JRP excludes Kitimat from questioning round, hearings in Prince Rupert, Prince George and Edmonton

The Northern Gateway Joint Review Panel will bypass Kitimat for the final questioning hearings on the controversial pipeline.

In a ruling issued late on July 4, 2012, the JRP said the questioning hearings will begin on September 4, 2012 in Edmonton followed by hearings in Prince George and Prince Rupert.

The JRP says a more detailed schedule will be issued closer to the start of the final hearings.

It adds, that details on the location for the final hearings for final argument will be announced at a later date.

In its ruling the JRP said:

As noted previously, these locations are centrally located, have adequate facilities and reasonable transportation access. The Panel is of the view that these locations are appropriate as they are relatively close to the proposed Project and are readily accessible by all parties who are actively participating in the Northern Gateway hearing process and their witnesses. Further, these locations will allow for appropriate hearing facilities that are safe, of an adequate size and can logistically and technologically accommodate a hearing with many participants.

The Joint Review panel acknowledged that some “witnesses would be financially and logistically
unable to attend three different hearing locations for questioning in Alberta and British
Columbia.”

The JRP says it will “to the best of its ability and to the extent reasonable, accommodate
interested parties’ participation at the final hearings through remote participation.
Standard procedures for the final hearings.”

(i) Parties and members of the public may listen to all of the final hearings live,
through the webcast (available from the Panel’s website).
(ii) Parties may register their appearance on the first day of the final hearings
remotely by telephone, or other technology to the extent feasible such as
videoconference or webex. Details regarding potential audio-visual options will
be provided in advance of the final hearings.
(iii)Parties may ask questions of other party’s witnesses by telephone, or other
technology such as vidoconference or webex to the extent possible. Parties will be
asked to confirm their method of participation, in advance of the final hearings for
questioning.
(iv) Parties’ witnesses may be presented for questioning by technology such as
videoconference or webex that is capable of capturing audio and visual images of
the witnesses simultaneously.

The JRP says its staff is working to address issues that may arise from remote questioning and video conferences.

Some key questions such as the effects of the pipeline and tanker traffic on marine mammals will be handled by “concurrent panels,” that is groups of expert witnesses sitting together. That is a standard National Energy Board procedure and was used during the NEB hearings on the Kitimat LNG project in June, 2011.

A separate ruling from the Joint Review Panel requires all parties to provide a list of witnesses for questioning hears on or before Friday, July 13, 2012.

This list must include all experts that have submitted reports on the party’s behalf, as well as those individuals that are able to answer questions on the specific evidence filed. Where relevant, it would be helpful if parties would organize their list of witnesses into “witness panels” by topic.

JR Procedural Direction 8 Final Hearings – Questioning  (pdf)

JRP Procedural Matters Final Hearings Witness Panels   (pdf)

 

Enbridge question on “marine vessel activity” on Douglas Channel gets obvious answer from the Haisla

Fog shrouds Kitimat harbour
Fog and low clouds shroud Kitimat harbour on the morning of June 27, 2012. (Robin Rowland/Northwest Coast Energy News)

If there is a major disconnect between the people who live in the Kitimat region and the rest of Canada, it is the question of vessel traffic on the Douglas Channel, with Enbridge spinning that there is already major tanker traffic on the Channel.

This section from the Northern Gateway website, is often quoted by Enbridge supporters, the vast majority of whom live in Alberta, thousands of kilometres away, have never been to Kitimat, but, somehow from Calgary or Fort McMurray,  claim to know more about the Douglas Channel than people who live in Kitimat, including those who have sailed Douglas Channel for decades.

On its website Northern Gateway claims

According to numbers from the Port of Kitimat, not only have vessels carrying industrial products been travelling the channels safely for some 35 years, but so too have ships carrying petroleum products—like the one featured arriving in the Port of Kitimat through the Douglas Channel in the picture above.
In fact, some 1,560 vessels carrying methanol and condensate called on Kitimat port from 1982 to 2009 – that’s over 3,100 transits of vessels dedicated to the transport of petroleum products.
When you add vessel traffic of all industrial activity into Kitimat port, the number jumps to 6,112.
To be clear…the number of ships servicing industry arriving at Kitimat port between 1978 and 2009 is 6,112. That’s 12,224 transits!

So in its questions to the Haisla, Enbridge asked:

c) Please confirm that the Haisla Nation is aware of existing and proposed
marine vessel activity within its Traditional Territory, including:

(i) fuel barges

(ii) cargo/container ships

(iii) commercial fishing vessels

(iv) condensate tankers

(v) liquefied natural gas tankers

 

Enbridge’s question was an obvious attempt to enhance their spin on vessel traffic on the Douglas Channel, by fishing for an admission that large vessels already ply the Channel, something the residents of the Kitimat, both First Nations and non-aboriginal already know well.

In its response, the Haisla Nation replies:

The Haisla Nation is aware of the existing and proposed marine vessel activity within its Territory, including fuel barges, cargo/container ships, commercial fishing vessels, condensate tankers, and liquefied natural gas tankers.

The Haisla Nation is also aware of the increased cumulative effect of additional marine vessel activity as projects are approved. The presence of this shipping increases the significance of the potential impacts of the project on Haisla Nation aboriginal title and rights, through cumulative impacts.

The Haisla Nation is responsible for some of the vessel traffic within its Territory, with modern forms of transportation having replaced canoes. Until legal developments in the early 2000s which have defined the content of the honour of the Crown with respect resource decisions and potential impacts on First Nations, the Haisla Nation had little say about the projects with associated vessel traffic in its Territory.

While standard petroleum product tankers, many carrying condensate, a natural gas product, have been visiting Kitimat for years, there have. so far, been no supertankers, much less Very Large Crude Carriers. No bitumen carrying tankers have visited Kitimat, a fact always ignored by the region’s critics in Alberta and by Enbridge on its website.

Not only the filing by the Haisla Nation but most of the testimony at the recent public comment hearings in at Kitamaat Village, were about the fear of the growing cumulative effect of greatly increased tanker traffic on the Channel.

Haisla outline where they believe Enbridge Gateway plans are inadequate

Haisla NationIn their filing with the Joint Review Panel, the Haisla Nation point to what they say is inadequate information provided by Enbridge on the Northern Gateway project, including:

To date the material provided by Northern Gateway does not adequately explain the known risks inherent to the proposed project and lacks significant detail with  respect to the extent and degree of potential effects. The material provided by  Northern Gateway does not provide sufficient information to determine how the  risks inherent to the proposed project will be minimized, nor how the potential for  significant adverse effects will be avoided.

There are a number of areas where the Haisla Nation has identified inadequateinformation, including but not limited to:

.
Design: there is a lack of information about detailed design  considerations and monitoring procedures for pipeline integrity to avoid  accidents and malfunctions due to corrosion, seismic events, and terrain  instability. A notable example of this problem is in the Kitimat River  Valley, where Northern Gateway has identified a high level of risk but has  not offered any solutions. Another is the concern about the corrosive nature of the material to be transported. Northern Gateway denies that  this is a problem, yet the US Department of Transportation Pipeline and
Hazardous Material Safety Administration (PHMSA) has commissioned a  major study to investigate the corrosive nature of diluted bitumen in pipelines.

Materials to be transported: there is a lack of information about the fate, behaviour and effects of diluted bitumen, synthetic crude and condensate in the cold water marine and freshwater environment. This concern has been identified by federal government participants as well as by numerous intervenors, and Northern Gateway has acknowledged the need for more research and information. Yet, Northern Gateway has not agreed to undertake this work so that it is available for review in this process.

Volume of material to be transported: Northern Gateway’s application is for a pipeline that will transport 525,000 barrels of diluted bitumen per day. Yet the pipeline will be built to have a capacity of up to 850,000 barrels per day, and Northern Gateway’s application materials identifies future phases with increased volumes up to this amount. The risk assessments conducted by Northern Gateway are premised on 525,000 barrels per day, and fail to contemplate higher volumes which would affect a number of matters, including but not limited to: pipeline risk; volume of potential spills; and tanker traffic volume. The risk assessment needs to be revised, to address the risks associated with the pipeline transporting 850,000 barrels of diluted bitumen per day. Without this revision, Northern Gateway is asking the JRP to conduct its assessment on incomplete information that, by definition, understates the true potential risk of the proposed project.

.Baseline information: Northern Gateway has not undertaken the studies necessary to generate baseline ecosystem assessments for the Kitimat River drainage and Kitimat Arm, including seasonal habitat utilization by species and life stages throughout the watershed. This information is necessary to determine both stream crossing construction strategy and to assess the potential impacts of a spill, as well as to determine how to respond to a spill and when. A ‘one-size fits all’ approach to stream crossings during construction and spill response, when adequateinformation about seasonal habitat utilization by species and life stages throughout the watershed is lacking, is not adequate. This information is needed to determine when construction can proceed and what timeframe limitations there are for activities, to ensure that adverse effects to fish and wildlife are avoided. This information is also required, should a spill occur, to enable a proper assessment of the extent and degree of adverse effects as well as to provide a proper basis for restoration of affected habitat.

Past spills: there is a lack of information about the cause, effects, emerging information and lessons learned as a result of Enbridge’s large diluted bitumen spill into the Kalamazoo River. We know that 3,785,400 liters of diluted bitumen were pumped out of the pipeline, with a largeportion of that ending up in to the Kalamazoo River. We know the large volume of the spill was the result of numerous attempts to re-pressurize the pipeline despite repeated spill alarms being triggered. We know that government agencies stepped in to manage the spill because Enbridge’s response was not swift enough. We know that Enbridge’s clean-up costs to date exceed insurance coverage. We know that two years later Enbridge is still under a clean-up mandate from the US Environmental Protection Agency and the Michigan Department of Environmental Quality, and that portions of the Kalamazoo River are still closed to recreational use. What we do not know, however, is what the cause of the pipeline rupture was, what Enbridge has learned about how diluted bitumen behaves once it is released into the environment, or how a local population that relies on the river for fishing, for traditional harvesting and gathering of foods and medicines would have been affected.

