Enbridge responds to NTSB criticism in e-mail to northwest BC “community leaders”

Enbridge Northern Gateway has issued a detailed reply to the criticism of its operations contained in a preliminary report from the US National Transportation Safety Board to the 2010 oil spill at Marshall, Michigan, which called the company’s response like the silent movie era “Keystone cops.”

The note from Michele Parrett,  Senior Manager, Community and Municipal Relations for Northern Gateway was sent to members of the District of Kitimat Council and presumably other politicians and community leaders along the proposed pipeline route.

The document was among those routinely released to the public at the regular council meeting on Monday, July 16, 2012 and is a much more detailed defence of Enbridge’s position than the news release issued after the NTSB report.

In the e-mail, Enbridge says it has updated its safety and response procedures and its corporate culture since the Michigan incident.

Despite widespread criticism of Enbridge from all sides of the political spectrum, that NTSB report does not seem to have had any impact on federal Environment Minister Peter Kent, who told The Canadian Press had had not yet read the NTSB report. Kent also said that unread report will not change the Conservative government’s mind about the Northern Gateway pipeline project, adding “Pipelines are still, by far, the safest way to transport petrochemicals in any form.”

 


 Overview of NTSB Report  into Line 6B  incident at Marshall, Michigan

July 12, 2012

Dear Community Leader,

I’m writing you today to provide information regarding the United States’ National Transportation Safety Board’s (NTSB) release of its conclusions and recommendations yesterday, with regard to the Enbridge pipeline leak in Marshall, Michigan in July 2010.

Enbridge has not been waiting for the NTSB’s report before furthering to improve our safety standards. Since the incident we have undertaken our own internal investigation and incorporated the findings of that investigation into new practices and processes to improve our safety and reliability.

Enbridge and Enbridge Energy Partners has been working with the NTSB and other regulators throughout the course of the investigation so that we can take the necessary steps to prevent such an accident from occurring again. We are now reviewing the NTSB reports in detail to determine whether any further changes are required.

Enbridge has already implemented, in 2010 and 2011, appropriate operational and procedural changes based on its own detailed internal investigation. Enbridge’s overarching objective and business priority is to ensure the safety and reliability of our delivery systems for the people who live and work near our pipeline systems across North America, our employees and our customers.

In direct response to the Marshall accident, or as part of our ongoing improvement initiatives and activities, Enbridge has taken the following steps:

Pipeline and Facility Integrity

· Further heightened the importance of our pipeline and facility integrity program.

· Re-organized the functional areas that are responsible for pipeline and facility integrity.

· Substantially increased capital and operating budgets associated with maintenance and integrity programs.

· Undertook hundreds of internal inspections and thousands of investigative digs.

· Placed a renewed emphasis on the safety of our overall system.

Leak Detection

· Established the Pipeline Control Systems and Leak Detection department, doubling the number of employees and contractors dedicated to leak detection and pipeline control.

· Enhanced procedures for leak detection analysis.

· Updated control room management procedures.

· Implemented a Leak Detection Instrumentation Improvement Program to add and upgrade instrumentation across our system.

Pipeline Control and Control Centre Operations (CCO)

· Developed a Control Room Management (CRM) plan based on the U.S. Code of Federal Regulations and implemented a number of the sections, October 1, 2011, remaining sections implemented by August 1, 2012.

· Revised and enhanced all procedures pertaining to decision making, handling pipeline start-ups and shutdowns, leak detection system alarms, communication protocols, and suspected column separations.

· Changed organizational structures to better align, focus and manage employees’ span of control and workloads.

· Augmented CCO (Control Centre Operations) staff, adding training, engineering and operator positions.

· We also completed the design and construction of a new, world-class CCO in Edmonton, Alberta which was underway at the time of the accident.

Public Awareness

· Reviewed and strengthened Public Awareness Programs in the U.S. and Canada.

· Developing an industry-leading online and in-person training tool to provide Enbridge-specific information to emergency responders.

