Haisla outline conditions, concerns for Northern Gateway project

Haisla NationIn its extensive document filed with the Northern Gateway Joint Review panel, the Haisla Nation emphasize their opposition to the project.

However, the Haisla are anticipating that the project will be approved and  therefore submitted a lengthy series of conditions for that project, should it be imposed on the northwest by the federal government.

Nevertheless, if the project were to be approved AFTER the Crown meaningfully consulted and accommodated the Haisla Nation with respect to the impacts of the proposed project on its aboriginal title and rights, and if that consultation were meaningful yet did not result in changes to the proposed project, the following conditions would, at a minimum, have to be attached to the project.

 

1. Conditions Precedent: The following conditions precedent should be met prior to any field investigations, pre-construction activities or construction activities as well as during and subsequent to such investigations or activities. These conditions are necessary to ensure that potential effects of the project can be avoided or mitigated to reduce the likelihood of habitat damage or destruction:

Comprehensive seasonal water quality monitoring throughout the Kitimat River watershed, Kitimat Arm and Douglas Channel that account for seasonal variations in flow, tidal cycles, snowmelt, rainfall, etc.

Parameters for measurement would be have to be agreed upon by the
Haisla Nation prior to certification of the project;

Comprehensive seasonal fisheries surveys of fish habitat utilization  throughout the Kitimat River watershed, Kitimat Arm and Douglas Channel that account for where species and life stages are at different times of the year and accurately define sensitive habitats;

Comprehensive seasonal wildlife and bird surveys of habitat utilization throughout the Kitimat River watershed, Kitimat Arm and Douglas Channel that account for where species and life stages are at different times of the year and accurately define sensitive habitats;

Comprehensive seasonal vegetation surveys of habitat utilization throughout the Kitimat River watershed, Kitimat Arm and Douglas Channel that accounts for the distribution of species and life stages at different times of the year and accurately define sensitive habitats;

Development of comprehensive spill response capability based on a realistic assessment of spill containment, spill response and spill capacity requirements throughout the Kitimat River Valley, Kitmat Arm and Douglas Channel. The Haisla Nation’s past experience has shown that relying onpromises is not good enough. This spill response capability must be demonstrated prior to project approval;

Verification that the proposed project would result in real benefits, economic or otherwise, that would flow to the Haisla Nation, to other First Nations, and to British Columbia.

Whenever any field investigations or activities are proposed, the proposal or permit application would have to include the following environmental protections:

Soil and erosion control plans;

Surface water management and treatment plans;

Groundwater monitoring plans;

Control and storage plans for fuels, lubricants and other potential contaminants;

Equipment deployment, access and use plans;

Habitat reclamation of disturbed or cleared areas.

Prior to any pre-construction or construction activities the following detailed studies would have to be undertaken and provided to the Haisla Nation for review and approval, to ensure that the best design and construction approaches are being used, so that potential effects of the project can be avoided or mitigated to reduce the likelihood of habitat damage or destruction:

Detailed analysis of terrain stability and slide potential throughout the pipeline corridor and at the storage tank and terminal site;

Detailed engineering design to mitigate seismic risk and local weather extremes;

.Development of pipeline integrity specifications and procedures including
best practices for leak detection;

Development of storage tank integrity specifications and maintenance and monitoring procedures;

Assessment of spill containment, spill response and spill capacity requirements throughout the Kitimat River watershed, Kitimat Arm and Douglas Channel;

.Development of detailed tanker acceptance program specifications and
procedures;

Development of detailed tanker and tug traffic management specifications and procedures;

Development of detailed port management specifications and procedures including operating limits for tanker operation, movement and docking.

2. Ongoing Consultation: A commitment to ongoing consultation with and accommodation of the Haisla Nation on all of the activities set out above.

3. Ongoing process for variance, waiver or discharge of conditions: A commitment to ongoing meaningful involvement of the Haisla Nation by the National Energy Board prior to any decision on any changes to or sign off on conditions and commitments to any certificate that is issued.

4. Third Party Oversight of Construction: A requirement that NorthernGateway fund a third party oversight committee, which should include a Haisla Nation representative, to monitor certificate compliance during construction of the marine terminal and the pipeline. This committee would have the ability to monitor and inspect construction and should be provided with copies of allcompliance documents submitted by Northern Gateway to the National Energy Board.

5. Operational Conditions: A number of operational conditions should beincorporated into the certificate, including but not limited to:

The requirement to monitor terrain along the pipeline so that breaches based on earth movements can be anticipated and prevented;

The requirement to implement automatic pipeline shutdown whenever a leak detection alarm occurs;

Conditions on the disposal of any contamination that must be removed as a result of an accident or malfunction resulting in a spill that will minimize additional habitat destruction and maximize the potential for regeneration of habitat and resources damaged by the spill;

Parameters for terminal and tanker operations (including standards for tankers allowed to transport cargo; tanker inspection requirements and schedules; escort tug specifications, standards, maintenance and inspection; pilotage protocols and procedures; environmental conditions and operating limits; etc.) as well as other parameters set out in and reliedon for the TERMPOL review to become conditions of any certificate issued by the National Energy Board, with a provision that the Haisla Nation’s approval of any changes to these conditions is required.

Answering the questions from Enbridge Northern Gateway, the Haisla also outline a long series of concerns.

1. Physical and Jurisdictional Impacts

1.1 Construction

The Haisla Nation is concerned about the direct physical and jurisdictional impacts that the construction of the proposed project will have. These concerns are set out for each of the marine terminal, the pipeline, and tanker traffic, below:

Marine Terminal:

a. The proposed marine terminal will require the alienation of 220-275
hectares (554-680 acres) of land from Haisla Nation Territory, land
to which the Haisla Nation claims aboriginal title.

b. The terminal will require the additional alienation of land for
ancillary infrastructure and development, including:

i. road upgrades,

ii. perimeter access roads and roads within the terminal area,

iii. a potential public bypass road,

iv. an impoundment reservoir,

v. a disposal site for excess cut material outside the terminal
area,

vi. a new 10km long transmission powerline, and

vii. a 100-m waterlot with a 150-m “safety zone”.

c. The terminal proposes to use Haisla Nation aboriginal title land,
including foreshore and waters, in a way that is inconsistent with
Haisla Nation stewardship of its lands, waters and resources and
with the Haisla Nation’s own aspirations for the use of this land.
Since aboriginal title is a constitutionally protected right to use the
aboriginal title land for the purposes the Haisla Nation sees fit, this
adverse use would fundamentally infringe the aboriginal title of the
Haisla Nation.

d. The terminal will require the destruction and removal of
documented culturally modified trees, some with modifications
dating back to 1754. These culturally modified trees are living
monuments to the history of the Haisla people.

e. The terminal will expose two Haisla Nation cultural heritage sites to
increased risk of vandalism and chemical weathering.

f. The terminal will result in the direct loss of 4.85 hectares (11.98
acres) of freshwater fish habitat (harmful alteration, disruption or
destruction (HADD) under the Fisheries Act).

g. The terminal will require dredging, underwater blasting, and
placement of piles and berthing foundations, resulting in an as yet
un-quantified loss of intertidal and subtidal marine habitat.

Pipeline:

a. The proposed pipeline construction right-of-way will require the
alienation of 9,200 hectares (22,734 acres) of Haisla Nation
Territory – land to which the Haisla Nation claims aboriginal title –
and will put this land to a use that is inconsistent with Haisla Nation
stewardship of its lands, waters and resources and with the Haisla
Nation’s own aspirations for the use of this land.

b. The pipeline will require 127 watercourse crossings in Haisla Nation
Territory. Seven of these are categorized as high risk, 5 as
medium high risk, and 7 are medium or medium low risk for harmful
alternation, disruption or destruction (HADD) of fish habitat. This
risk is just from pipeline construction and does not address the
issue of spills.

c. The pipeline is estimated to result in temporary or permanent
destruction of freshwater fish habitat of 3.1 hectares (7.68 acres) in
Haisla Nation Territory.

d. The pipeline will require the clearing of land and vegetation and the
destruction of wetlands. The extent of this is yet to be quantified.

Tanker Traffic:

a. Although Northern Gateway has not made any submission on this
point, it is clear that having adequate spill response capability at
Kitimat will require additional infrastructure upgrades in and around
Kitimat, as well as potential spill response equipment cache sites.
None of this has been considered or addressed in Northern
Gateway’s application material – as such the material is
incomplete.

b. The construction for this additional infrastructure could result
impacts to ecosystems, plants, wildlife and fish, and in additional
HADD or fish mortality from accidents.

All of the land alienations required for the proposed project would profoundly
infringe Haisla Nation aboriginal title which is, in effect, a constitutionally
protected ownership right. The proposed project would use Haisla Nation
aboriginal title land in a way that is inconsistent with Haisla Nation stewardship of
its lands, waters and resources and with the Haisla Nation’s own aspirations for
the use of this land. Since aboriginal title is a constitutionally protected right to
use the aboriginal title land for the purposes the Haisla Nation sees fit, this
adverse use would fundamentally infringe the aboriginal title of the Haisla Nation.

The Haisla Nation is also concerned about the socio-economic and health
impacts of the proposed project. Northern Gateway has yet to file its Human
Health and Ecological Risk Assessment. Further, the socio-economic impact
analysis submitted as part of the application provides only a limited assessment
of the potential impacts of the project on the Haisla Nation at a socio-economic
level.