Oil spill response: there is a lack of information about oil spill response and planning, including best practices, best available technology and the local on-site equipment and personnel required full-time to respond properly to a spill. This is largely due to the lack of adequate baseline information on which to base response planning. Further, Northern Gateway has demonstrated an unwillingness to fully consider how spill response would be carried out until it receives a certificate for its project.

Yet Northern Gateway seeks to rely on spill response as a mitigation strategy. If Northern Gateway seeks to rely on spill response as a mitigation strategy, it should provide in detail, prior to project approval, what its oil spill response would include and demonstrate that it is logistically, technologically and economically feasible. Northern Gateway has not done this.

.Mitigation measures: there is a lack of information about existing proven mitigation measures and their effectiveness in cleaning up an oil spill, restoring habitat and regenerating the species dependent on the affected habitat. This should be evaluated as part of project review, prior to project approval. Where Northern Gateway seeks to rely on a mitigation measure as a basis for project approval, it must demonstrate that the proposed mitigation will actually work.

Avoidance of any significant adverse effects must be the primary goal and dictate the design and location of the proposed project. Mitigation (e.g. complete resolution) of any potential environmental effects should be the preferred option, when all efforts to avoid such effects fail. Compensation for environmental effects must be a last resort and relied on only when best efforts have been made to avoid or mitigate effects. Unfortunately, the material submitted by Northern Gateway suggests that compensation is the primary option and lack of evidence on project design and procedures makes it impossible to evaluate how potential effects could be avoided or mitigated.

For example, Northern Gateway proposes to have spill interception points (river control points) along the Kitimat River Valley as part of its mitigation, but has no realistic plan in place that takes into consideration response delay times, rates of transportation, access issues or baseline ecosystem, fish and wildlife information for the receiving environment.

 

 

Main story Haisla Nation confirms it opposes Northern Gateway, demands Ottawa veto Enbridge pipeline; First Nation also outlines “minimum conditions” if Ottawa approves the project

Haisla Nation Response to NGP Information Request  (pdf)

Haisla outline conditions, concerns for Northern Gateway project

Haisla NationIn its extensive document filed with the Northern Gateway Joint Review panel, the Haisla Nation emphasize their opposition to the project.

However, the Haisla are anticipating that the project will be approved and  therefore submitted a lengthy series of conditions for that project, should it be imposed on the northwest by the federal government.

Nevertheless, if the project were to be approved AFTER the Crown meaningfully consulted and accommodated the Haisla Nation with respect to the impacts of the proposed project on its aboriginal title and rights, and if that consultation were meaningful yet did not result in changes to the proposed project, the following conditions would, at a minimum, have to be attached to the project.

 

1. Conditions Precedent: The following conditions precedent should be met prior to any field investigations, pre-construction activities or construction activities as well as during and subsequent to such investigations or activities. These conditions are necessary to ensure that potential effects of the project can be avoided or mitigated to reduce the likelihood of habitat damage or destruction:

Comprehensive seasonal water quality monitoring throughout the Kitimat River watershed, Kitimat Arm and Douglas Channel that account for seasonal variations in flow, tidal cycles, snowmelt, rainfall, etc.

Parameters for measurement would be have to be agreed upon by the
Haisla Nation prior to certification of the project;

Comprehensive seasonal fisheries surveys of fish habitat utilization  throughout the Kitimat River watershed, Kitimat Arm and Douglas Channel that account for where species and life stages are at different times of the year and accurately define sensitive habitats;

Comprehensive seasonal wildlife and bird surveys of habitat utilization throughout the Kitimat River watershed, Kitimat Arm and Douglas Channel that account for where species and life stages are at different times of the year and accurately define sensitive habitats;

Comprehensive seasonal vegetation surveys of habitat utilization throughout the Kitimat River watershed, Kitimat Arm and Douglas Channel that accounts for the distribution of species and life stages at different times of the year and accurately define sensitive habitats;

Development of comprehensive spill response capability based on a realistic assessment of spill containment, spill response and spill capacity requirements throughout the Kitimat River Valley, Kitmat Arm and Douglas Channel. The Haisla Nation’s past experience has shown that relying onpromises is not good enough. This spill response capability must be demonstrated prior to project approval;

Verification that the proposed project would result in real benefits, economic or otherwise, that would flow to the Haisla Nation, to other First Nations, and to British Columbia.

Whenever any field investigations or activities are proposed, the proposal or permit application would have to include the following environmental protections:

Soil and erosion control plans;

Surface water management and treatment plans;

Groundwater monitoring plans;

Control and storage plans for fuels, lubricants and other potential contaminants;

Equipment deployment, access and use plans;

Habitat reclamation of disturbed or cleared areas.

Prior to any pre-construction or construction activities the following detailed studies would have to be undertaken and provided to the Haisla Nation for review and approval, to ensure that the best design and construction approaches are being used, so that potential effects of the project can be avoided or mitigated to reduce the likelihood of habitat damage or destruction:

Detailed analysis of terrain stability and slide potential throughout the pipeline corridor and at the storage tank and terminal site;

Detailed engineering design to mitigate seismic risk and local weather extremes;

.Development of pipeline integrity specifications and procedures including
best practices for leak detection;

Development of storage tank integrity specifications and maintenance and monitoring procedures;

Assessment of spill containment, spill response and spill capacity requirements throughout the Kitimat River watershed, Kitimat Arm and Douglas Channel;

.Development of detailed tanker acceptance program specifications and
procedures;

Development of detailed tanker and tug traffic management specifications and procedures;

Development of detailed port management specifications and procedures including operating limits for tanker operation, movement and docking.

2. Ongoing Consultation: A commitment to ongoing consultation with and accommodation of the Haisla Nation on all of the activities set out above.

3. Ongoing process for variance, waiver or discharge of conditions: A commitment to ongoing meaningful involvement of the Haisla Nation by the National Energy Board prior to any decision on any changes to or sign off on conditions and commitments to any certificate that is issued.

4. Third Party Oversight of Construction: A requirement that NorthernGateway fund a third party oversight committee, which should include a Haisla Nation representative, to monitor certificate compliance during construction of the marine terminal and the pipeline. This committee would have the ability to monitor and inspect construction and should be provided with copies of allcompliance documents submitted by Northern Gateway to the National Energy Board.

5. Operational Conditions: A number of operational conditions should beincorporated into the certificate, including but not limited to:

The requirement to monitor terrain along the pipeline so that breaches based on earth movements can be anticipated and prevented;

The requirement to implement automatic pipeline shutdown whenever a leak detection alarm occurs;

Conditions on the disposal of any contamination that must be removed as a result of an accident or malfunction resulting in a spill that will minimize additional habitat destruction and maximize the potential for regeneration of habitat and resources damaged by the spill;

Parameters for terminal and tanker operations (including standards for tankers allowed to transport cargo; tanker inspection requirements and schedules; escort tug specifications, standards, maintenance and inspection; pilotage protocols and procedures; environmental conditions and operating limits; etc.) as well as other parameters set out in and reliedon for the TERMPOL review to become conditions of any certificate issued by the National Energy Board, with a provision that the Haisla Nation’s approval of any changes to these conditions is required.

Answering the questions from Enbridge Northern Gateway, the Haisla also outline a long series of concerns.

1. Physical and Jurisdictional Impacts

1.1 Construction

The Haisla Nation is concerned about the direct physical and jurisdictional impacts that the construction of the proposed project will have. These concerns are set out for each of the marine terminal, the pipeline, and tanker traffic, below:

Marine Terminal:

a. The proposed marine terminal will require the alienation of 220-275
hectares (554-680 acres) of land from Haisla Nation Territory, land
to which the Haisla Nation claims aboriginal title.

b. The terminal will require the additional alienation of land for
ancillary infrastructure and development, including:

i. road upgrades,

ii. perimeter access roads and roads within the terminal area,

iii. a potential public bypass road,

iv. an impoundment reservoir,

v. a disposal site for excess cut material outside the terminal
area,

vi. a new 10km long transmission powerline, and

vii. a 100-m waterlot with a 150-m “safety zone”.

c. The terminal proposes to use Haisla Nation aboriginal title land,
including foreshore and waters, in a way that is inconsistent with
Haisla Nation stewardship of its lands, waters and resources and
with the Haisla Nation’s own aspirations for the use of this land.
Since aboriginal title is a constitutionally protected right to use the
aboriginal title land for the purposes the Haisla Nation sees fit, this
adverse use would fundamentally infringe the aboriginal title of the
Haisla Nation.

d. The terminal will require the destruction and removal of
documented culturally modified trees, some with modifications
dating back to 1754. These culturally modified trees are living
monuments to the history of the Haisla people.

e. The terminal will expose two Haisla Nation cultural heritage sites to
increased risk of vandalism and chemical weathering.

f. The terminal will result in the direct loss of 4.85 hectares (11.98
acres) of freshwater fish habitat (harmful alteration, disruption or
destruction (HADD) under the Fisheries Act).

g. The terminal will require dredging, underwater blasting, and
placement of piles and berthing foundations, resulting in an as yet
un-quantified loss of intertidal and subtidal marine habitat.

Pipeline:

a. The proposed pipeline construction right-of-way will require the
alienation of 9,200 hectares (22,734 acres) of Haisla Nation
Territory – land to which the Haisla Nation claims aboriginal title –
and will put this land to a use that is inconsistent with Haisla Nation
stewardship of its lands, waters and resources and with the Haisla
Nation’s own aspirations for the use of this land.

b. The pipeline will require 127 watercourse crossings in Haisla Nation
Territory. Seven of these are categorized as high risk, 5 as
medium high risk, and 7 are medium or medium low risk for harmful
alternation, disruption or destruction (HADD) of fish habitat. This
risk is just from pipeline construction and does not address the
issue of spills.

c. The pipeline is estimated to result in temporary or permanent
destruction of freshwater fish habitat of 3.1 hectares (7.68 acres) in
Haisla Nation Territory.

d. The pipeline will require the clearing of land and vegetation and the
destruction of wetlands. The extent of this is yet to be quantified.

