news for Alberta, for
British Columbia and for all Canadians. I welcome Premier Clark’s
endorsement of the Canadian Energy Strategy and our shared commitment
to create jobs, long-term growth and position Canada as a true global
energy superpower. We look forward to continued constructive dialogue
with B.C.”

The governments of B.C. and Alberta agree that British Columbia’s
conditions are intended to ensure both the responsible production of
energy as well as its safe transport to new markets, giving projects
the social licence to proceed.

B.C.’s conditions 1-4 are designed to achieve both economic benefit and
risk mitigation on increased shipments through B.C. They mirror
Alberta’s legislated commitments on responsible energy production.
Alberta and B.C. agree that only through intensive environmental review
and protection, enhanced marine safeguards and First Nations support,
can projects proceed.

On condition five, Alberta agrees that B.C. has a right to negotiate
with industry on appropriate economic benefits. Both governments agree
it is not for the governments of Alberta and B.C. to negotiate these
benefits. Both provinces reaffirmed that Alberta’s royalties are not on
the table for negotiation.

Check out Kitimat’s LNG competition

Screen grab American Petroleum Institute interactive map of LNG export projects. (API)
Screen grab American Petroleum Institute interactive map of LNG export projects. (API)

The American Petroleum Institute, the lobby group for US energy companies has launched an interactive map on its website covering liquefied natural gas export projects.

The API says the U.S. Department of Energy has approved only four applications for permits to export liquefied natural gas nations that don’t have a free trader agreement with the US, adding: “There are currently 21 pending applications, covering 18 discrete facilities where U.S. businesses are seeking to build and operate terminals to process LNG for sales abroad.”

API interactive LNG export map
(requires Flash, may be slow loading)

 

While the map does show proposed projects at Kitimat and Prince Rupert, the “interactivity” does not give details, while there is detailed information on the US projects including “anticipated capital investments, jobs, and export volumes associated with each U.S. site, as well an estimated value of potential exports.”

One of the Kitimat LNG projects plans to self-generate power for liquefaction plant

At least one of the two large liquified natural gas projects in Kitimat is, at least at this point, planning to self-generate the power required using a gas-fired, steam-driven electrical generation system.

A job ad posted this weekend by the headhunting firm Fircroft is seeking a Lead Project Engineer, Power Plant for “Our client, a major international owner/operating company, requires expertise for their LNG mega-project in Western Canada.”

The job, which requires 20 years and more experience, would be located in Calgary for eighteen months, then move to Kitimat for the remainder of a four year contract paying from $1650 to $1850 per day.

By Fircroft describing the job as a “mega-project” means that the client is either Shell’s LNG Canada project or the Chevron and Apache KM LNG project, since the much smaller BC LNG project could not be described as a “mega-project.”

As well as the standard qualifications for a senior engineer, the job posting lists:

• Power Plant design, operation and construction experience required.
• Boiler design, construction, operation, and commissioning experience required.
• Heat Recovery Steam Generation (HRSG) design, processes, construction, operation, and commissioning experience required.
• Integrates inherent safety in design and operability in concept selection and development for gas resource opportunities.

Providing the power for the Kitimat and other northwestern LNG projects is becoming controversial. The power is needed to cool the natural gas so it can be loaded onto tankers for shipment to customers.

The BC government recently announced a $650,000 study of the cumulative effect on air quality for the planned industrial expansion in the Kitimat area, including the Rio Tinto Alcan Kitimat modernization project, which would increase the amount of sulphur dioxide emissions, combined with as many as three LNG projects and the associated increase in tanker traffic, as well as the possible and even more controversial Enbridge Northern Gateway project.

At the time of the BC announcement, the Globe and Mail reported:

If natural gas is used either for direct-drive or combined-cycle electricity generation to produce the energy required for the proposed Shell LNG facility at Kitimat, approximately 300 million cubic feet of natural gas would be burned. The proposed Chevron Apache LNG facility could burn approximately 140 million cubic feet of natural gas.