Haisla Nation society and economy must be understood within the cultural
context of a people who have lived off the lands, waters and resources of their
Territory since long before European arrival. To limit a socio-economic impact
assessment to direct impacts and to ignore consequential impacts flowing from
those impacts fails to capture the potential impacts of the proposed project on the
Haisla Nation at a socio-economic level.

1.2 Operation

The proposed marine terminal, pipeline corridor and shipping lanes will be
located in highly sensitive habitats for fish, wildlife and plants. Any accident of
malfunction at the wrong time in the wrong place can be devastating ecologically.
The Haisla Nation has identified the following concerns relating to physical
impacts from the operation of the proposed project:

Marine Terminal:

a. Intertidal and subtidal marine habitat impacts as a result of marine
vessels.
b. The likelihood of spills from the marine terminal as a result of operational
mistakes or geohazards.

c. The effects and consequences of a spill from the marine terminal. This
includes impacts on the terrestrial and intertidal and subtidal marine
environment and fish, marine mammals, birds, and other wildlife, as well
as impacts on Haisla Nation culture and cultural heritage that could result
from such impacts.

d. Response to a spill from the marine terminal, including concerns about
spill response knowledge, planning and capability, as well as impacts
flowing from response measures themselves.

Pipeline:

a. The likelihood of spills from the pipeline as a result of pipeline failure,
resulting from inherent pipeline integrity issues or external risks to pipeline
integrity, such as geohazards.

b. The effects and consequences of a spill from the pipelines. This includes
impacts on the terrestrial environment and freshwater environment, and
on plants, fish, birds, and other wildlife, as well as impacts on Haisla
Nation culture and cultural heritage that could result from such impacts.

c. Response to a spill from the pipelines, including concerns about spill
response knowledge, planning and capability, as well as impacts flowing
from response measures themselves.

Tanker Traffic:

a. Increased vessel traffic in waters used by Haisla Nation members for
commercial fishing and for traditional fishing, hunting and food gathering.

b. The likelihood of spills, including condensate, diluted bitumen, synthetic
crude, and bunker C fuel and other service fuels, from the tankers at sea
and at the marine terminal.

c. The effects and consequences of a spill. This includes impacts on the
marine environment and fish, marine mammals, birds, and other wildlife,
as well as impacts on Haisla Nation culture and cultural heritage that could
result from such impacts.

d. Response to a spill, including concerns about spill response knowledge,
planning and capability, as well as impacts flowing from response
measures themselves.

e. Potential releases of bilge water, with concerns about oily product and
foreign organisms.
These issues are important. They go to the very heart of Haisla Nation culture.
They go to the Haisla Nation relationship with the lands, waters, and resources of
its Territory. A major spill from the pipeline at the marine terminal or from a
tanker threatens to sever us from or damage our lifestyle built on harvesting and
gathering seafood and resources throughout our Territory.

Northern Gateway proposes a pipeline across numerous tributaries to the Kitimat
River. A spill into these watercourses is likely to eventually occur. The evidence
before the Panel shows that pipeline leaks or spills occur with depressing
regularity.

One of Enbridge’s own experiences, when it dumped 3,785,400 liters of diluted
bitumen into the Kalamazoo River, shows that the concern of a spill is real and
not hypothetical. A thorough understanding of this incident is critical to the
current environmental assessment since diluted bitumen is what Northern
Gateway proposes to transport. However, nothing was provided in the application
materials to address the scope of impact, the level of effort required for cleanup
and the prolonged effort required to restore the river. An analysis of this incident
would provide a basis for determining what should be in place to maintain
pipeline integrity as well as what should be in place locally to respond to any spill.

The Kalamazoo spill was aggravated by an inability to detect the spill, by an
inability to respond quickly and effectively, and by an inability to predict the fate
of the diluted bitumen in the environment. As a result, the Kalamazoo River has
suffered significant environmental damage. The long-term cumulative
environmental damage from this spill is yet to be determined.

Further, the Haisla Nation is also concerned about health impacts of the
proposed project and awaits the Human Health and Ecological Risk Assessment
which Northern Gateway has promised to provide.

1.3 Decommissioning

Northern Gateway has not provided information on decommissioning that is detailed enough to allow the Haisla Nation to set out all its concerns about the potential impacts from decommissioning at this point in time. This is not good enough. The Haisla Nation needs to know how Northern Gateway proposes to undertake decommissioning, what the impacts will be, and that there will be financial security in place to ensure this is done properly.

2. Lack of Consultation

 

Broadly, the Haisla Nation has concerns about all three physical aspects of the
proposed project – the pipeline, the marine terminal and tanker traffic – during all
three phases of the project – construction, operation and decommissioning.
These concerns have not been captured or addressed by Northern Gateway’s
proposed mitigation. The Haisla Nation acknowledges that a number of these
concerns can only be addressed through meaningful consultation with the
Crown. The Haisla Nation has therefore repeatedly asked federal decision-
makers to commit to the joint development of a meaningful consultation process
with the Haisla Nation. The federal Crown decision-makers have made it very
clear that they have no intention of meeting with the Haisla Nation until the Joint
Review Panel’s review of the proposed project is complete.

The federal Crown has also stated that it is relying on consultation by NorthernGateway to the extent possible. The federal Crown has failed to provide anyclarity, however, about what procedural aspects of consultation it has delegated to Northern Gateway. Northern Gateway has not consulted with the Haisla Nation and has not advised the Haisla Nation that Canada has delegated any aspects of the consultation process.

The Haisla Nation asserts aboriginal title to its Territory. Since the essence of

aboriginal title is the right of the aboriginal title holder to use land according to its
own discretion, Haisla Nation aboriginal title entails a constitutionally protected
ability of the Haisla Nation to make decisions concerning land and resource use
within Haisla Nation Territory. Any government decision concerning lands,
waters, and resource use within Haisla Nation Territory that conflicts with a
Haisla lands, waters or resources use decision is only valid to the extent that the
government can justify this infringement of Haisla Nation aboriginal title.

The Supreme Court of Canada has established that infringements of aboriginal
title can only be justified if there has been, in the case of relatively minor
infringements, consultation with the First Nation. Most infringements will require
something much deeper than consultation if the infringement is to be justified.
The Supreme Court has noted that in certain circumstances the consent of the
aboriginal nation may be required. Further, compensation will ordinarily be
required if an infringement of aboriginal title is to be justified [Delgamuukw].

The Haisla Nation has a chosen use for the proposed terminal site. This land
was selected in the Haisla Nation’s treaty land offer submitted to British Columbia
and Canada in 2005, as part of the BC Treaty Negotiation process, as lands
earmarked for Haisla Nation economic development.

The Haisla Nation has had discussions with the provincial Crown seeking to
acquire these lands for economic development purposes for a liquefied natural
gas project. The Haisla Nation has had discussions with potential partners about
locating a liquefied natural gas facility on the site that Northern Gateway
proposes to acquire for the marine terminal. The Haisla Nation sees these lands
as appropriate for a liquefied natural gas project as such a project is not nearly
as detrimental to the environment as a diluted bitumen export project. This use,
therefore, is far more compatible with Haisla Nation stewardship of its lands,
waters and resources.

By proposing to use Haisla Nation aboriginal title land in a manner that is
inconsistent with Haisla Nation stewardship of its lands, waters and resources,
and that interferes with the Haisla Nation’s own proposed reasonable economic
development aspirations for the land, the proposed project would result in a
fundamental breach of the Haisla Nation’s constitutionally protected aboriginal
title.

Similarly, Haisla Nation aboriginal rights are constitutionally protected rights to
engage in certain activities (e.g. hunting, fishing, gathering) within Haisla Nation
Territory. Government decisions that infringe Haisla Nation aboriginal rights will
be illegal unless the Crown can meet the stringent test for justifying an
infringement.
Main story Haisla Nation confirms it opposes Northern Gateway, demands Ottawa veto Enbridge pipeline; First Nation also outlines “minimum conditions” if Ottawa approves the project

Haisla Nation Response to NGP Information Request  (pdf)

Haisla Nation confirms it opposes Northern Gateway, demands Ottawa veto Enbridge pipeline; First Nation also outlines “minimum conditions” if Ottawa approves the project

Haisla NationThe Haisla Nation has confirmed in a filing with the Northern Gateway Joint Review Panel that it opposes the Enbridge Northern Gateway project.

The document, filed June 29, 2012, is one of the most significant filed with the JRP during all the years of the debate over the controversial Northern Gateway, setting out a three stage process that will govern, whether Enbridge or the federal government like it or not, the future of the Northern Gateway pipeline project.

First, the Haisla Nation affirms that it opposes the Northern Gateway project

Second, the Haisla Nation is demanding that the federal government, in recognition of aboriginal rights and title, reject the Northern Gateway project on Haisla traditional territory.

Third, probably anticipating that Stephen Harper and his government will attempt to force the Northern Gateway on British Columbia, the Haisla are demanding meaningful consultation and set out a stringent set of minimum conditions for the project on Haisla traditional territory.

The Haisla Nation’s lawyers filed the document today late today, June 29, in response to a series of questions posed to the First Nation by Enbridge through the Joint Review process.

The Haisla also say that there already projects that are better suited to their traditional territory, the liquified natural gas projects.