Tanker Traffic:

a. Although Northern Gateway has not made any submission on this
point, it is clear that having adequate spill response capability at
Kitimat will require additional infrastructure upgrades in and around
Kitimat, as well as potential spill response equipment cache sites.
None of this has been considered or addressed in Northern
Gateway’s application material – as such the material is
incomplete.

b. The construction for this additional infrastructure could result
impacts to ecosystems, plants, wildlife and fish, and in additional
HADD or fish mortality from accidents.

All of the land alienations required for the proposed project would profoundly
infringe Haisla Nation aboriginal title which is, in effect, a constitutionally
protected ownership right. The proposed project would use Haisla Nation
aboriginal title land in a way that is inconsistent with Haisla Nation stewardship of
its lands, waters and resources and with the Haisla Nation’s own aspirations for
the use of this land. Since aboriginal title is a constitutionally protected right to
use the aboriginal title land for the purposes the Haisla Nation sees fit, this
adverse use would fundamentally infringe the aboriginal title of the Haisla Nation.

The Haisla Nation is also concerned about the socio-economic and health
impacts of the proposed project. Northern Gateway has yet to file its Human
Health and Ecological Risk Assessment. Further, the socio-economic impact
analysis submitted as part of the application provides only a limited assessment
of the potential impacts of the project on the Haisla Nation at a socio-economic
level.

Haisla Nation society and economy must be understood within the cultural
context of a people who have lived off the lands, waters and resources of their
Territory since long before European arrival. To limit a socio-economic impact
assessment to direct impacts and to ignore consequential impacts flowing from
those impacts fails to capture the potential impacts of the proposed project on the
Haisla Nation at a socio-economic level.

1.2 Operation

The proposed marine terminal, pipeline corridor and shipping lanes will be
located in highly sensitive habitats for fish, wildlife and plants. Any accident of
malfunction at the wrong time in the wrong place can be devastating ecologically.
The Haisla Nation has identified the following concerns relating to physical
impacts from the operation of the proposed project:

Marine Terminal:

a. Intertidal and subtidal marine habitat impacts as a result of marine
vessels.
b. The likelihood of spills from the marine terminal as a result of operational
mistakes or geohazards.

c. The effects and consequences of a spill from the marine terminal. This
includes impacts on the terrestrial and intertidal and subtidal marine
environment and fish, marine mammals, birds, and other wildlife, as well
as impacts on Haisla Nation culture and cultural heritage that could result
from such impacts.

d. Response to a spill from the marine terminal, including concerns about
spill response knowledge, planning and capability, as well as impacts
flowing from response measures themselves.

Pipeline:

a. The likelihood of spills from the pipeline as a result of pipeline failure,
resulting from inherent pipeline integrity issues or external risks to pipeline
integrity, such as geohazards.

b. The effects and consequences of a spill from the pipelines. This includes
impacts on the terrestrial environment and freshwater environment, and
on plants, fish, birds, and other wildlife, as well as impacts on Haisla
Nation culture and cultural heritage that could result from such impacts.

c. Response to a spill from the pipelines, including concerns about spill
response knowledge, planning and capability, as well as impacts flowing
from response measures themselves.

Tanker Traffic:

a. Increased vessel traffic in waters used by Haisla Nation members for
commercial fishing and for traditional fishing, hunting and food gathering.

b. The likelihood of spills, including condensate, diluted bitumen, synthetic
crude, and bunker C fuel and other service fuels, from the tankers at sea
and at the marine terminal.

c. The effects and consequences of a spill. This includes impacts on the
marine environment and fish, marine mammals, birds, and other wildlife,
as well as impacts on Haisla Nation culture and cultural heritage that could
result from such impacts.

d. Response to a spill, including concerns about spill response knowledge,
planning and capability, as well as impacts flowing from response
measures themselves.

e. Potential releases of bilge water, with concerns about oily product and
foreign organisms.
These issues are important. They go to the very heart of Haisla Nation culture.
They go to the Haisla Nation relationship with the lands, waters, and resources of
its Territory. A major spill from the pipeline at the marine terminal or from a
tanker threatens to sever us from or damage our lifestyle built on harvesting and
gathering seafood and resources throughout our Territory.

Northern Gateway proposes a pipeline across numerous tributaries to the Kitimat
River. A spill into these watercourses is likely to eventually occur. The evidence
before the Panel shows that pipeline leaks or spills occur with depressing
regularity.

One of Enbridge’s own experiences, when it dumped 3,785,400 liters of diluted
bitumen into the Kalamazoo River, shows that the concern of a spill is real and
not hypothetical. A thorough understanding of this incident is critical to the
current environmental assessment since diluted bitumen is what Northern
Gateway proposes to transport. However, nothing was provided in the application
materials to address the scope of impact, the level of effort required for cleanup
and the prolonged effort required to restore the river. An analysis of this incident
would provide a basis for determining what should be in place to maintain
pipeline integrity as well as what should be in place locally to respond to any spill.

The Kalamazoo spill was aggravated by an inability to detect the spill, by an
inability to respond quickly and effectively, and by an inability to predict the fate
of the diluted bitumen in the environment. As a result, the Kalamazoo River has
suffered significant environmental damage. The long-term cumulative
environmental damage from this spill is yet to be determined.

Further, the Haisla Nation is also concerned about health impacts of the
proposed project and awaits the Human Health and Ecological Risk Assessment
which Northern Gateway has promised to provide.

1.3 Decommissioning

Northern Gateway has not provided information on decommissioning that is detailed enough to allow the Haisla Nation to set out all its concerns about the potential impacts from decommissioning at this point in time. This is not good enough. The Haisla Nation needs to know how Northern Gateway proposes to undertake decommissioning, what the impacts will be, and that there will be financial security in place to ensure this is done properly.

2. Lack of Consultation

 

Broadly, the Haisla Nation has concerns about all three physical aspects of the
proposed project – the pipeline, the marine terminal and tanker traffic – during all
three phases of the project – construction, operation and decommissioning.
These concerns have not been captured or addressed by Northern Gateway’s
proposed mitigation. The Haisla Nation acknowledges that a number of these
concerns can only be addressed through meaningful consultation with the
Crown. The Haisla Nation has therefore repeatedly asked federal decision-
makers to commit to the joint development of a meaningful consultation process
with the Haisla Nation. The federal Crown decision-makers have made it very
clear that they have no intention of meeting with the Haisla Nation until the Joint
Review Panel’s review of the proposed project is complete.

The federal Crown has also stated that it is relying on consultation by NorthernGateway to the extent possible. The federal Crown has failed to provide anyclarity, however, about what procedural aspects of consultation it has delegated to Northern Gateway. Northern Gateway has not consulted with the Haisla Nation and has not advised the Haisla Nation that Canada has delegated any aspects of the consultation process.

The Haisla Nation asserts aboriginal title to its Territory. Since the essence of

aboriginal title is the right of the aboriginal title holder to use land according to its
own discretion, Haisla Nation aboriginal title entails a constitutionally protected
ability of the Haisla Nation to make decisions concerning land and resource use
within Haisla Nation Territory. Any government decision concerning lands,
waters, and resource use within Haisla Nation Territory that conflicts with a
Haisla lands, waters or resources use decision is only valid to the extent that the
government can justify this infringement of Haisla Nation aboriginal title.

The Supreme Court of Canada has established that infringements of aboriginal
title can only be justified if there has been, in the case of relatively minor
infringements, consultation with the First Nation. Most infringements will require
something much deeper than consultation if the infringement is to be justified.
The Supreme Court has noted that in certain circumstances the consent of the
aboriginal nation may be required. Further, compensation will ordinarily be
required if an infringement of aboriginal title is to be justified [Delgamuukw].

The Haisla Nation has a chosen use for the proposed terminal site. This land
was selected in the Haisla Nation’s treaty land offer submitted to British Columbia
and Canada in 2005, as part of the BC Treaty Negotiation process, as lands
earmarked for Haisla Nation economic development.

The Haisla Nation has had discussions with the provincial Crown seeking to
acquire these lands for economic development purposes for a liquefied natural
gas project. The Haisla Nation has had discussions with potential partners about
locating a liquefied natural gas facility on the site that Northern Gateway
proposes to acquire for the marine terminal. The Haisla Nation sees these lands
as appropriate for a liquefied natural gas project as such a project is not nearly
as detrimental to the environment as a diluted bitumen export project. This use,
therefore, is far more compatible with Haisla Nation stewardship of its lands,
waters and resources.

By proposing to use Haisla Nation aboriginal title land in a manner that is
inconsistent with Haisla Nation stewardship of its lands, waters and resources,
and that interferes with the Haisla Nation’s own proposed reasonable economic
development aspirations for the land, the proposed project would result in a
fundamental breach of the Haisla Nation’s constitutionally protected aboriginal
title.

Similarly, Haisla Nation aboriginal rights are constitutionally protected rights to
engage in certain activities (e.g. hunting, fishing, gathering) within Haisla Nation
Territory. Government decisions that infringe Haisla Nation aboriginal rights will
be illegal unless the Crown can meet the stringent test for justifying an
infringement.
Main story Haisla Nation confirms it opposes Northern Gateway, demands Ottawa veto Enbridge pipeline; First Nation also outlines “minimum conditions” if Ottawa approves the project

Haisla Nation Response to NGP Information Request  (pdf)

Haisla Nation confirms it opposes Northern Gateway, demands Ottawa veto Enbridge pipeline; First Nation also outlines “minimum conditions” if Ottawa approves the project

Haisla NationThe Haisla Nation has confirmed in a filing with the Northern Gateway Joint Review Panel that it opposes the Enbridge Northern Gateway project.