The other alternative for powering the LNG plants is to use hydro-electricity, and BC Hydro at the moment doesn’t have the capacity to supply the LNG projects with power. One possibility is the controversial Site C dam project in the Peace River basin, which is also under review by the BC government. 

Although the job is restricted to Canadian citizens or permanent residents, it is clear that the engineer will have to also answer to the project’s overseas partners since one requirement is to conduct:  “Overseas VIP workshops, including Value Engineering, Process Simplification, Process Optimization and Design to Capacity.”

As pods recover from whaling, more whales come back to Douglas Channel, researcher believes

 

Fin whale
Fin whale in Squally Channel (Courtesy Chris Picard)

Whales are coming back to Douglas Channel.

In 2013, many Kitimat residents with long experience on the water have reported and are still reporting more sightings of both orcas and humpback whales.

Add to this a recently published scientific study that shows the number of humpbacks at the mouth of the channel near Gil Island has doubled in the past decade, with the study saying there were 137 identifiable whales in 2011.

So why are the whales returning? Chris Picard, Science Director for the Gitga’at First Nation and one of the co-authors of the study believes that answer is simple. There are, so far, three species of whales seen in the area, humpbacks, orcas and fin whales. It is only now, Picard believes, that the humpback and fin whale populations are recovering from a century of whaling.

The study estimates there were once about 15,000 humpback whales in the North Pacific when whalers began hunting the animals. That number was down to 1,400 when whale hunting was stopped in Canada in 1966.

As whale numbers increase, they are searching for the rich food sources found in the Channel, both at the mouth around near Gil Island where the study took place and as far north as the Kildala Arm and Clio Bay.

“One of the things the humpbacks like to do when they are on our coast or the Alaskan coast and that is they feed,” Picard said, “So they are really targeting areas that there is a high density of their preferred prey, krill or herring or other schooling fish, sardines in some years.”

So far the study has concentrated in Gitga’at traditional territory around the mouth of Douglas Channel near Gil Island. Picard says increasing the study area to include more of Douglas Channel is a good idea, but would require more resources than are currently available. “We’d like to continue with the study consistent with the work that we have been doing. Considering what we’re seeing in the local Douglas Channel area, Wright Sound, Gil Island, it can be very worthwhile.

“We are going to continue with our current study which involve getting to know how many humpbacks are using the area and continue with the study that we just published to see if numbers continue to increase or to see whether or if they do start to stabilize at some number,” Picard said. “With more and more proposals for increased shipping, we get to see any changes with humpback numbers that may be linked to increased shipping. We’ll continue to monitor the humpback population; not just their numbers but also their distribution in the area. We’ll continue to monitor that, again in relation to the various shipping proposals and activities that are proposed.”

It was during that study on humpbacks that the researchers from the Gitga’at Nation and the Cetacean Lab noticed the appearance of fin whales, another species that had been hit hard by whaling. (“We’ve worked very closely with the Cetacean Lab group and frankly without their help we would never have published any of this work because their data certainly was instrumental in getting the overall data set that made possible a publishable study,” Picard said.)

“We have observed is that fin whales have increased in their abundance in the area quite a bit, “ Picard said. “I can remember when we first started doing surveys, there were not too many. We’ve gone from seeing a couple over the course of an entire year. Now when we do our marine mammal surveys in the area the fin whales you pretty much see in every survey and in more and more numbers. So it’s quite encouraging to see that fin whales are becoming more abundent in the area. They were also hunted, so if you factor in the days of commercial whaling operations, that of course has stopped, so its encouraging to see that their numbers are coming back too.

The fin whales tend to be found in many of the same areas at the humpack whales are using, Caamaño Sound, Campania Sound and areas south of Gil Island. “we’ve also seen them more in the interior waters like Squally Channel, Wright Sound, Whale Channel, similar to the areas where we see the humpbacks.

“We haven’t done the same level of detailed analysis on the fin whale distribution as we have with the humpback, so it’s just my overall impression that they’re using similar habitats.