The Haisla position that Ottawa must reject the pipeline if First Nations oppose it is the opening round in the constitutional battle over not just the pipeline, but entire question of aboriginal rights and title. So far the government of Stephen Harper has said that First Nations do not have a “veto” on the pipeline and terminal project.

The Haisla also refuse to answer questions that Enbridge posed on the liquified natural gas projects because the filing argues, the questions are beyond the scope of the current Joint Review inquiry.


Detailed excerpts

Haisla outline where they believe Enbridge Gateway plans are inadequate

Haisla outline conditions, concerns for Northern Gateway project

 


 

Why the Haisla oppose Northern Gateway

In the filing with the Joint Review panel, the Haisla outline nine reasons for opposition to the Northern Gateway project:

1. Northern Gateway is proposing to site its project in a location that places at risk the ecological integrity of a large portion and significant aspects of Haisla Nation Territory and resources.

2. All three aspects of the proposed project – the pipelines, the marine terminal and tankers – have the potential to impact Haisla Nation lands, waters and resources.

3. Northern Gateway has neither conducted sufficient due diligence nor provided sufficient information with respect to the assessment of a number of critical aspects of the proposed project, including but not limited to project design, impacts, risks, accidents and malfunctions, spill response, potential spill consequences and the extent, degree and duration of any significant adverse environmental effects.

4. There are significant risks of spills of diluted bitumen, synthetic crude, and condensate from corrosion, landslide hazards, seismic events along the pipeline route and at the terminal site; as well asloss of cargo or service fuels from tanker accidents, with no realistic plan provided for spill containment, cleanup, habitat restoration or regeneration of species dependent on the affected habitat.

5. Diluted bitumen, synthetic crude and condensate are all highly toxic to the environment and living systems and the consequences and effects of a spill could be devastating on the resources that support the Haisla Nation way of life, and would therefore have significant adverse effects on Haisla Nation culture and cultural heritage and aboriginal rights.

6. Risk assessments and technology have not overcome the potential for human error, wherein it is well established that 80% of oil tanker accidents that cause oil spills at sea are a result of human errors: badly handled manoeuvres, neglected maintenance, insufficient checking of systems, lack of communication between crew members, fatigue, or an inadequate response to a minor incident
causing it to escalate into a major accident often resulting in groundings and collisions (http://www.black-tides.com/uk/source/oil-tanker-accidents/causes-accidents.php). It has also become increasingly obvious that maintenance of pipeline integrity and the remote detection of pipeline ruptures is inadequate as exemplified by major environmental damage from recent pipeline ruptures in Michigan and Alberta.

7. The proposed project requires the alienation of Haisla Nation aboriginal title land, and the federal government has refused to engage in consultation with the Haisla Nation about the potential impacts of the proposed project on Haisla Nation aboriginal rights, including aboriginal title.

8. The proposed project would require the use of Haisla Nation aboriginal title land for a purpose that is inconsistent with Haisla Nation stewardship principles and with the Haisla Nation’s own aspirations for this land.

9. For the reasons set out above, the proposed project would constitute an unjustified infringement of Haisla Nation aboriginal title and rights. It would therefore be illegal for the Crown to authorize the project.

Canada is obliged to decline approval of the project

Up until now, the federal government has refused to engage First Nations in the northwestern region over the issue of the Northern Gateway pipeline and terminal, saying that the constitutionally mandated consultation will take place after the Joint Review Panel has released its report. However, the government’s Bill C-38, which gives the federal cabinet (actually the prime minister) the power to decide the pipeline means that the JRP report will be less significant than it would have been before the Conservatives gained a majority government in May, 2010.

The Haisla say the nation has “repeatedly requested early engagement by federal government decision-makers to develop, together with the Haisla Nation, a meaningful process for consultation and accommodation in relation to the proposed project.”

The filing says JRP and “the federal government’s ‘Aboriginal Consultation Framework’ have been imposed on the Haisla Nation and other First Nations, with significant aspects of the concerns expressed by the Haisla Nation about this approach being ignored.”

The Haisla says it “continues to seek a commitment from the federal government to the joint development of a meaningful process to assess the proposed project and its potential impacts on Haisla Nation aboriginal rights, including aboriginal title.”

Later in the filing the Haisla say:

The Haisla Nation has…  repeatedly asked federal decision-makers to commit to the joint development of a meaningful consultation process with the Haisla Nation. The federal Crown decision-makers have made it very clear that they have no intention of meeting with the Haisla Nation until the Joint Review Panel’s review of the proposed project is complete…

The federal Crown has failed to provide any clarity, however, about what procedural aspects of consultation it has delegated to Northern Gateway. Northern Gateway has not consulted with the Haisla Nation and has not advised the Haisla Nation that Canada has delegated any aspects of the consultation process.

The Haisla then go on to say:

Canada is legally required to work with the Haisla Nation to develop and follow such a process. If the process establishes that the approval of the proposed project would constitute an unjustified infringement of Haisla Nation aboriginal rights or aboriginal title, then Canada would be legally obliged to decline approval.

Deficiencies and Conditions

Enbridge asked the Haisla that if there are conditions of approval that would nonetheless
address, in whole or in part, the Nation’s concerns; and then asked for details “on the nature of any conditions that the Haisla Nation would suggest be imposed on the Project, should it be approved.”

The Haisla reply that because there are “significant deficiencies in the evidence provided by Northern Gateway to date.” The nation goes on to say that “the acknowledged risks that have not been adequately addressed in the proposed project.” The Haisla Nation then says it “does not foresee any conditions that could be attached to the project as currently conceived and presented that would eliminate the Haisla Nation’s concerns.”

The Haisla then repeat that Enbridge has not provided sufficient information so that

it is difficult for the Haisla Nation to identify conditions to attach to the proposed project as it is still trying to fully understand the potential impacts of the project and the proposed mitigation. This is primarily because there is insufficient information provided by Northern Gateway in its application material.

Although we have attempted to elicit additional information through the JRP’s information request process, Northern Gateway has not provide adequate and complete answers to the questions posed.

The Haisla then anticipate that Stephen Harper will force the pipeline and terminal on British Columbia and say:

Nevertheless, if the project were to be approved AFTER the Crown meaningfully
consulted and accommodated the Haisla Nation with respect to the impacts of
the proposed project on its aboriginal title and rights, and if that consultation were
meaningful yet did not result in changes to the proposed project, the following
conditions would, at a minimum, have to be attached to the project.

The emphasis of the word “after” is in the original document.

The document that then goes on to present an extensive list of list of conditions the Haisla believe should be imposed on the Enbridge Northern Gateway if the project goes ahead.

The conditions include comprehensive monitoring of water quality, fisheries, wildlife and birds, vegetation throughout the Kitimat River watershed, Kitimat Arm and Douglas Channel; development of comprehensive spill response capability throughout the Kitimat River Valley, Kitmat Arm and Douglas Channel.

The Haisla also want soil and erosion control plans; water management plans; control and storage plans for fuels, lubricants and other potential contaminants; detailed plans for equipment deployment and habitat reclamation of disturbed or cleared areas.

The Haisla also want much more detailed studies before any construction, including analysis of terrain stability and slide potential throughout the pipeline corridor and at the storage tank and terminal site; engineering designs to mitigate seismic risk and local weather extremes; development of pipeline integrity specifications and procedures including best practices for leak detection; storage tank integrity specifications, maintenance and monitoring; assessment of spill containment, spill response and spill capacity requirements throughout the Kitimat River watershed, Kitimat Arm and Douglas Channel.

On tankers the Haisla want more details beyond the plans already filed by Enbridge including
detailed tanker specifications, detailed tanker and tug traffic management procedures; detailed port management specifications and procedures including operating limits for tanker operation, movement and docking.

The Haisla are also demanding “on going consultation” on all issues involved by the National Energy Board prior to any decision on any changes to or sign off on conditions and commitments to any certificate that is issued.

The Haisla want an independent third party be part of a committee to oversee the construction proecess to monitor certificate compliance during construction of the marine terminal and the pipeline.

Once the pipeline and terminal operational, the Haisla want conditions imposed on the project that include ongoing monitoring of the terrain along the pipeline, a system that would automatically shut down the pipeline shutdown whenever a leak detection alarm occurs.

The Hasila want conditions “on the disposal of any contamination that must be removed as
a result of an accident or malfunction resulting in a spill that will minimize additional habitat destruction and maximize the potential for regeneration of habitat and resources damaged by the spill.”

As well as more detailed parameters for the tankers, tugs, and pilotage procedures, the Haisla want approval of any future changes in those procedures.

The Haisla are also concerned about the “alienation” of a large area of their traditional territory by the construction of the Northern Gateway project as well as the “additional infrastructure” required by adequate spill response capability and spill response equipment cache sites.

The Haisla say “all of the land alienations required for the proposed project would profoundly
infringe Haisla Nation aboriginal title which is, in effect, a constitutionally protected ownership right” and goes on to say “proposed project would use Haisla Nation aboriginal title land in a way that is inconsistent with Haisla Nation stewardship of its lands, waters and resources and with the Haisla Nation’s own aspirations for the use of this land.”

The Haisla filing then goes on to say:

Since aboriginal title is a constitutionally protected right to use the aboriginal title land for the purposes the Haisla Nation sees fit, this adverse use would fundamentally infringe the aboriginal title of the Haisla Nation.