The document, filed June 29, 2012, is one of the most significant filed with the JRP during all the years of the debate over the controversial Northern Gateway, setting out a three stage process that will govern, whether Enbridge or the federal government like it or not, the future of the Northern Gateway pipeline project.

First, the Haisla Nation affirms that it opposes the Northern Gateway project

Second, the Haisla Nation is demanding that the federal government, in recognition of aboriginal rights and title, reject the Northern Gateway project on Haisla traditional territory.

Third, probably anticipating that Stephen Harper and his government will attempt to force the Northern Gateway on British Columbia, the Haisla are demanding meaningful consultation and set out a stringent set of minimum conditions for the project on Haisla traditional territory.

The Haisla Nation’s lawyers filed the document today late today, June 29, in response to a series of questions posed to the First Nation by Enbridge through the Joint Review process.

The Haisla also say that there already projects that are better suited to their traditional territory, the liquified natural gas projects.

The Haisla position that Ottawa must reject the pipeline if First Nations oppose it is the opening round in the constitutional battle over not just the pipeline, but entire question of aboriginal rights and title. So far the government of Stephen Harper has said that First Nations do not have a “veto” on the pipeline and terminal project.

The Haisla also refuse to answer questions that Enbridge posed on the liquified natural gas projects because the filing argues, the questions are beyond the scope of the current Joint Review inquiry.


Detailed excerpts

Haisla outline where they believe Enbridge Gateway plans are inadequate

Haisla outline conditions, concerns for Northern Gateway project

 


 

Why the Haisla oppose Northern Gateway

In the filing with the Joint Review panel, the Haisla outline nine reasons for opposition to the Northern Gateway project:

1. Northern Gateway is proposing to site its project in a location that places at risk the ecological integrity of a large portion and significant aspects of Haisla Nation Territory and resources.

2. All three aspects of the proposed project – the pipelines, the marine terminal and tankers – have the potential to impact Haisla Nation lands, waters and resources.

3. Northern Gateway has neither conducted sufficient due diligence nor provided sufficient information with respect to the assessment of a number of critical aspects of the proposed project, including but not limited to project design, impacts, risks, accidents and malfunctions, spill response, potential spill consequences and the extent, degree and duration of any significant adverse environmental effects.

4. There are significant risks of spills of diluted bitumen, synthetic crude, and condensate from corrosion, landslide hazards, seismic events along the pipeline route and at the terminal site; as well asloss of cargo or service fuels from tanker accidents, with no realistic plan provided for spill containment, cleanup, habitat restoration or regeneration of species dependent on the affected habitat.

5. Diluted bitumen, synthetic crude and condensate are all highly toxic to the environment and living systems and the consequences and effects of a spill could be devastating on the resources that support the Haisla Nation way of life, and would therefore have significant adverse effects on Haisla Nation culture and cultural heritage and aboriginal rights.

6. Risk assessments and technology have not overcome the potential for human error, wherein it is well established that 80% of oil tanker accidents that cause oil spills at sea are a result of human errors: badly handled manoeuvres, neglected maintenance, insufficient checking of systems, lack of communication between crew members, fatigue, or an inadequate response to a minor incident
causing it to escalate into a major accident often resulting in groundings and collisions (http://www.black-tides.com/uk/source/oil-tanker-accidents/causes-accidents.php). It has also become increasingly obvious that maintenance of pipeline integrity and the remote detection of pipeline ruptures is inadequate as exemplified by major environmental damage from recent pipeline ruptures in Michigan and Alberta.

7. The proposed project requires the alienation of Haisla Nation aboriginal title land, and the federal government has refused to engage in consultation with the Haisla Nation about the potential impacts of the proposed project on Haisla Nation aboriginal rights, including aboriginal title.

8. The proposed project would require the use of Haisla Nation aboriginal title land for a purpose that is inconsistent with Haisla Nation stewardship principles and with the Haisla Nation’s own aspirations for this land.

9. For the reasons set out above, the proposed project would constitute an unjustified infringement of Haisla Nation aboriginal title and rights. It would therefore be illegal for the Crown to authorize the project.

Canada is obliged to decline approval of the project

Up until now, the federal government has refused to engage First Nations in the northwestern region over the issue of the Northern Gateway pipeline and terminal, saying that the constitutionally mandated consultation will take place after the Joint Review Panel has released its report. However, the government’s Bill C-38, which gives the federal cabinet (actually the prime minister) the power to decide the pipeline means that the JRP report will be less significant than it would have been before the Conservatives gained a majority government in May, 2010.

The Haisla say the nation has “repeatedly requested early engagement by federal government decision-makers to develop, together with the Haisla Nation, a meaningful process for consultation and accommodation in relation to the proposed project.”

The filing says JRP and “the federal government’s ‘Aboriginal Consultation Framework’ have been imposed on the Haisla Nation and other First Nations, with significant aspects of the concerns expressed by the Haisla Nation about this approach being ignored.”

The Haisla says it “continues to seek a commitment from the federal government to the joint development of a meaningful process to assess the proposed project and its potential impacts on Haisla Nation aboriginal rights, including aboriginal title.”

Later in the filing the Haisla say:

The Haisla Nation has…  repeatedly asked federal decision-makers to commit to the joint development of a meaningful consultation process with the Haisla Nation. The federal Crown decision-makers have made it very clear that they have no intention of meeting with the Haisla Nation until the Joint Review Panel’s review of the proposed project is complete…

The federal Crown has failed to provide any clarity, however, about what procedural aspects of consultation it has delegated to Northern Gateway. Northern Gateway has not consulted with the Haisla Nation and has not advised the Haisla Nation that Canada has delegated any aspects of the consultation process.

The Haisla then go on to say:

Canada is legally required to work with the Haisla Nation to develop and follow such a process. If the process establishes that the approval of the proposed project would constitute an unjustified infringement of Haisla Nation aboriginal rights or aboriginal title, then Canada would be legally obliged to decline approval.

Deficiencies and Conditions

Enbridge asked the Haisla that if there are conditions of approval that would nonetheless
address, in whole or in part, the Nation’s concerns; and then asked for details “on the nature of any conditions that the Haisla Nation would suggest be imposed on the Project, should it be approved.”

The Haisla reply that because there are “significant deficiencies in the evidence provided by Northern Gateway to date.” The nation goes on to say that “the acknowledged risks that have not been adequately addressed in the proposed project.” The Haisla Nation then says it “does not foresee any conditions that could be attached to the project as currently conceived and presented that would eliminate the Haisla Nation’s concerns.”

The Haisla then repeat that Enbridge has not provided sufficient information so that

it is difficult for the Haisla Nation to identify conditions to attach to the proposed project as it is still trying to fully understand the potential impacts of the project and the proposed mitigation. This is primarily because there is insufficient information provided by Northern Gateway in its application material.

Although we have attempted to elicit additional information through the JRP’s information request process, Northern Gateway has not provide adequate and complete answers to the questions posed.

The Haisla then anticipate that Stephen Harper will force the pipeline and terminal on British Columbia and say:

Nevertheless, if the project were to be approved AFTER the Crown meaningfully
consulted and accommodated the Haisla Nation with respect to the impacts of
the proposed project on its aboriginal title and rights, and if that consultation were
meaningful yet did not result in changes to the proposed project, the following
conditions would, at a minimum, have to be attached to the project.

The emphasis of the word “after” is in the original document.

The document that then goes on to present an extensive list of list of conditions the Haisla believe should be imposed on the Enbridge Northern Gateway if the project goes ahead.

The conditions include comprehensive monitoring of water quality, fisheries, wildlife and birds, vegetation throughout the Kitimat River watershed, Kitimat Arm and Douglas Channel; development of comprehensive spill response capability throughout the Kitimat River Valley, Kitmat Arm and Douglas Channel.

The Haisla also want soil and erosion control plans; water management plans; control and storage plans for fuels, lubricants and other potential contaminants; detailed plans for equipment deployment and habitat reclamation of disturbed or cleared areas.

The Haisla also want much more detailed studies before any construction, including analysis of terrain stability and slide potential throughout the pipeline corridor and at the storage tank and terminal site; engineering designs to mitigate seismic risk and local weather extremes; development of pipeline integrity specifications and procedures including best practices for leak detection; storage tank integrity specifications, maintenance and monitoring; assessment of spill containment, spill response and spill capacity requirements throughout the Kitimat River watershed, Kitimat Arm and Douglas Channel.

On tankers the Haisla want more details beyond the plans already filed by Enbridge including
detailed tanker specifications, detailed tanker and tug traffic management procedures; detailed port management specifications and procedures including operating limits for tanker operation, movement and docking.

The Haisla are also demanding “on going consultation” on all issues involved by the National Energy Board prior to any decision on any changes to or sign off on conditions and commitments to any certificate that is issued.

The Haisla want an independent third party be part of a committee to oversee the construction proecess to monitor certificate compliance during construction of the marine terminal and the pipeline.

Once the pipeline and terminal operational, the Haisla want conditions imposed on the project that include ongoing monitoring of the terrain along the pipeline, a system that would automatically shut down the pipeline shutdown whenever a leak detection alarm occurs.

The Hasila want conditions “on the disposal of any contamination that must be removed as
a result of an accident or malfunction resulting in a spill that will minimize additional habitat destruction and maximize the potential for regeneration of habitat and resources damaged by the spill.”

As well as more detailed parameters for the tankers, tugs, and pilotage procedures, the Haisla want approval of any future changes in those procedures.

The Haisla are also concerned about the “alienation” of a large area of their traditional territory by the construction of the Northern Gateway project as well as the “additional infrastructure” required by adequate spill response capability and spill response equipment cache sites.

The Haisla say “all of the land alienations required for the proposed project would profoundly
infringe Haisla Nation aboriginal title which is, in effect, a constitutionally protected ownership right” and goes on to say “proposed project would use Haisla Nation aboriginal title land in a way that is inconsistent with Haisla Nation stewardship of its lands, waters and resources and with the Haisla Nation’s own aspirations for the use of this land.”