“It’s unique for fin whales to be using these more confined waters. It is my understanding that they are more of an open water species. I think that makes the area fairly unique,” he said.
Picard added it would be interesting to do a historic study to see how many fin whales were taken by whalers in the previous decades, especially in Caamaño Sound, Squally Channel and Wright Sound.

“The fact that we saw so many humpbacks relative to the size of the area, which is pretty small relative to the whole coast, so there must be a high abundance of food in the area,” Picard said.

“I’d like to get a better understanding of what is really driving the food abundance in the area. What is the oceanography in the area, what are the currents, what is driving that high area of biological activity that the whales seeming to be homing in on.”

Humpback whale
Humpback whale in the Kildala Arm, September 14, 2013. (Robin Rowland)

That means, Picard believes, that there could be krill and juvenile herring schooling in the upper Douglas Channel and that is what is attracting the whales.

One of the next steps, Picard said, is to study social interaction among whales. “We do take identification photographs, so we get a sense of who’s hanging out with who; who is bringing their calves into the area to introduce them into what seems to be very good whale habitat,” Picard.

So one aim of a future study would be to se what role social interactions play in the increased whale sightings in the Douglas Channel. He also wants to know what role are the potential negative impacts on that whale social interaction comes noise impacts, or being struck by ships, and the potential environmental affects of oil spills. “So do these social interactions decrease as the impacts increase, does that mean there are going to be fewer whales that come into this area? Those are some of the questions we want to address.”

Clio Bay: Clay capping “relatively new technique”: DFO statement

Carrie Mishima, a communications advisor for the Department of Fisheries and Oceans sent this statement in response to questions from Northwest Coast Energy News:

· The proposal by the Kitimat LNG project uses a relatively new technique that is expected to improve aquatic habitat in Clio Bay. The bay has been used as a log handling site for decades, resulting in areas of degraded habitat from woody debris on the seafloor. The project will cap impacted areas with inert material to restore the seafloor.

· Capping at smaller-scale sites in Canada has shown that the technique has successfully restored low-value aquatic habitat.

· The project will implement standard and project-specific measures to protect fish and aquatic habitat and will conduct a five-year monitoring program to determine how well the habitat is recovering.

· Data from the monitoring program will be used to guide future habitat reclamation at impacted habitat sites. Reference sites are being established as benchmarks against which the capped sites can be measured.

· Site-specific standards for dissolved oxygen levels will be developed for the enhanced site by sampling a control site having similar habitat parameters.

· Detailed mapping has been done to identify the best areas for the soil placement and to protect sensitive habitat such as intertidal areas, rocky substrates and eelgrass beds.
· Other required mitigation measures will include analyzing the cap material to confirm it is free of contaminants and placing this material during appropriate tidal conditions to ensure accurate placement of the cap in accordance with design plans.

[rps-include post=5057]

LNG, Clio Bay construction superintendent contract position posted on job sites

A job for a “construction area superintendent” for both the Kitimat LNG plant and the Clio Bay restoration appeared on job sites in the world wide web on October 1.  The posting expires on December 31.

The job was originally posted by Brunel Energy, a consulting firm that describes itself as  a company that  “provides specialist personnel to the international oil & gas, petrochemical, power generation and construction industries.”

The contract job, which, requires 20 years experience and will pay between $1,500 and $2,500 a day, calls for someone who would be “developing project level execution plans for EW&I, LNG Plant & Clio Bay restoration program, and implement/control against these plans in accordance with Project Management System (PMS) processes, procedures and standards.” That superintendent will eventually turn over “functioning facilities to LNG Plant or operations staff.”

As well as standard requirements for a giant construction job of this nature, the requirements include:

• Represent the Company in all interfaces with BC and Kitimat agency associated with EW&I construction activity. Maintaining a positive relationship with the agency by conforming to all regulations and resolving areas of uncertainty in a mutually agreeable manner.
• Maintaining positive relations with the First Nations Haisla representative, recognizing them as a partner and owner of the overall Kitimat LNG Project Development.

Chevron and Apache are partners in the development of the KM LNG project at Bish Cove.