The report also expresses concerns about the ongoing socio-economic affects of such a large project.

It concludes by saying:

These issues are important. They go to the very heart of Haisla Nation culture.
They go to the Haisla Nation relationship with the lands, waters, and resources of
its Territory. A major spill from the pipeline at the marine terminal or from a
tanker threatens to sever us from or damage our lifestyle built on harvesting and
gathering seafood and resources throughout our Territory.

Northern Gateway proposes a pipeline across numerous tributaries to the Kitimat
River. A spill into these watercourses is likely to eventually occur. The evidence
before the Panel shows that pipeline leaks or spills occur with depressing
regularity.

One of Enbridge’s own experiences, when it dumped 3,785,400 liters of diluted
bitumen into the Kalamazoo River, shows that the concern of a spill is real and
not hypothetical. A thorough understanding of this incident is critical to the
current environmental assessment since diluted bitumen is what Northern
Gateway proposes to transport. However, nothing was provided in the application
materials to address the scope of impact, the level of effort required for cleanup
and the prolonged effort required to restore the river. An analysis of this incident
would provide a basis for determining what should be in place to maintain
pipeline integrity as well as what should be in place locally to respond to any spill.

The Kalamazoo spill was aggravated by an inability to detect the spill, by an
inability to respond quickly and effectively, and by an inability to predict the fate
of the diluted bitumen in the environment. As a result, the Kalamazoo River has
suffered significant environmental damage. The long-term cumulative
environmental damage from this spill is yet to be determined.

Looking to the future, the Haisla are also asking for a plan for the eventual decommissioning of the project, pointing out that “ Northern Gateway has not provided information on decommissioning that is
detailed enough to allow the Haisla Nation to set out all its concerns about the
potential impacts from decommissioning at this point in time.”

Haisla leaders have already expressed concern about the legacy of the Eurocan paper plant. Now it tells Enbridge

This is not good enough. The Haisla Nation needs to know how Northern Gateway proposes to undertake decommissioning, what the impacts will be, and that there will be financial security in place to ensure this is done properly.

Asserts aboriginal title

The section of the report concludes by saying:

The Haisla Nation asserts aboriginal title to its Territory. Since the essence of
aboriginal title is the right of the aboriginal title holder to use land according to its
own discretion, Haisla Nation aboriginal title entails a constitutionally protected
ability of the Haisla Nation to make decisions concerning land and resource use
within Haisla Nation Territory. Any government decision concerning lands,
waters, and resource use within Haisla Nation Territory that conflicts with a
Haisla lands, waters or resources use decision is only valid to the extent that the
government can justify this infringement of Haisla Nation aboriginal title.

The Supreme Court of Canada has established that infringements of aboriginal
title can only be justified if there has been, in the case of relatively minor
infringements, consultation with the First Nation. Most infringements will require
something much deeper than consultation if the infringement is to be justified.
The Supreme Court has noted that in certain circumstances the consent of the
aboriginal nation may be required. Further, compensation will ordinarily be
required if an infringement of aboriginal title is to be justified [Delgamuukw].

The Haisla then go on to say that the preferred use of the land in question is for the liquified natural gas projects:

The Haisla Nation has a chosen use for the proposed terminal site. This land
was selected in the Haisla Nation’s treaty land offer submitted to British Columbia
and Canada in 2005, as part of the BC Treaty Negotiation process, as lands
earmarked for Haisla Nation economic development.

The Haisla Nation has had discussions with the provincial Crown seeking to
acquire these lands for economic development purposes for a liquefied natural
gas project. The Haisla Nation has had discussions with potential partners about
locating a liquefied natural gas facility on the site that Northern Gateway
proposes to acquire for the marine terminal. The Haisla Nation sees these lands
as appropriate for a liquefied natural gas project as such a project is not nearly
as detrimental to the environment as a diluted bitumen export project.

Northwest Coast Energy News is attempting to contact Enbridge Northern Gateway for comment on the Haisla filing. Response may be delayed by the Canada Day holiday.

 

Haisla Nation Response to NGP Information Request  (pdf)

The Empire Strikes Back I: Enbridge takes on First Nations, small intervenors

Douglas Channel
Douglas Channel at the site of the proposed Enbridge marine terminal, June 27, 2012. (Robin Rowland/Northwest Coast Energy News)

Enbridge is striking back against the First Nations and intervenors who oppose the Northern Gateway pipeline and marine terminal projects by filing questions that those groups must answer as part of the Joint Review Process.

On May 11, 2012, Enbridge filed questions with 24 organizations,  and from the questions, it appears that Enbridge isn’t  just building a strictly legal case in their favour but are preparing to try and discredit opponents.

Enbridge’s questions are part of the legal process. For months, First Nations and intervenors have been filing a whole series of questions asking for clarification of items in the Enbridge’s filings on the project with Joint Review Process and Enbridge has the legal right to ask the First Nations and intervenors to clarify their positions.

However, the difference is that Enbridge is a giant corporation which can afford to spend millions of dollars on both the approval process as well as the current nationwide advertising process, while some of the intervenors are made up of volunteers or retirees working on their own time. Sources among the intervenors have been saying for months that they believe that Enbridge is following a perceived policy of working to wear down the opponents so much they burn out and drop out of the process.

A large proportion of the questions Enbridge is demanding that First Nations and intervenors answer are overtly political, rather than technical responses to their filings.

In an apparent escalation of its campaign against its opponents, Enbridge is using the Joint Review process to ask intervenors about funding, naming such hot button organizations such as Tides Canada, which is under attack by the Harper government.  Enbridge is also  questioning  the “academic credentials” of numerous intervenors and commenters, even though the Joint Review Panel has spent most of the past seven months asking people to comment based on “local knowledge,” leaving the technical questions to the documents filed with the JRP

Some key questions directed at both the Haisla and Wet’suwet’en First Nations seem to indicate that Enbridge is preparing to build both a legal and probably a public relations case questioning the general, but not unanimous support for liquified natural gas projects in northwestern BC, by saying “Why not Northern Gateway,” as seen in this question to the Haisla Nation.

Please advise as to whether similar measures would be requested by the Haisla First Nation to deal with construction-related impacts of the Northern Gateway Project.

Black Swan

A series of questions to the coalition known as the Coastal First Nations questions the often heard assertion that an oil spill on the BC coast is “inevitable,” and Enbridge appears to be prepared to argue that spills are not inevitable. Enbridge asks Coastal First Nations about a study that compared the bitumen that could be shipped along the coast with the proposed LNG projects.

Please provide all environmental and risk assessment studies, including studies of “Black Swan” events, conducted by the Coastal First Nations or any of its members in respect of the LNG projects referred to.

Enbridge is referring to Nassim Nicholas Taleb’s now widely known “theory of high-impact, hard-to-predict, and rare events that are beyond the realm of normal expectations in history, science, finance and technology.”

It is Black Swan events that most of the people of the northwest coast fear when it comes to all the major energy projects, but if as Taleb says they are hard-to-predict and rare, how can the studies Enbridge is requesting actually predict those disasters?

Enbridge’s questions to the Haisla Nation runs for 28 pages and many of those questions are political, not technical, including asking for details of the Haisla support for the various Kitimat liquified natural gas projects and who may be funding the Haisla participation in the Joint Review Process. Many technical questions around the questions of “acceptable risk” and it appears, despite the fact Enbridge officials have listened to the Haisla official presentation at Kitamaat Village last January and the speeches of Haisla members this week at the pubic comment hearings, that Enbridge is preparing to use a paper-based or Alberta-based concept of acceptable risk as opposed to listening to the First Nation that will be most directly affected by any disaster in the Kitimat harbour or estuary.

(See The Enbridge Empire Strikes Back II The Haisla “fishing expedition”)

A series of questions seems to negate Enbridge’s claim that it has the support of many First Nations along the pipeline route because Enbridge is asking for details of agreements that First Nations have reached with the Pacific Trails Pipeline. Enbridge has consistently refused to release a list of the First Nations it claims has agreements with the company, but in the questions filed with the JRP, Enbridge is asking for details of agreements First Nations in northern BC have reached with the Pacific Trails Pipeline.

Funding demands

For example, while Enbridge is refusing to name all the backers of the pipeline for reasons of corporate confidentiality, the company is asking who may be funding the Wet’suwet’en First Nation in its appearances before the Joint Review Panel, including the US-based foundations named by right-wing blogger Vivian Krause,  (note Krause recently declared victory and suspended her blog) right-wing columnists and the Harper cabinet:

Please confirm that the Office of the Wet’suwet’en has received participant funding from the Canadian Environmental Assessment Agency to participate in the Joint Review Panel (“JRP”) proceeding.

Please advise as to the amount of participant funding received to date from the Canadian Environmental Assessment Agency.

Please advise whether or not the Office of the Wet’suwet’en has received funding within the
last 5 years from Tides Canada, the Gordon and Betty Moore Foundation, the William and Flora Hewlett Foundation, or any other similar foundations, to oppose the Northern Gateway Project or to oppose oil sands projects in general.

If so, please provide the amount of funding received from each foundation.

In the case of the Raincoast Conservation Foundation, Enbridge is asking for details, including a membership list.

Please provide a description of the Raincoast Conservation Foundation.

Does the Raincoast Conservation Foundation prepare Annual Reports? If so, please provide the most recently published Annual report available.