The Haisla filing then goes on to say:

Since aboriginal title is a constitutionally protected right to use the aboriginal title land for the purposes the Haisla Nation sees fit, this adverse use would fundamentally infringe the aboriginal title of the Haisla Nation.

The report also expresses concerns about the ongoing socio-economic affects of such a large project.

It concludes by saying:

These issues are important. They go to the very heart of Haisla Nation culture.
They go to the Haisla Nation relationship with the lands, waters, and resources of
its Territory. A major spill from the pipeline at the marine terminal or from a
tanker threatens to sever us from or damage our lifestyle built on harvesting and
gathering seafood and resources throughout our Territory.

Northern Gateway proposes a pipeline across numerous tributaries to the Kitimat
River. A spill into these watercourses is likely to eventually occur. The evidence
before the Panel shows that pipeline leaks or spills occur with depressing
regularity.

One of Enbridge’s own experiences, when it dumped 3,785,400 liters of diluted
bitumen into the Kalamazoo River, shows that the concern of a spill is real and
not hypothetical. A thorough understanding of this incident is critical to the
current environmental assessment since diluted bitumen is what Northern
Gateway proposes to transport. However, nothing was provided in the application
materials to address the scope of impact, the level of effort required for cleanup
and the prolonged effort required to restore the river. An analysis of this incident
would provide a basis for determining what should be in place to maintain
pipeline integrity as well as what should be in place locally to respond to any spill.

The Kalamazoo spill was aggravated by an inability to detect the spill, by an
inability to respond quickly and effectively, and by an inability to predict the fate
of the diluted bitumen in the environment. As a result, the Kalamazoo River has
suffered significant environmental damage. The long-term cumulative
environmental damage from this spill is yet to be determined.

Looking to the future, the Haisla are also asking for a plan for the eventual decommissioning of the project, pointing out that “ Northern Gateway has not provided information on decommissioning that is
detailed enough to allow the Haisla Nation to set out all its concerns about the
potential impacts from decommissioning at this point in time.”

Haisla leaders have already expressed concern about the legacy of the Eurocan paper plant. Now it tells Enbridge

This is not good enough. The Haisla Nation needs to know how Northern Gateway proposes to undertake decommissioning, what the impacts will be, and that there will be financial security in place to ensure this is done properly.

Asserts aboriginal title

The section of the report concludes by saying:

The Haisla Nation asserts aboriginal title to its Territory. Since the essence of
aboriginal title is the right of the aboriginal title holder to use land according to its
own discretion, Haisla Nation aboriginal title entails a constitutionally protected
ability of the Haisla Nation to make decisions concerning land and resource use
within Haisla Nation Territory. Any government decision concerning lands,
waters, and resource use within Haisla Nation Territory that conflicts with a
Haisla lands, waters or resources use decision is only valid to the extent that the
government can justify this infringement of Haisla Nation aboriginal title.

The Supreme Court of Canada has established that infringements of aboriginal
title can only be justified if there has been, in the case of relatively minor
infringements, consultation with the First Nation. Most infringements will require
something much deeper than consultation if the infringement is to be justified.
The Supreme Court has noted that in certain circumstances the consent of the
aboriginal nation may be required. Further, compensation will ordinarily be
required if an infringement of aboriginal title is to be justified [Delgamuukw].

The Haisla then go on to say that the preferred use of the land in question is for the liquified natural gas projects:

The Haisla Nation has a chosen use for the proposed terminal site. This land
was selected in the Haisla Nation’s treaty land offer submitted to British Columbia
and Canada in 2005, as part of the BC Treaty Negotiation process, as lands
earmarked for Haisla Nation economic development.

The Haisla Nation has had discussions with the provincial Crown seeking to
acquire these lands for economic development purposes for a liquefied natural
gas project. The Haisla Nation has had discussions with potential partners about
locating a liquefied natural gas facility on the site that Northern Gateway
proposes to acquire for the marine terminal. The Haisla Nation sees these lands
as appropriate for a liquefied natural gas project as such a project is not nearly
as detrimental to the environment as a diluted bitumen export project.

Northwest Coast Energy News is attempting to contact Enbridge Northern Gateway for comment on the Haisla filing. Response may be delayed by the Canada Day holiday.

 

Haisla Nation Response to NGP Information Request  (pdf)

The Enbridge Empire Strikes Back II: The Haisla “fishing expedition”

Kitamaat Village dock
The Kitamaat Village dock seen on June 27, 2012. Enbridge has filed questions asking the Haisla what they know about current vessel traffic on Douglas Channel. (Robin Rowland/Northwest Coast Energy News)

A series of questions filed by Enbridge Northern Gateway with the Joint Review Panel appear to be a “fishing expedition” to find out not only what the Haisla Nation feel about the Northern Gateway project but also seeks details of Haisla agreements with the various Kitimat liquified natural gas projects.

In its May filing, Enbridge asks the Haisla Nation 28 pages of questions, many of them political, and also try to find out the sources of funding the Haisla Nation is using for its participation in the Northern Gateway Joint Review process, questioning the credentials of the experts hired by the Haisla and are likely setting up the First Nation for Enbridge’s propaganda campaigns about current vessel traffic on the Douglas Channel.

( See: The Empire Strikes Back I: Enbridge takes on First Nations, small intervenors )

On May 11, Enbridge filed a series of questions with 24 intervenors and First Nations asking detailed questions not only about the technical issues raised by those groups but also their funding sources and their political actvity.

In its questions to the Haisla Nation, Enbridge asks a series of technical questions around the questions of “acceptable risk” and it appears, despite the fact Enbridge officials have listened to the Haisla official presentation at Kitamaat Village last January (and the speeches of Haisla members this week at the pubic comment hearings) that Enbridge is preparing to use a paper-based or Alberta-based concept of “acceptable risk,” as opposed to listening to the First Nation that will be most directly affected by any disaster in the Kitimat harbour or estuary.

The first questions Enbridge asks the Haisla Nation are blunt, and again, appear to contradict what Enbridge has been saying about First Nations agreeing to back the pipeline.

(a) Please confirm that the Haisla Nation opposes the approval of Northern Gateway’s Application for the Project.(b) If the Haisla Nation opposes the approval of the Application, please advise as to whether there are conditions of approval that would nonetheless address, in whole or in part, the Nation’s concerns.

(c) If so, please elaborate on the nature of any conditions that the Haisla Nation would suggest be imposed on the Project, should it be approved.

(d) Please summarize the effects that the Haisla Nation considers would be created by the Project, should it be approved and constructed. Include both positive and negative effects.

(e) Please describe the mitigation measures proposed by the Haisla Nation (if any) to reduce potentially adverse Project effects on the Haisla Nation’s rights and interests.

Another section of questions asks about the funding Haisla may or not be receiving.
The Haisla Nation has expressed the view that inadequate funding has been provided to participate in this proceeding.

Request:
(a) Please confirm that the Haisla Nation has received participant funding from the Canadian Environmental Assessment Agency to participate in this proceeding.
(b) Please advise as to the amount of participant funding received to date from the Canadian Environmental Assessment Agency.
(c) Please confirm that the Haisla Nation has received significant funding from the Northern Gateway Project for the purpose of preparing traditional use studies in relation to this Project.
(d) Please advise as to the amount of funding received by the Haisla Nation from any other external sources to participate in this proceeding, or otherwise oppose the Northern Gateway Project.
(e) Is the Haisla Nation a member of the Turning Point/Great Bear Initiative?
(f) Has the Haisla Nation received funding, directly or indirectly, from the Turning Point/Great Bear Initiative for the purpose of participating in this proceeding, or otherwise opposing the Northern Gateway Project? If so, how much funding was received?
(g) Has the Haisla Nation received funding from Tides Canada or any similar organization for the purpose of participating in this proceeding or otherwise opposing the Northern Gateway Project? If so, how much funding was received and from whom?
(h)Have any members of the Kitimaat Village Council received funding from Tides Canada or similar organizations to participate in this proceeding or to otherwise oppose the Northern Gateway Project, either directly or indirectly? If so, how much funding was received and by whom? Please include funding received by the Headwaters Initiative in this response.
(i) Are there agreements or understandings in place as between coastal First Nations whereby no
coastal First Nation will oppose LNG development supported by the Haisla First Nation, and no coastal First Nation, including the Haisla First Nation, will support the Northern Gateway Project?

Enbridge then goes on a fishing expedition to find out more about their agreements with the LNG projects.

Position Regarding LNG Projects 1.5
Reference:
(i)
Kitimat LNG, News Release, “Canada, BC, Join Haisla Nation and Kitimat LNG Partners in Marking
Project Go-Ahead; ‘A Very Big Day for Our People’ Says Chief Councillor Pollard” (9 March
2011)
online: Kitimat LNG
<http://mediacenter.kitimatlngfacility.com/Mediacenter/view_press_release.as
px?PressRelease.ItemID=2807>.
(ii) Dina O’Meara, “National regulator approves BC LNG export licence Co-operative
a partnership with Haisla First Nation”, The Calgary Herald (3 February 2012) online The Calgary Herald <http://www.calgaryherald.com/business/National+regulator+approves+export+
licence/6093310/story.html>.

Preamble:
Northern Gateway would like to confirm the Haisla Nation’s position with respect to certain liquefied
natural gas (“LNG”) projects.

Request: (a) Please confirm that the Haisla Nation supports construction and operation of the Kitimat LNG Project (also known as the KM LNG Project).
(b) Please confirm that Kitimat LNG holds an export licence to ship 200 million tonnes of LNG over  20 years from the Kitimat LNG Terminal, to be located at Bish Cove, near the Port of Kitimat, BC, to Pacific Rim markets by marine vessel.