If the Raincoast Conservation Foundation is a collection of like-minded individuals, please list its members.

Did the Raincoast Conservation Foundation apply for and receive participant funding in this proceeding? If so, how much was received?

While many of Enbridge’s question to the RainCoast Foundation are technical, the company which is currently conducting a multi-million dollar public relations campaign in favour of the pipeline, asks:

Please confirm that the “What’s at Stake? study” was prepared for use as a public relations tool, to advocate against approval of the Northern Gateway.

Enbridge also appears to be gearing up for personal attacks on two of the most vocal members of Kitimat’s Douglas Channel Watch, Murray Minchin and Cheryl Brown, who have been appearing regularly before District of Kitimat council to oppose the Northern Gateway pipeline.

 

Murray Minchin
Murray Minchin of Douglas Channel Watch addresses protesters at Kitimat City Centre Mall, Sunday, June 24, 2012, He talked about how he has learned as he goes along in examining Enbridge documents (Robin Rowland/Northwest Coast Energy News)

Credentials

On Murray Minchin, Enbridge asks:

Written Evidence Regarding Proposed Liquid Petroleum Pipelines from the proposed Nimbus Mountain West Portal to the Kitimat River Estuary submitted by Murray Minchin of Douglas Channel Watch…. Supplemental Written Evidence Photographic Evidence Regarding Proposed Liquid Petroleum Pipelines from Nimbus Mountain to the Kitimat River Estuary submitted by Murray Minchin of Douglas Channel Watch….

Mr. Minchin provides extensive opinion relative to geotechnical and other technical matters. Request: Please provide Mr. Minchin’s curriculum vitae which includes his education, training and employment history, to demonstrate his qualifications to provide geotechnical and other technical opinions that appear….

Minchin is one of Enbridge’s strongest opponents in Kitimat and in his various appearances (the latest at the anti-Enbridge demonstration in Kitimat on Sunday, June 24, 2012, Minchin has told the audiences that he is self-taught and has spent much of his spare time over the past few years studying the documents Enbridge has filed with the JRP.

As for Cheryl Brown, a vocal critic of the Enbridge Community Advisory Board process, Enbridge has filed a long series of questions about her involvement with the CAB, including asking how many meetings she has attended (see document below)

Two of Enbridge’s questions about Brown stand out

Has Ms. Brown offered a suggestion for a speaker that would have provided a differing viewpoint from those of Northern Gateway?

Many people in Kitimat, not just the outspoken members of Douglas Channel Watch, say they do not trust the Community Advisory Board process. When the CAB held a meeting recently to discuss marine safety, a meeting that was heavily advertised in Kitimat Terrace area, the CAB facilitators ( from a Vancouver -based company) attempted to bar the media, including this reporter, from this “public” meeting, until apparently overruled by Enbridge’s own pubic relations staff. On the other hand, everytime Douglas Channel Watch has appeared before the District of Kitimat Council to request a public forum on Gateway issues, DCW has always insisted that Enbridge be invited to any forum, along with DCW and independent third parties.

Ms. Brown states that Enbridge has not addressed the hard questions. Please confirm that Northern Gateway responded to questions put forth by the Douglas Channel Watch in Letters to the Editor in both the Kitimat Northern Sentinel and Terrace Standard in August of 2009.

Here Enbridge appears to be basing its case on one letter to the editor that appeared in local papers three years ago. During the public comment hearings that the JRP held at Kitamaat Village earlier this week, numerous people testified time and time again that Enbridge was failing to answer major questions about the pipeline and terminal, by saying that those questions would be answered later, once the project is approved.

Bird watching

In one series of questions, Enbridge is demanding a professional level database from the Kitimat Valley Naturalists, the local birdwatching group. Quoting a submission by the naturalists group, Enbridge asks

Paragraph 2.2, indicates that the Kitimat Valley Naturalists has birding records for the estuary for over 40 years and that Kitimat Valley Naturalists visits the estuary at least 100 times per year.

Paragraph 2.3 indicates the Kitimat Valley Naturalists have local expertise in birds of the Kitimat River estuary as well as other plants and animals that utilize those habitats.

Request: To contribute to baseline information for the Kitimat River estuary and facilitate a detailed and comprehensive environmental monitoring strategy, please provide the long term database of marine birds in and adjacent to the Kitimat River estuary, with a focus on data collected by the Kitimat Valley Naturalists in recent years, and where possible, the methodology or survey design, dates, weather and assumptions for the data collection.

Today the Kitimat Valley Naturalists, three local retirees, Walter Thorne, Dennis Horwood and April Macleod filed this response with the JRP:

Northern Gateway has specifically requested the long-term database of birds occurring over many years within the Kitimat River Estuary. The data we have collected includes monthly British Columbia Coastal Water Survey (BC CWS) and yearly Christmas Bird Counts (CBC). The data from
these bird counts are available on the web or in print form.

For access to BC CWS enter http://www.bsc-eoc.org

For access to CBC data, enter http://birds.audubon.org

Historical results for CBC counts have also been published by the journal American Birds. The earliest CBC count for Kitimat was 1974.

In regard to the long-term database, we have significant numbers of records for the foreshore of the Kitimat River Estuary. The number increases when the larger estuary perimeter is considered. These cover a 40-year period with the majority in the last 20 years. We would be willing to provide this information in a meaningful format.

The Kitimat Valley Naturalists, however, lack the expertise or financial ability to convert the data into a format that would address Northern Gateway’s interest in methodology, survey design, dates, weather, and assumptions for data collection.

Alternatively, we do have access to a consulting firm, which is willing to analyze our data and convert it to a useable and practical design. We assume, since this is a considerable undertaking in both time and cost, that Northern Gateway would be willing to cover the associated fees.

We look forward to hearing back from Northern Gateway and pursuing this with a budget proposal.

Northwest Coast Energy News consulted data management experts who estimated that complying with the Enbridge request would likely cost between $100,000 and $150,000.

First Nations

Some Wet’suwet’en houses have opposed the Pacific Trails Pipeline, and while negotiations with Apache Corporation are continuing, Enbridge is asking the First Nation for details of what is happening with that pipeline.

Is it the position of the Office of the Wet’suwet’en that each First Nation whose traditional territory is traversed by the proposed pipeline has a veto on whether it is approved or refused?

Please confirm that the Office of the Wet’suwet’en opposed approval of the Pacific Trails Pipeline (also known as the Kitimat Summit Lake Looping Project).

Does the Office of the Wet’suwet’en continue to oppose construction of the Pacific Trails Pipeline?

Have the First Nations who are proposing to participate as equity owners in the Pacific Trails Pipeline Project advised the Office of the Wet’suwet’en that they accept that the Office of the Wet’suwet’en has a right to veto approval and construction of that Project?

Please confirm that the First Nations holding an equity ownership position or entitlement in the Pacific Trails Pipeline Project (also known as the Kitimat-Summit Lake Looping Project) include:
• Haisla First Nation
•Kitselas First Nation
•Lax Kw’alaams Band
•Lheidli T’enneh Band
•McLeod Lake Indian Band
•Metlakatla First Nation
•Nadleh Whut’en First Nation
•Nak’azdli Band
•Nee Tahi Buhn Band
•Saik’uz First Nation
•Skin Tyee First Nation
•Stellat’en First Nation
•Ts’il Kaz Koh First Nation
•West Moberly First Nation
•Wet’suwet’en First Nation

The majority of questions filed with the Coast First Nations are technical challenges to studies filed by the coalition. Enbridge also filed questions with the Gitga’at, Gitxaala, Heiltsuk Nations and the Metis Nation of Alberta.

(Disclosure: The author, who is also a photographer, sometimes accompanies members of the Kitimat Valley Naturalists to photograph birds during the time they are doing the counts)

Enbridge Cover letter to JRP Information Requests to Intervenors (pdf)

Information Request Coastal First Nations (pdf)

Information Request Haisla (pdf)

Information Request Douglas Channel Watch (pdf)

Information Request Living Oceans Society (pdf)

Information Request Raincoast Conservation (pdf)

Information Request Wet’suwet’en (pdf)

Information Request Kitimat Valley Naturalists (pdf)

Kitimat Valley Naturalists response to Enbridge (pdf)

 

First Nations, environmentalists and ‘rednecks’ stand together opposing Gateway, witness tells Kitimat JRP hearings

 

Members of the Joint Review panel make notes at Kitamaat Village (Robin Rowland)
Members of the Northern Gateway Joint Review Panel, left to right, Kenneth Bateman, chair Sheila Leggett and Hans Matthews make notes at the June 25, 2012 hearings at the Haisla Recreation Centre, Kitamaat Village. A map of Douglas Channel can be seen behind the panel. (Robin Rowland/Northwest Coast Energy News)

“This will be the first project in Canadian history to have First Nations, environmentalists and, for a lack of a better term, rednecks standing together in protest,” that sentence from Katherina Ouwehand summed up the first day of public comment testimony Monday, June 25, 2012, as the Northern Gateway Joint Review Panel returned to the Haisla Recreation Centre at Kitamaat Village.

Ten minutes isn’t that long. Ten minutes is the time that the Northern Gateway Joint Review Panel gives a member of the public to express their opinion on the controversial Enbridge project that would pipe oil sands bitumen from Alberta through the port of Kitimat to Asia.

Ten minutes is sufficient if you know what you’re talking about, if you’ve done your homework and rehearsed presentation so it can comes in right on time.

Ten minutes can be eternity if you’re an Enbridge official sitting silently at a nearby table as people who do know what they’re saying tear apart your public presentations, your multi-million dollar ads and the thousands of pages the company has filed with the Joint Review Panel. Or perhaps, as some at the public comment hearings pointed out, those ten minutes mean little if Prime Minister Stephen Harper has already decided the pipeline will go ahead no matter what, and thus any recommendation from the JRP has little credibility.

The first witness to appear before the public comment hearings on Monday afternoon was someone who knows all about the role of human error in accidents, Manny Aruda, an Emergency Response Team leader at the Rio Tinto Alcan smelter.

Aruda began by commenting, “To be clear, I do not belong to any environmental or radical organization, although I do recycle and occasionally I do eat granola.” His responsibilities at RTA include overseeing anything related to an emergency response, including dealing with spills and reporting the spills. Before that he worked at Methanex first in operations as a field operator and then as an ammonia control room operator. He also volunteers as a Search Manager for Kitimat Search and Rescue.

Talking about his time in the control room at Methanex, Aruda said, “I worked in the state-of-the-art chemical plant which is constantly being updated with the newest instrumentation. No matter how many safety features are in place, human error could supersede. Incorrect wires were cut causing plants to shut down; drain lines were left open during start-up causing methanol to go into the effluent system and eventually into the ocean; pigs [robots that operate inside pipes] are used to clean pipelines that were supposed to be collected at the end of a line at the wharf, and over-pressurizing of the line and mental error, leaving a valve open and the next thing you know pigs really do fly right into the ocean.

“Enbridge has spoken many times about how they’ll use smart pigs. Perhaps their smart pigs will know when to put the brakes on and stop.

Humans weak link

“The bottom line is that no matter what state-of-the-art infrastructure, instrumentation, safety

Manny Aruda
Manny Aruda takes some water after testifying before the Northern Gateway Joint Review Panel at Kitamaat Village, June 25, 2012. (Robin Rowland/Northwest Coast Energy News)

measures are in place human decisions or lack of decisions will affect the outcome. Humans are the weak link.

“There is an enormous pressure from management to keep plants and pipelines running. Control room operators are most at risk on start-ups and shutdowns, when conditions are changing rapidly. When a suspected issue arises it requires interpretation and analytical skills. These skills are relative to the amount of knowledge and experience of the individual.

“When in the control room you can’t see, hear or smell what’s going on outside, this is why the field operator is so valuable and utilized to go out in the field to verify a level, check a pump status, a pressure reading, identify leaks, et cetera.

Despite what some people may believe, it’s not black and white. There’s not a red Staples easy button flashing indicating that a spill is happening.

“When in the control room you can’t see, hear or smell what’s going on outside, this is why the field operator is so valuable and utilized to go out in the field to verify a level, check a pump status, a pressure reading, identify leaks… Despite what some people may believe, it’s not black and white. There’s not a red Staples easy button flashing indicating that a spill is happening.”
Any deviation from normal operations is subject to interpretation by the control room operator, “a human, the weak link,” Aruda said. He added: “Industry can continue to make improvements and make things more and more idiot-proof. History has shown that better idiots will come along.”

He told the JRP that the long Northern Gateway pipeline through remote mountain passes would have no field operators available to check every kilometre of the line to verify what the control room operator thinks is happening.

Like other witnesses, Aruda pointed to the Enbridge spill at Marshall, Michigan, where four million litres were spilled into a river in a populated area. “The spill went unnoticed due to human error,
the weak link.”

He testified that he has spent “hundreds of hours looking at Enbridge’s risk assessment,
management of spills, emergency response,” and then he said from the point of view of an
emergency response team leader, “reading these documents has flabbergasted me.” He said Enbridge’s risk management was “seriously deficient and woefully lacking in substance. They do not take into consideration the rugged terrain, the climatic conditions and dangers of fast flowing moving water.”

He said Talmadge Creek that feeds the Kalamazoo River, the location of the spill in Michigan, flows at much slower rate than the Kitimat River. At Kalamazoo, he said, four million litre oil spill moved 39 miles downstream contaminating everything in its path and it was contained two days later.

“It took Enbridge two days to deal with a meandering Kalamazoo River spill. Enbridge has stated in their risk assessment and management of spills they can contain a spill in the Kitimat River within two to four hours. This is irresponsible and inaccurate statement with no associated details.

It rains a lot in Kitimat

“To be fair, the Marshall spill happened at the worst possible time when the Kalamazoo River flows were at flood stage, causing oil to be deposited high on marshes and banks. This caused widespread contamination in the area. The Kitimat area also has high periods of flows and flood stages. It’s called, May, June, September, October and November. I’m not sure if you’re aware, but it rains here, a lot.

“In a worst-case scenario for the Kitimat River, Aruda said, based on events of September 2011, “heavy rain caused a dramatic increase in river levels within 24 hours. This is a normal occurrence. And the river widens by 75 yards in some locations. I have personally witnessed tree after tree, including 100 foot trees with full root balls 20-feet in diameter barrelling down this river. The Kitimat River flow at that time, 72,000 cubic feet a second, [was] some 18 times more than the Kalamazoo River. There’s not one qualified incident commander that would even consider sending out emergency responders into that raging river.”

He said that even during a moderate rise of the river, booms are not effective because of all the debris floating down the river.

Aruda said, “I invite anyone who thinks this oil spill can be cleaned up effectively to drift down the river with me to see for themselves how impossible a task that would be.” He noted that Enbridge has spent $765 million in clean-up costs, and while some parts of the Kalamazoo River have recently been opend for recreational use, other parts remain closed for clean-up.

He repeated his belief that Enbridge’s response plans are insufficient and concluded by saying, “Other pipelines and transmission lines have succumbed to the forces of nature in this area without any long-term environmental impacts. Sadly, this will not be the case if oil spills here.”

A later witness was Terry Brown, a former project engineer at Eurocan. Brown began by describing his love for sailing the Douglas Channel for the past 28 years. In one instance, Brown said, “ One extra-special night was when the ocean waters were disturbed and the phosphorescence was a glow like fireworks. We were seldom alone on the water as we often saw, heard and smelled seals, sea lions, orcas, and humpback whales, just like a huge aquarium but all to our own and so secluded.

“We not only stayed on the surface but some of our family engaged in scuba diving. What a joy to see so much life, crabs, fish, and shrimp, sea anemones, sea lions and much more. What a gorgeous dive it was as our daughter Stacy and I went down deep on the wall at Coste Rocks to see many different life forms hanging in our view. Later, we circumnavigated the rock and were amazed to see the pure white forms of a large sea anemone.”

Katherina Ouwehand   Murray Minchin  at JRP hearings
Katherina Ouwehand testifies at the Northern Gateway Joint Review hearings as Murray Minchin, the next witness listens, at the Haisla Recreation Centre, Kitamaat Village, June 25, 2012 (Robin Rowland/Northwest Coast Energy News)

 

Things failed

Like Aruda, he then turned to how things can go wrong. “No matter how hard we tried to do our best, things failed or as they often said, ‘shit happens’. Pipes, gaskets would fail; tanks would collapse; equipment would break. We even had SRBs in our stainless tanks. Many items would fail with such power that it would resemble an explosion.

“Lately, I have heard comments on how new gaskets are much better than old. Our experience was the opposite, as old gaskets contained asbestos they had a much better life span than the new synthetic ones.

“My largest project at Eurocan, a 300-tonne per day CMP pulp mill, actually had 10 — that’s it, 10 major failures within the first one to two years after start-up. During my working time, I was also involved in some of the projects to reduce the tainting of the local oohlican fish. This involves a highly cultural activity that the Haisla engaged in up until Eurocan start up in 1970.

“Over the 10 to 15 years spent looking for a solution, some $100 million was spent on related activities. If this much was spent with no success on a minor issue, if you call it that, how can anyone expect to clean up the beaches of a real nasty oil like dilbit?”

There was a third, highly technical presentation from Kelly Marsh, a millwright with the District of Kitimat (as well as Kitimat Search and Rescue volunteer) who presented his mathematical evidence, based on what he said we standard and accepted models that he said showed that Enbridge has vastly underestimated the chances of spill.

For the first time in public, some voiced in public what many in Kitimat have been saying in private, that if Stephen Harper pushes the project, there will be resistance from the residents of Northwestern British Columbia.

Katherina Ouwehand testified, “I am not a bully and I don’t lose my temper easily, but if this project is given the go-ahead by our Prime Minister, they had better be prepared for a huge fight. My thousands of like-minded friends and I will unite in force and do more than
speak up peacefully. There will be many blockades on the pathways of the pipeline and marine blockades in the channel.”

Murray Minchin, a member of Douglas Channel Watch (although everyone at the public comment hearings are testifying on their own behalf) said, “The original organizers of the Clayoquot Sound clear-cut logging blockades hoped that 500 to 600 people would turn out and help them protest. Over 10,000 showed up and almost 1,000 were arrested. Those numbers will be shattered if this project gets steamrolled through the regulatory process.”

Bill C-38

Many of the witnesses voiced their concerns about the Conservative omnibus Bill C-38 which they said would destroy many of the environmental safeguards in the Fisheries and Environmental Assessment Acts.