(Note since the National Energy Board approved the export licence, and that is available on the NEB site, why is Enbridge asking the Haisla and the NEB to provide information that is so readily available?)


(c)Please provide copies of all environmental assessment studies, risk assessments, TERMPOL review studies and Aboriginal Traditional Knowledge (“ATK”) studies pertaining to the Kitimat LNG Project. If such studies do not currently exist, please advise when they will be completed and provided. If confidentiality concerns exist in respect of the ATK study, please indicate whether the Haisla Nation is prepared to provide it to the Panel in confidence.
(d) Please provide copies of all agreements that the Haisla Nation has entered into with Kitimat LNG including, impact benefit agreements and lease agreements.
(e) Please confirm that the Haisla Nation supports construction and operation of the BC LNG Export Cooperative Project.
(f) Please confirm that the Haisla Nation is a joint venturer or partner with LNG Partners of Houston, in the BC LNG Export Cooperative.
(g) Please confirm that the BC LNG Export Cooperative holds an export licence to ship 36 million
tonnes of supercooled natural gas over 20 years from floating terminal off Kitimat, BC to
Pacific Rim markets by marine vessel.
(Again this information is publicly available on the NEB website, so why is Enbridge asking the question?)
(h) Please provide copies of all environmental assessment studies, risk assessments, TERMPOL review studies and ATK studies pertaining to the BC LNG Export Cooperative Project. If such studies do not currently exist, please advise when they will be completed and provided. If  confidentiality concerns exist in respect of the ATK study, please indicate whether the Haisla Nation is prepared to provide it to the Panel in confidence.
Position Regarding Kitimat – Summit Lake Pipeline Looping Project
1.6  Reference: (i) BC Environmental Assessment Office, “Kitimat

Summit Lake Pipeline Looping Project Assessment Report With Respect to Review of the Application for an Environmental Assessment Certificate Pursuant to the Environmental Assessment Act, S.B.C. 2002, c. 43” (12 May 2008) at page 7, online: BC Environmental Assessment Office
<http://a100.gov.bc.ca/appsdata/epic/documents/p270/1214599791218_8e248
a8d30d995f6590f6f694d7789f6e20e141ef52b.pdf>.

(i) states: “The Haisla Nation wrote to the EAO indicating that they support the Project receiving a Provincial EA Certificate, subject to certain conditions (which are being
met).” Reference (ii) provides a First Nations Consultation Report in respect of the Haisla Nation.
Request:
(a) Please confirm that the Haisla First Nation supports the construction and operation of the Pacific Trails Pipeline Project (also known as the Kitimat-Summit Lake Looping Project).
(b)
Please confirm that Reference (ii) accurately describes the nature and strength of claim by the Haisla First Nation in respect of those portions of the Kitimat-Summit Lake Looping Project that will traverse Haisla traditional territory.
(c) Please confirm that
(ci) Reference (ii) lists the mitigation measures proposed by the Kitimat-Summit Lake Looping Project to address construction-related impacts on Haisla First Nation traditional territory, and that such measures are acceptable to the Haisla First Nation. If any such measures are not acceptable, please identify them and advise as to modifications considered appropriate by the Haisla First Nation.

(d) Please advise as to whether similar measures would be requested by the Haisla First Nation to deal with construction-related impacts of the Northern Gateway Project.
(e) Please file a copy of the report entitled Haisla Traditional Use and Occupancy of the Proposed PNG Pipeline Corridor through the lower Kitimat River Valley cited on page 124 of Reference
(ii).] If confidentiality concerns exist in respect of the study, please indicate whether the Haisla are prepared to provide it to the Panel in confidence.

Enbridge also asks the Haisla to provide examples of how the Haisla Nation currently regulates,
or purports to regulate, vessel movements within its Traditional Territory.

(c) Please confirm that the Haisla Nation is aware of existing and proposed marine vessel activity within its Traditional Territory, including:
(i) fuel barges
(ii) cargo/container ships
(iii) commercial fishing vessels
(iv) condensate tankers
(v) liquefied natural gas tankers

On its website Northern Gateway claims

According to numbers from the Port of Kitimat, not only have vessels carrying industrial products been travelling the channels safely for some 35 years, but so too have ships carrying petroleum products—like the one featured arriving in the Port of Kitimat through the Douglas Channel in the picture above.
In fact, some 1,560 vessels carrying methanol and condensate called on Kitimat port from 1982 to 2009 – that’s over 3,100 transits of vessels dedicated to the transport of petroleum products.
When you add vessel traffic of all industrial activity into Kitimat port, the number jumps to 6,112.
To be clear…the number of ships servicing industry arriving at Kitimat port between 1978 and 2009 is 6,112. That’s 12,224 transits!

This Enbridge propaganda campaign has been quite successful in Alberta, leading to constant tweets over the past year, mostly from Albertans such as this one from

@jeffreylowes “Tanker traffic in Kitimat today” So I wonder what the problem is? #northerngateway #cdnpoli http://t.co/w38dt7KA

(Lowes’ Twitter profile describes him as Director of Government & Industrial Relations at MREP Communications A Social Conservative, Opinions are my own. RTs not necessarily endorsements.)

That page is frequently cited on Twitter, again mostly by tweeters from Alberta and Saskatchewan who have never been within 1,000 kilometres of the the BC coast as justification for the increased tanker traffic.

Ellis Ross
Haisla Nation Chief Counselor Ellis Ross testifies before the Northern Gateway Joint Review Panel at Kitamaat Village, January 10, 2012 (Robin Rowland/Northwest Coast Energy News)

Countering the Enbridge propaganda, at least in BC, but largely ignored in the rest of Canada,  was the eloquence of the Haisla elders at the January 2012 hearings in Kitimat which described the destruction of the local environment by 60 years of industrial development and the testimony of Haisla Chief Counsellor Ellis Ross about the major problems caused by a relatively minor spill in Kitimat harbour.

In addition, many of those who testified at this week’s public comment hearings, noted the difference between the current vessel traffic—no supertankers or Very Large Crude Carriers have yet sailed Douglas Channel and the fears of the vast increase in tanker traffic that will happen if all the various projects including LNG and Enbridge go ahead.

Many of the remaining questions to the Haisla are highly technical responses to their questions or filings with the Joint Review Panel.

 

Enbridge Information request to the Haisla (pdf)

 

The Empire Strikes Back I: Enbridge takes on First Nations, small intervenors

Douglas Channel
Douglas Channel at the site of the proposed Enbridge marine terminal, June 27, 2012. (Robin Rowland/Northwest Coast Energy News)

Enbridge is striking back against the First Nations and intervenors who oppose the Northern Gateway pipeline and marine terminal projects by filing questions that those groups must answer as part of the Joint Review Process.

On May 11, 2012, Enbridge filed questions with 24 organizations,  and from the questions, it appears that Enbridge isn’t  just building a strictly legal case in their favour but are preparing to try and discredit opponents.

Enbridge’s questions are part of the legal process. For months, First Nations and intervenors have been filing a whole series of questions asking for clarification of items in the Enbridge’s filings on the project with Joint Review Process and Enbridge has the legal right to ask the First Nations and intervenors to clarify their positions.

However, the difference is that Enbridge is a giant corporation which can afford to spend millions of dollars on both the approval process as well as the current nationwide advertising process, while some of the intervenors are made up of volunteers or retirees working on their own time. Sources among the intervenors have been saying for months that they believe that Enbridge is following a perceived policy of working to wear down the opponents so much they burn out and drop out of the process.

A large proportion of the questions Enbridge is demanding that First Nations and intervenors answer are overtly political, rather than technical responses to their filings.

In an apparent escalation of its campaign against its opponents, Enbridge is using the Joint Review process to ask intervenors about funding, naming such hot button organizations such as Tides Canada, which is under attack by the Harper government.  Enbridge is also  questioning  the “academic credentials” of numerous intervenors and commenters, even though the Joint Review Panel has spent most of the past seven months asking people to comment based on “local knowledge,” leaving the technical questions to the documents filed with the JRP

Some key questions directed at both the Haisla and Wet’suwet’en First Nations seem to indicate that Enbridge is preparing to build both a legal and probably a public relations case questioning the general, but not unanimous support for liquified natural gas projects in northwestern BC, by saying “Why not Northern Gateway,” as seen in this question to the Haisla Nation.

Please advise as to whether similar measures would be requested by the Haisla First Nation to deal with construction-related impacts of the Northern Gateway Project.

Black Swan

A series of questions to the coalition known as the Coastal First Nations questions the often heard assertion that an oil spill on the BC coast is “inevitable,” and Enbridge appears to be prepared to argue that spills are not inevitable. Enbridge asks Coastal First Nations about a study that compared the bitumen that could be shipped along the coast with the proposed LNG projects.

Please provide all environmental and risk assessment studies, including studies of “Black Swan” events, conducted by the Coastal First Nations or any of its members in respect of the LNG projects referred to.

Enbridge is referring to Nassim Nicholas Taleb’s now widely known “theory of high-impact, hard-to-predict, and rare events that are beyond the realm of normal expectations in history, science, finance and technology.”

It is Black Swan events that most of the people of the northwest coast fear when it comes to all the major energy projects, but if as Taleb says they are hard-to-predict and rare, how can the studies Enbridge is requesting actually predict those disasters?

Enbridge’s questions to the Haisla Nation runs for 28 pages and many of those questions are political, not technical, including asking for details of the Haisla support for the various Kitimat liquified natural gas projects and who may be funding the Haisla participation in the Joint Review Process. Many technical questions around the questions of “acceptable risk” and it appears, despite the fact Enbridge officials have listened to the Haisla official presentation at Kitamaat Village last January and the speeches of Haisla members this week at the pubic comment hearings, that Enbridge is preparing to use a paper-based or Alberta-based concept of acceptable risk as opposed to listening to the First Nation that will be most directly affected by any disaster in the Kitimat harbour or estuary.