Margaret Ouwehand said. “I have a great fear. I am afraid of Enbridge because it represents much more than a pipeline; Enbridge is an enabler of all the things that make us ashamed to be Canadian. Do we want a Canada that endangers the whole world by contributing to global warming?

Do we want a Canada that muzzles scientists who don’t say what the oil companies want them to say? Do we feel proud when Canada puts up roadblocks to treaties with other countries so that oil companies can continue to pollute? Do we really want a Canada that prefers temporary foreign workers to be used and, in many cases, abused, just to provide oil companies with cheap labour? Wouldn’t it be more ethical to encourage immigrants to come to Canada to make permanent homes and actually contribute to the country?

“Once we were proud of Canada’s leadership in protecting the environment, both in Canada and world-wide. Now we have sold out to the highest bidders and by so doing we are jeopardizing our very sovereignty. We cannot enter into agreements to limit pollution because the big oil companies who own our resources won’t allow it.

“Once we were the world’s good guys, the peacekeepers, the ones who were caretakers of the environment and of endangered species. Now it’s all about money. Now we are at the bottom of the heap, along with other money-grubbers of the world.”

Mike Langegger, who has testified at previous National Energy Board and JRP hearings on behalf of the Kitimat Rod and Gun, testified, “Today I wish to speak to the implications of the Northern Gateway Project will have on my and many coastal families who call British Columbia home and the threat it poses to a generations of culture, lifestyle, relying on healthy and productive environment and ecosystems we currently have.

“My family, along with many resident British Columbians have a strong connection to our natural environment and is as much part of us as we are of it. By nature we are hunters and gatherers who have sustainable harvest from our natural environment over the generations providing for our families. Abundant and healthy fish and wildlife populations in environment that sustained their existence is critical and must be guaranteed.

“Unfortunately, over my lifetime I’ve witnessed commercial and industrial exploitation come and go, each diminishing our areas natural environment and its ability to support wildlife and the many associated values. It is critical that not only negative implications of the Northern Gateway Project be considered but also the cumulative effects of current, proposed, and past exploitation that has or is likely to occur in our area. Often a single negative impact can be mitigated. However, when a series of impacts are allowed to compile, the end result has proven to be devastating.

“Today the Dungeness crab and our local estuary area are deemed as contaminated and not recommended for consumption. The oohlican populations have been wiped out on most of our local area streams. The Kitimat River has been negatively impacted by resource extractions rendering it reliant on hatchery augmentation. Trees on the west side of the valley have died off suspect to pollution; wildlife populations have been impacted and the list goes on.

“We have seen industries come and exploit our area and its resources, profit substantially and leave, only to pass on a legacy of toxic sites and compromised environment. What they have not left behind is any established fund for impacted First Nation’s area residents and stakeholders to manage and reinvest back into our environment for the benefit of habitat, fish, wildlife that has been impacted.

“Ultimately, industry in general has been allowed to exploit, profit, and leave without being held accountable for our forest to correct damage. That’s the history we currently witness here.

“For those of us that call coastal British Columbia home, the existing environment, fish, wildlife, and associated values are the foundation of who we are. It is those values that foster and nurture many family bonds and are the result of cherished memories with loved ones and friends. It is those values that provide a healthy lifestyle and food source. It is those values that support numerous traditions and are the base of revered culture. It is those values that the Northern Gateway Project ultimately threatens to extinguish.”
Transcript Vol.58-Mon June 25, 2012 (pdf)

Enbridge pipeline controversy now on both coasts, Maine residents object to plan to send bitumen to Portland

It didn’t take long for the plans to send bitumen eastbound, perhaps as an alternative to Kitimat, to start controversy. The bitumen would go through the Montreal-Portland pipeline, thus the terminal could be at Portland, Maine.

The Maine coast is likely even more delicate than the British Columbia coast, and environmental groups are already gearing up to fight the pipeline as reported in the Kennebec (Maine) Journal, in tomorrow’s edition, June 21, 2012.

Tar sands oil transit meets objections

As speculation grows about the possibility of tar sands oil flowing from Canada through Maine, environmental advocates are banding together to oppose what they see as a risky proposition.

On Tuesday at Portland City Hall, [fisher Brooke] Hidell joined representatives from the Natural Resources Council of Maine, the Natural Resources Defense Council and the local chapter of the Sierra Club to protest what they say is a growing threat to Maine’s quality of life.

Enbridge Corp., a major petroleum company in Canada, has applied for a permit to reverse the flow of oil between Ontario and Montreal. Dylan Voorhees of the Natural Resources Council of Maine and others predict a similar reversal of the Portland-Montreal Pipe Line, so Canadian oil could be loaded onto tankers in Casco Bay, then shipped to refineries.

Voorhees said that would provide no real benefits to Maine but would threaten the environment while increasing profits for oil companies.

If Enbridge thinks the fight in British Columbia was a headache, it is likely that any plan to use Maine as a conduit for bitumen, will be as equal, if not more controversial.

The area is often home to prominent members of the American establishment.  The Bush family compound, summer retreat for presidents George W and George H. W. Bush, is in nearby Kennebunkport.

The state is also home to a large, vibrant and vocal artistic community.

Editor’s note:  Thirty years ago, in 1983, I took an Outward Bound course on the coast of Maine at the Hurricane Island School (it has since closed).  Unlike the rugged islands of the coast of British Columbia, the offshore islands where I sailed in Maine, are considered environmentally delicate and there are restrictions on the number of visitors and use of the island.

 

 

Kitimat gets ready for Joint Review hearings, protest rally and visit by NDP federal caucus

Kitimat is getting ready for the next round of Joint Review hearings in the district on the Enbridge Northern Gateway project.

The JRP is scheduled to hold the ten minute comment hearings at the Haisla Recreation Centre on the afternoon of June 25 and 26. The hearings scheduled for June 27 have been cancelled because, the JPR says: “The number of registered participants does not require the hearing session on 27 June.”  As with other locations, it appears that many people are dropping out of the hearings because given Prime Minister Stephen Harper’s determination to push through the pipeline no matter what and they feel their voices will not matter.

On Monday night, June 18, the District of Kitimat Council approved a request from Douglas Channel Watch for a protest rally to be held Sunday, June 24, at 2 p.m. in the lower parking lot at City Centre Mall. The application to the council said that a number of speakers will also address the issue of the government’s omnibus Bill C-38.

Margaret Ouwehand of Douglas Channel Watch, also noted in her application, “we wish to have a short march where participants would walk on sidewalks and obey all traffic signals.” In the report on the application, District staff noted that under the BC Municipal Code, a march of more than 30 people is considered a parade and in the case of Kitimat would also require the permssion of the local RCMP. The protest rally is being heavily promoted on Twitter and Facebook as well as more traditional media, so it is likely that there will be more than 30 people participating in the rally and march.

At the same time, some members of the federal NDP caucus will be in Kitimat for the second day of the hearings. A release from the NDP says Deputy Leader and Environment Critic Megan Leslie will lead the delegation to the northwest.

“Our caucus feels so strongly about the risks of Enbridge that many MPs are joining Megan to stand up to heavy-handed Conservative tactics,” said Skeena-Bulkley MP and House Leader Nathan Cullen. “The government has gutted environmental assessments and is trying to ram this project through and we’re not going to let that happen.”

The NDP Enbridge tour begins on Monday, June 25 with events and a public forum in Vancouver, a clear attempt to gain major media attention there, especially in an era where budget-strapped news organizations are always reluctant to send people to Kitimat.

Leslie and Cullen will then lead a smaller delegation to meet with Haisla Chief Councillor Ellis Ross and will tour a portion of the proposed marine route that oil supertankers would take to transport raw bitumen to Asia from Kitimat.

As well as attending the JRP hearings at Kitamaat Village, the NDP caucus plan to meet with local muncipal leaders in Kitimat as well as municipal officials and First Nations leaders from other communities.

“I’m really looking forward to key members of our Opposition caucus meeting with people who are directly affected by Enbridge,” Cullen said in his news release.

“Having taken part in dozens of Enbridge rallies and meetings over the years, I know there will be many very powerful moments. It’ll be pretty up front and personal.

“Megan and our caucus are here to stand in solidarity with residents of the Northwest in opposing a dangerous project that brings us so many risks and really only benefits Enbridge shareholders.”

In the evening after the JRP hearings, the NDP will then hold a public forum at the Best Western Inn in Terrace, starting about 6:30 p.m. (depending on the length of the afternoon JRP hearings)

Terrace mayor Dave Pernarowski and perhaps members of other local councils will make a welcoming statement, followed by an address from MEgan and then an information session with presentations from individuals & organizations, followed by a question and answer session and break-out groups for those interested.

With the June 27 JRP hearings now cancelled, there may be a second public meeting in Kitimat that afternoon starting at 12:30 p.m. but that is yet to be confirmed.

 

(Typo fixed, correcting day of rally from Monday to Sunday)

Haida Gwaii group releases rap video against Stephen Harper, Northern Gateway pipeline

A group called Haida Gwaii CoASt has released a video called ‘Haida Raid 2′, a rap rendition of what could happen if, as expected, Prime Minister Stephen Harper goes ahead with the Northern Gateway pipeline.

On the website, the group describes itself this way:

CoASt, Communities Against Super Tankers is an informal group made up of a diverse cross section of islanders on Haida Gwaii who are concerned about the consequences of tanker traffic on the West Coast of BC….

CoASt is a revival of the original Coalition Against Super Tankers that first opposed tanker traffic on behalf of Haida Gwaii in the late 1970s. The original members of the group could never have imagined the size of the tankers that are on the horizon for the Coast: 1/2 a kilometre long with 10 times the capacity of the Exxon Valdez. Imagine a spill from Alaska to California…

Enbridge claims support from 60 % of First Nations on pipeline route; company also sticks to repudiated Gitxsan deal.

Enbridge Northern Gateway says that 60 per cent of the aboriginal communities on the route of the $5.5 billion Northern Gateway oil pipeline have agreed to accept an equity stake in the project.

In releases to the media today, June 5, 2012, Enbridge says that half of the communities that signed up for a piece of the 10 per cent equity stake on offer are in British Columbia and the other half in Alberta.

There was immediate controversy because Enbridge is refusing to release the names of the communities that have signed up for the deal for “privacy reasons.”

The controversy was heightened late Tuesday when Enbridge spokesman Paul Stanway told The Terrace Standard  the company’s deal with the Gitxsan First Nation still stands, despite the fact both a majority of the heriditary leadership of the Gitxsan and the elected council have rejected the agreement signed by one chief Elmer Derrick.

A blockade of the Gitxsan treaty office is continuing despite a court injunction ordering an end to the blockade.

“We feel we certainly have an agreement,” said Enbridge official Paul Stanway told the Standard in describing discussions it has subsequently had with Gitxsan officials. Stanway said the deal followed a protocol arrangement signed with Gitxsan chiefs several years ago.

“We are confident we were negotiating with the right people,” he said of discussions with treaty society chief land claims negotiator Elmer Derrick and other society officials.

In addition, Art Sterritt, executive director of the Coastal First Nations issued a news release   that called Enbridge’s claims about aboriginal equity partners a “complete sham”.

“We’ve checked with all First Nations on the pipeline route west of Prince George and only two First Nations have signed equity agreements,” Sterritt says in the release.  “Enbridge expanded its pipeline corridor by 80 kilometres  to increase its numbers. Many of those communities that have signed on are located outside of the areas that will be impacted by a spill.”

Sterritt also challenged Enbridge’s contentions on the Gitxsan deal, saying that the Gitxsan people have made it clear they don’t support the project. “They have strongly rejected the agreement.”

Sterritt concluded. “We intend to stop this project.”

Sterrit says his coastal alliance is “absolutely mystified” about the inclusion of the Metis — who don’t have aboriginal rights and title within the corridor — in Enbridge’s 60 per cent. (Representatives of the Metis have taken part in the Joint Review hearings from the opening days of hearings in Kitimat last January).

Enbridge has announced before that First Nations support the pipeline project but, with the exception of Derrick, has never publicly discussed which nations support the project.

The near simultaneous announcement by Enbridge of First Nation’s support for the pipeline and the statement that the company is sticking with its agreement with Elmer Derrick could raise more controversy by causing more splits within First Nations if a few individuals sign and then the agreement is repudiated by other leaders, as happened with the Gitxsan Nation.

The pipeline which would run more than 1770 kilometres from the Alberta bitumen sands to Kitimat, carrying 525,000 barrels of diluted bitumen in the first train and as much as 825,000 barrels in the second train. If everything is approved, Enbridge hopes to ship the bitumen by 2017.

“It’s a good place for us to start in demonstrating that there is aboriginal support for Northern Gateway,” Stanway said. “It’s not 100 per cent, but neither is it the wall of opposition that our opponents sometimes claim.”

The 10 per cent equity ownership for the First Nations who signed the deal will give them about $280 million over 30 years. They would see cash flow starting in the first year of the pipeline’s operation.

There are 45 First Nations along the pipeline, but Stanway wouldn’t give a final figure on how many signed on.

“Some of those are willing to partner with us. That’s not to say they still don’t have some concerns. They want to make sure that we build and operate the pipeline as safety as possible.”

Wilf Adam of the Lake Babine First Nation in Burns Lake, B.C., the Canadian Press (as reported on the  Global BC  site)  he refused to sign the equity agreement because Enbridge was unwilling to release more details in the contract.

“I’d been asking for the financial figures and I’d been asking about the employment. They said there would be a lot of employment.”

Adam told CP it appeared to him that there would be few jobs available for his people. Hesaid there was a flurry of emails and phone calls from Enbridge officials after the company moved the deadline for signing the equity agreement up to May 31.
Related links

Reuters: Enbridge Northern Gateway wins some native support

Globe and Mail: Some first nations want equity in Northern Gateway, but opposition remains

Common Sense Canadian Tough Questions for Enbridge on its Alleged Support from First Nations

CBC Majority of aboriginal communities sign on to Northern Gateway

Anti-Enbridge group adopts Quebec students’ “red square” campaign

An anonymous group opposing the Enbridge Northern Gateway pipeline is calling for a demonstration at the site of an oil and gas export conference in Vancouver on May 30 and 31 and asking participants to wear the red square that has become symbolic of the Quebec student protests first against tuition fee hikes and later against Bill 78 aimed at controlling demonstrations in the province.

A notice posted on the website Infoshop News, which describes itself as an anarchist news service, calls for the demonstration at the Four Seasons hotel in Vancouver, site of the Canada Oil and Gas Export Summit. The notice is being widely circulated on Twitter.

The notice adds: “Don’t forget your red squares. Let’s bring the Maple Spring to BC and join Quebec students in opposing the 1% agenda of austerity and environmental destruction.”

Calling the demonstration, “Green Jobs, Not Oil Spills,” the notice says:  “On May 30th/31st the 1% are meeting at the Four Seasons hotel for a two day conference to plot their strategy for Exporting raw tar sands bitumen across BC and overseas to China via pipelines and super tankers.”

The website for the Canadian Oil and Gas Export Summit,  says “The oil and gas industry is at a critical crossroads and now is the time to take a hard look to alternative outlets for Canadian oil and gas,” meaning alternative markets to the United States.  The energy companies are worried about the future of  their American market share due to the effect of political gridlock on the US economy and the growing exploitation of American shale gas deposits which are cutting into Canadian export markets.

The site says the conference highlights include:

  • The latest updates on opening new market opportunities – Moving Canada oil and
    gas exports beyond U.S. markets
  • The impact of the U.S. pipeline decision on the Canadian oil and gas sector
  • The benefits for Canadian producers to tap into Asian markets and
    addressing the perceptions of the two markets
  • The most cost effective strategies of getting to market in light of opposition
  • Infrastructure requirements necessary for accessing Canada’s East and West Coast
  • The legal and regulatory issues surrounding west coast energy corridors, terminals and
    shipping in British Columbia

The conference speakers will tackle a large number of hot button issues in BC, from the energy industry point of view: Paul Fisher, vice present, Commercial, Western Access for Enbridge Pipelines speaks on “Exploring Canada’s Ability to Compete in a Global Marketplace.” Gordon Houlden, Director of the China Institute at the University of Alberta, has a talk touching on “Balancing the complexities of unresolved land claims, environmental and infrastructure issues and the economic development of Western Canada.” Tracy Robinson, Vice President Marketing & Sales, Canadian Pacific Railway, speaks on exporting crude by rail. Douglas Ford, of Communica Public Affairs Inc. handles a large number of issues from the PR point of view, including “the regulatory processes related to British Columbia coastal development,” “the complexity of project development in BC vis a vis First Nations,” with advice on “How to effectively engage community, NGOs, and aboriginal stakeholders.” Van Zorbas of Deloitte Canada speaks about the problems from the current labour shortage.

 

US National Transportation Safety Board releases photos, documents on Enbridge Kalamzoo oil spill

NTSB staff examine ruptured pipe
US National Transportation Safety Board staff examine a ruptured pipe from the Enbridge oil spill in August, 2010. The photo was released by the NTSB May 21, 2012. (NTSB)

The United States National Transportation Safety Board today released more than 5,000 pages relating to its investigation of the 2010 of the Marshall, Michigan, Enbridge pipeline rupture and oil spill.

The NTSB release says it is adding the documents to the “public docket” on the case.

About 11:17 a.m. EDT on July 26, 2010, Enbridge Energy Partners was notified of a leak on a 30-inch diameter crude oil pipeline (Line 6B) in Marshall, Michigan. The pipeline had ruptured 17 hours earlier and spilled about a million gallons of crude oil into the immediate area resulting in extensive environmental damage to Talmadge Creek and the Kalamazoo River.

Fifty-eight photographs and 170 documents totaling more than 5000 pages are in the docket. The information being released is factual in nature and does not provide any analysis.

Additional material may be added to the docket as it becomes available. Analysis of the accident, along with conclusions and its probable cause, will be determined at a later date.

This is a document release only; no interviews will be conducted.

Documents are available at this link

More than 800,000 gallons of heavy bitumen crude spilled from the pipeine near Marshall in Calhoun County, Michigan. NTSB spokesman Peter Knudson said Monday the NTSB expects to reach a conclusion on the spill sometime this summer.

On May 10, Enbridge announced it would spend $1.6 billion to upgrade and replace portions of the pipeline through Michigan and Indiana. The broken pipeline, however, would be decontaminated and “abandoned in place.”