(See The Enbridge Empire Strikes Back II The Haisla “fishing expedition”)

A series of questions seems to negate Enbridge’s claim that it has the support of many First Nations along the pipeline route because Enbridge is asking for details of agreements that First Nations have reached with the Pacific Trails Pipeline. Enbridge has consistently refused to release a list of the First Nations it claims has agreements with the company, but in the questions filed with the JRP, Enbridge is asking for details of agreements First Nations in northern BC have reached with the Pacific Trails Pipeline.

Funding demands

For example, while Enbridge is refusing to name all the backers of the pipeline for reasons of corporate confidentiality, the company is asking who may be funding the Wet’suwet’en First Nation in its appearances before the Joint Review Panel, including the US-based foundations named by right-wing blogger Vivian Krause,  (note Krause recently declared victory and suspended her blog) right-wing columnists and the Harper cabinet:

Please confirm that the Office of the Wet’suwet’en has received participant funding from the Canadian Environmental Assessment Agency to participate in the Joint Review Panel (“JRP”) proceeding.

Please advise as to the amount of participant funding received to date from the Canadian Environmental Assessment Agency.

Please advise whether or not the Office of the Wet’suwet’en has received funding within the
last 5 years from Tides Canada, the Gordon and Betty Moore Foundation, the William and Flora Hewlett Foundation, or any other similar foundations, to oppose the Northern Gateway Project or to oppose oil sands projects in general.

If so, please provide the amount of funding received from each foundation.

In the case of the Raincoast Conservation Foundation, Enbridge is asking for details, including a membership list.

Please provide a description of the Raincoast Conservation Foundation.

Does the Raincoast Conservation Foundation prepare Annual Reports? If so, please provide the most recently published Annual report available.

If the Raincoast Conservation Foundation is a collection of like-minded individuals, please list its members.

Did the Raincoast Conservation Foundation apply for and receive participant funding in this proceeding? If so, how much was received?

While many of Enbridge’s question to the RainCoast Foundation are technical, the company which is currently conducting a multi-million dollar public relations campaign in favour of the pipeline, asks:

Please confirm that the “What’s at Stake? study” was prepared for use as a public relations tool, to advocate against approval of the Northern Gateway.

Enbridge also appears to be gearing up for personal attacks on two of the most vocal members of Kitimat’s Douglas Channel Watch, Murray Minchin and Cheryl Brown, who have been appearing regularly before District of Kitimat council to oppose the Northern Gateway pipeline.

 

Murray Minchin
Murray Minchin of Douglas Channel Watch addresses protesters at Kitimat City Centre Mall, Sunday, June 24, 2012, He talked about how he has learned as he goes along in examining Enbridge documents (Robin Rowland/Northwest Coast Energy News)

Credentials

On Murray Minchin, Enbridge asks:

Written Evidence Regarding Proposed Liquid Petroleum Pipelines from the proposed Nimbus Mountain West Portal to the Kitimat River Estuary submitted by Murray Minchin of Douglas Channel Watch…. Supplemental Written Evidence Photographic Evidence Regarding Proposed Liquid Petroleum Pipelines from Nimbus Mountain to the Kitimat River Estuary submitted by Murray Minchin of Douglas Channel Watch….

Mr. Minchin provides extensive opinion relative to geotechnical and other technical matters. Request: Please provide Mr. Minchin’s curriculum vitae which includes his education, training and employment history, to demonstrate his qualifications to provide geotechnical and other technical opinions that appear….

Minchin is one of Enbridge’s strongest opponents in Kitimat and in his various appearances (the latest at the anti-Enbridge demonstration in Kitimat on Sunday, June 24, 2012, Minchin has told the audiences that he is self-taught and has spent much of his spare time over the past few years studying the documents Enbridge has filed with the JRP.

As for Cheryl Brown, a vocal critic of the Enbridge Community Advisory Board process, Enbridge has filed a long series of questions about her involvement with the CAB, including asking how many meetings she has attended (see document below)

Two of Enbridge’s questions about Brown stand out

Has Ms. Brown offered a suggestion for a speaker that would have provided a differing viewpoint from those of Northern Gateway?

Many people in Kitimat, not just the outspoken members of Douglas Channel Watch, say they do not trust the Community Advisory Board process. When the CAB held a meeting recently to discuss marine safety, a meeting that was heavily advertised in Kitimat Terrace area, the CAB facilitators ( from a Vancouver -based company) attempted to bar the media, including this reporter, from this “public” meeting, until apparently overruled by Enbridge’s own pubic relations staff. On the other hand, everytime Douglas Channel Watch has appeared before the District of Kitimat Council to request a public forum on Gateway issues, DCW has always insisted that Enbridge be invited to any forum, along with DCW and independent third parties.

Ms. Brown states that Enbridge has not addressed the hard questions. Please confirm that Northern Gateway responded to questions put forth by the Douglas Channel Watch in Letters to the Editor in both the Kitimat Northern Sentinel and Terrace Standard in August of 2009.

Here Enbridge appears to be basing its case on one letter to the editor that appeared in local papers three years ago. During the public comment hearings that the JRP held at Kitamaat Village earlier this week, numerous people testified time and time again that Enbridge was failing to answer major questions about the pipeline and terminal, by saying that those questions would be answered later, once the project is approved.

Bird watching

In one series of questions, Enbridge is demanding a professional level database from the Kitimat Valley Naturalists, the local birdwatching group. Quoting a submission by the naturalists group, Enbridge asks

Paragraph 2.2, indicates that the Kitimat Valley Naturalists has birding records for the estuary for over 40 years and that Kitimat Valley Naturalists visits the estuary at least 100 times per year.

Paragraph 2.3 indicates the Kitimat Valley Naturalists have local expertise in birds of the Kitimat River estuary as well as other plants and animals that utilize those habitats.

Request: To contribute to baseline information for the Kitimat River estuary and facilitate a detailed and comprehensive environmental monitoring strategy, please provide the long term database of marine birds in and adjacent to the Kitimat River estuary, with a focus on data collected by the Kitimat Valley Naturalists in recent years, and where possible, the methodology or survey design, dates, weather and assumptions for the data collection.

Today the Kitimat Valley Naturalists, three local retirees, Walter Thorne, Dennis Horwood and April Macleod filed this response with the JRP:

Northern Gateway has specifically requested the long-term database of birds occurring over many years within the Kitimat River Estuary. The data we have collected includes monthly British Columbia Coastal Water Survey (BC CWS) and yearly Christmas Bird Counts (CBC). The data from
these bird counts are available on the web or in print form.

For access to BC CWS enter http://www.bsc-eoc.org

For access to CBC data, enter http://birds.audubon.org

Historical results for CBC counts have also been published by the journal American Birds. The earliest CBC count for Kitimat was 1974.

In regard to the long-term database, we have significant numbers of records for the foreshore of the Kitimat River Estuary. The number increases when the larger estuary perimeter is considered. These cover a 40-year period with the majority in the last 20 years. We would be willing to provide this information in a meaningful format.

The Kitimat Valley Naturalists, however, lack the expertise or financial ability to convert the data into a format that would address Northern Gateway’s interest in methodology, survey design, dates, weather, and assumptions for data collection.

Alternatively, we do have access to a consulting firm, which is willing to analyze our data and convert it to a useable and practical design. We assume, since this is a considerable undertaking in both time and cost, that Northern Gateway would be willing to cover the associated fees.

We look forward to hearing back from Northern Gateway and pursuing this with a budget proposal.

Northwest Coast Energy News consulted data management experts who estimated that complying with the Enbridge request would likely cost between $100,000 and $150,000.

First Nations

Some Wet’suwet’en houses have opposed the Pacific Trails Pipeline, and while negotiations with Apache Corporation are continuing, Enbridge is asking the First Nation for details of what is happening with that pipeline.

Is it the position of the Office of the Wet’suwet’en that each First Nation whose traditional territory is traversed by the proposed pipeline has a veto on whether it is approved or refused?

Please confirm that the Office of the Wet’suwet’en opposed approval of the Pacific Trails Pipeline (also known as the Kitimat Summit Lake Looping Project).

Does the Office of the Wet’suwet’en continue to oppose construction of the Pacific Trails Pipeline?

Have the First Nations who are proposing to participate as equity owners in the Pacific Trails Pipeline Project advised the Office of the Wet’suwet’en that they accept that the Office of the Wet’suwet’en has a right to veto approval and construction of that Project?

Please confirm that the First Nations holding an equity ownership position or entitlement in the Pacific Trails Pipeline Project (also known as the Kitimat-Summit Lake Looping Project) include:
• Haisla First Nation
•Kitselas First Nation
•Lax Kw’alaams Band
•Lheidli T’enneh Band
•McLeod Lake Indian Band
•Metlakatla First Nation
•Nadleh Whut’en First Nation
•Nak’azdli Band
•Nee Tahi Buhn Band
•Saik’uz First Nation
•Skin Tyee First Nation
•Stellat’en First Nation
•Ts’il Kaz Koh First Nation
•West Moberly First Nation
•Wet’suwet’en First Nation

The majority of questions filed with the Coast First Nations are technical challenges to studies filed by the coalition. Enbridge also filed questions with the Gitga’at, Gitxaala, Heiltsuk Nations and the Metis Nation of Alberta.

(Disclosure: The author, who is also a photographer, sometimes accompanies members of the Kitimat Valley Naturalists to photograph birds during the time they are doing the counts)

Enbridge Cover letter to JRP Information Requests to Intervenors (pdf)

Information Request Coastal First Nations (pdf)

Information Request Haisla (pdf)

Information Request Douglas Channel Watch (pdf)

Information Request Living Oceans Society (pdf)

Information Request Raincoast Conservation (pdf)

Information Request Wet’suwet’en (pdf)

Information Request Kitimat Valley Naturalists (pdf)

Kitimat Valley Naturalists response to Enbridge (pdf)

 

TransCanada to build Shell’s “Coastal Gaslink” natural gas pipeline to Kitimat

Trans Canada logoShell Canada and its Asian partners have chosen TransCanada Corporation to design, build, own and operate the proposed natural gas pipline to Kitimat, now called the Coastal GasLink project.

The estimated $4-billion pipeline will transport natural gas from the Montney gas-producing region near Dawson Creek, in northeastern British Columbia to the proposed natural gas export facility at Kitimat, BC.

The LNG Canada project is a joint venture led by Shell, with partners Korea Gas Corporation, Mitsubishi Corporation and PetroChina Company Limited.

A news release from TransCanada says “Shell and TransCanada are working toward the execution of definitive agreements on the Coastal GasLink project.”

In the release, Russ Girling, TransCanada president and CEO says:

Our team has the expertise to design, build and safely operate pipeline systems. We look forward to having open and meaningful discussions with Aboriginal communities and key stakeholder groups, including local residents, elected officials and the Government of British Columbia, where we will listen to feedback, build on the positive and seek to address any potential concerns. Coastal GasLink will add value to British Columbians, particularly Aboriginals and communities along the conceptual route, by creating real jobs, making direct investments in communities during construction and providing economic value for years to come.

TransCanada says the company has approximately 24,000 kilometres of pipelines in operation in western Canada including 240 kilometres of pipelines in service in northeast BC. Another 125 kilometres of proposed additions either already having received regulatory approval or currently undergoing regulatory review. These pipelines form an integral and growing part of TransCanada’s NOVA Gas Transmission Ltd. (NGTL) System, which brings natural gas from Alberta to British Columbia to a hub near Vanderhoof.

Girling said in the release:

TransCanada is a leading energy infrastructure company in North America, with a 60-year history of safe, efficient and reliable operation of our assets and a respect for the communities and environments where we operate. We appreciate the confidence that Shell and its partners have placed in us to build, own and operate this natural gas pipeline in British Columbia. We will work collaboratively with them, Aboriginals and other stakeholders as we launch into the initial phases of consultation and regulatory review.

LNG Canada logo

Project parameters

 

In it’s release TransCanada describes the potential Coastal GasLink pipeline project this way:

  • Receipt point: Near Dawson Creek, BC
  • Delivery point: Proposed LNG Canada facility near Kitimat, BC
  • Product: Natural gas from BC’s abundant Montney, Horn River and Cordova basins and elsewhere from the Western Canada Sedimentary Basin
  • Length of route: Approximately 700 kilometres of large diameter pipe
  • Initial pipeline capacity: In excess of 1.7 billion cubic feet of gas per day
  • Anticipated jobs: Estimated 2000-2500 direct construction jobs over a 2- during construction 3 year construction period
    Estimated cost: Detailed cost information will be developed following completion of project scoping and planning. The current estimate is approximately $4 billion
  • Regulatory process: Applications for required regulatory approvals are expected to be made through applicable BC provincial and Canadian federal processes
  • Estimated in-service date: Toward the end of the decade, subject to regulatory and corporate approvals

Pipeline route

TransCanada says: “The final pipeline route will take into consideration Aboriginal and stakeholder input, the environment, archaeological and cultural values, land use compatibility, safety, constructability and economics.:

Pacific Trails Pipeline
The Pacific Trails Pipeline would go cross country to Kitimat. (PTP)

At this point there are two possible routes for the pipeline west of Vanderhoof. One route would be to follow the existing Pacific Northern Gas route that roughly parallels Highway 16. The second possibility is a cross-country route, which may lead to controversy. The Pacific Trails Pipeline, which would feed the KM LNG partners (Apache, Encana and EOG) goes across the mountains from Smithers. While the PTP project has the approval of most First Nations in the regions, Apache and PTP are still in negotiations with some Wet’suwet’en houses over portions where the pipeline would cross the traditional territory of the houses. The much more controversial Enbridge Northern Gateway pipeline follows a similar cross-country route and faces much stiffer opposition than the Pacific Trails Pipeline, due to the content of that pipeline, mainly diluted bitumen and because, critics say, Pacific Trails managed to secure the most geologically stable cross country route earlier in this decade when the pipeline was originally planned to import, not export, natural gas.

TransCanada says the Coast Gaslink pipeline will also have an interconnection with the existing Nova Gas (NGTL System and the liquid NIT) trading hub operated by TransCanada.  The company says:

A proposed contractual extension of TransCanada’s NGTL System using capacity on the Coastal GasLink pipeline, to a point near the community of Vanderhoof, BC, will allow NGTL to offer delivery service to its shippers interested in gas transmission service to interconnecting natural gas pipelines serving the West Coast. NGTL expects to elicit interest in and commitments for such service through an open season process in late 2012.

That means that the Asian customers will not be just dependent on natural gas from northeast British Columbia.  Instead the “molecules” of natural gas from Alberta will join the stream heading to Kitimat. “Open season” in the energy industry is an auction where potential customers or transporters bid for use the pipeline.

In the release Girling says:

The potential Coastal GasLink pipeline project will allow British Columbians, and all Canadians, to benefit from the responsible development of valuable natural gas resources and will provide access to new markets for that gas. The project will also create substantial employment opportunities for local, skilled labourers and businesses as part of our construction team,” concluded Girling. “We know the value and benefits that strong relationships in British Columbia can bring to this project and we look forward to deepening those ties as our extensive pipeline network grows to meet market and customer needs.

TransCanada Corp. is no stranger to controversy, the company is the main proponent of the Keystone XL pipeline from Alberta to the US Gulf Coast. Portions of that pipeline were put on hold by President Barack Obama pending further review and Keystone has become a hot issue in the current American presidential election.

Anti-Enbridge group adopts Quebec students’ “red square” campaign

An anonymous group opposing the Enbridge Northern Gateway pipeline is calling for a demonstration at the site of an oil and gas export conference in Vancouver on May 30 and 31 and asking participants to wear the red square that has become symbolic of the Quebec student protests first against tuition fee hikes and later against Bill 78 aimed at controlling demonstrations in the province.

A notice posted on the website Infoshop News, which describes itself as an anarchist news service, calls for the demonstration at the Four Seasons hotel in Vancouver, site of the Canada Oil and Gas Export Summit. The notice is being widely circulated on Twitter.

The notice adds: “Don’t forget your red squares. Let’s bring the Maple Spring to BC and join Quebec students in opposing the 1% agenda of austerity and environmental destruction.”

Calling the demonstration, “Green Jobs, Not Oil Spills,” the notice says:  “On May 30th/31st the 1% are meeting at the Four Seasons hotel for a two day conference to plot their strategy for Exporting raw tar sands bitumen across BC and overseas to China via pipelines and super tankers.”

The website for the Canadian Oil and Gas Export Summit,  says “The oil and gas industry is at a critical crossroads and now is the time to take a hard look to alternative outlets for Canadian oil and gas,” meaning alternative markets to the United States.  The energy companies are worried about the future of  their American market share due to the effect of political gridlock on the US economy and the growing exploitation of American shale gas deposits which are cutting into Canadian export markets.

The site says the conference highlights include:

  • The latest updates on opening new market opportunities – Moving Canada oil and
    gas exports beyond U.S. markets
  • The impact of the U.S. pipeline decision on the Canadian oil and gas sector
  • The benefits for Canadian producers to tap into Asian markets and
    addressing the perceptions of the two markets
  • The most cost effective strategies of getting to market in light of opposition
  • Infrastructure requirements necessary for accessing Canada’s East and West Coast
  • The legal and regulatory issues surrounding west coast energy corridors, terminals and
    shipping in British Columbia

The conference speakers will tackle a large number of hot button issues in BC, from the energy industry point of view: Paul Fisher, vice present, Commercial, Western Access for Enbridge Pipelines speaks on “Exploring Canada’s Ability to Compete in a Global Marketplace.” Gordon Houlden, Director of the China Institute at the University of Alberta, has a talk touching on “Balancing the complexities of unresolved land claims, environmental and infrastructure issues and the economic development of Western Canada.” Tracy Robinson, Vice President Marketing & Sales, Canadian Pacific Railway, speaks on exporting crude by rail. Douglas Ford, of Communica Public Affairs Inc. handles a large number of issues from the PR point of view, including “the regulatory processes related to British Columbia coastal development,” “the complexity of project development in BC vis a vis First Nations,” with advice on “How to effectively engage community, NGOs, and aboriginal stakeholders.” Van Zorbas of Deloitte Canada speaks about the problems from the current labour shortage.

 

Apache expects first LNG cargo from Kitimat in 2016

Map of Apache Corp LNG projects in the Pacific Region
A map of Apache Corp's liquified natural gas projects, including Ktimat, as presented to the UBS conference on May 22, 2012 (Apache)

Apache said Tuesday, May 22, 2012, that it expects the first LNG cargo leave the Kitimat terminal for Asia sometime in 2016, with possible further expansion in the future.

Patrick Cassidy, director of Apache’s Investor relations division, was making a presentation to the UBS Global Oil and Gas Conference in Houston, Texas, on the company’s future plans.

One slide in the Power Point presentation summed up Apache’s Pacific strategy, both at Kitimat and its chief rival, the Wheatstone project in Western Australia.

Apache said the final investment decision for the first train or phase the Kitimat LNG is still expected later this year. Previous reports have indicated the decision will likely come in the fourth quarter as Apache and its partners line up customers in Asia.

Originally the KM LNG partners said the project would start up in 2015, but delays, including the unusually harsh winter in Kitimat, which slowed construction at the Bish Cove site,  and the search for customers for the natural gas, has pushed the date back to 2016.

Apache  Corp. owns 40 per cent the KM LNG partnership,  Canada’sEncana Corp. and EOG Resources each  own 30 per cent each.

Two other projects are planned for Kitimat, the smaller BC LNG co-owned by Houston-based investors and the Haisla Nation and a larger project announced last week by Royal Dutch Shell.

LINK: Apache presentation to UBS Conference