· In the U.S, we:

o Formalized the U.S. Public Awareness Committee.

o Improved the Program Effectiveness Evaluation process.

o Provided annual employee training for field employees across the company’s U.S. operations.

o Created a Public Awareness Hotline.

· In Canada, we:

o Formalized the Canadian Public Awareness Committee.

o Are creating a Canadian Public Awareness Database.

o Improved the landowner/tenant database.

o Developed a landowner newsletter.

o Established Community Relations positions in each region.

Emergency Response

· $50 million spent between 2012 and 2013 (projected) to improve our equipment, training and capabilities.

· Develop better tools for waterborne spills.

· In 2011, a cross-business unit response team was created for large-scale events requiring more resources that a single region could provide.

· In 2011, created a dedicated Emergency Response group in Operation Services for increased regional support.

· Conducting an Emergency Response preparedness assessment to enhance abilities to more rapidly respond and contain a significant release.

Safety Culture

· Reinforced a high level of safety and operational integrity across Enbridge in integrity management, third-party damage avoidance and detection, leak detection, incident response capacity, worker and contractor occupational safety, public safety and environmental protection.

· Implemented “Lifesaving Rules” and training for all Enbridge employees and contractors. The Lifesaving Rules are applicable to all employees and contractors, and are communicated, clarified and reinforced across all business units at Enbridge.

· Introduced new Safety Culture training sessions for all employees.

Over the past two years we have made significant improvements in the above areas. The NTSB’s findings will provide us with regulatory guidance and important information to help improve our performance and achieve our goal of zero spills.

We remain committed to a respectful, open and transparent review and discussion of the Northern Gateway Project. Should you have any questions, please do not hesitate to contact me or a member of the Northern Gateway team at the information provided below.

Sincerely,

Michele Perret

Senior Manager, Community and Municipal Relations

Enbridge Northern Gateway Pipelines

Enbridge files massive river oil spill study with the Joint Review Panel

Kitimat River map from Enbridge study
A Google Earth satellite map of the Kitimat River used as part of Enbridge Northern Gateway’s oil spill modelling study.

Enbridge Northern Gateway today filed a massive 11-volume study with the Joint Review Panel outlining possible scenarios for oil spills along the route including the Kitimat and Morice Rivers in British Columbia.

The study, carried out by three consulting firms, Stantec Consuting and AMEC Environmental & Infrastructure both of Calgary and RPS ASA of Rhode Island, is called “Ecological and Human Health Assessment for Pipeline spills.”

Overall the models created by study appear to be extremely optimistic, especially in light of recent events, such as the damning report on by the US
National Transportation Safety Board and the finding of violations by the US Pipeline and Hazardous Material Safety Administration with Enbridge operations during the 2010 Marshall, Michigan, spill and subsequent cleanup difficulties encountered by Enbridge.

The executive summary of the report begins by saying

This document presents conservatively developed assessments of the acute and chronic risk to ecological and human receptors in the unlikely event of a full bore pipeline break on the proposed Enbridge Northern Gateway Pipeline project. Three representative hydrocarbon types (condensate, synthetic oil
and diluted bitumen) were evaluated with releases occurring to four different rivers representing a range of hydrological and geographic characteristics, under both low-flow and high-flow conditions. The analysis indicates that that the potential environmental effects on ecological and human health from each hydrocarbon release scenario could be adverse and may be significant. However, the probability of the releases as considered in the assessment (i.e., full bore rupture, with no containment or oil recovery) is low, with return periods for high consequence watercourses ranging from 2,200 to 24,000 years. Therefore, the significant adverse environmental effects as described in this report are not likely to occur.

So the study says that it is “conservative” that means optimistic, that a full bore pipelink break with no containment or recovery is “an unlikely event” and would probably occur every 2,200 and 24,000 years. Not bad for a pipeline project that is supposed to be operational for just 50 years.

The summary does caution:

The analysis has also shown that the outcomes are highly variable and are subject to a great many factors including the location of the spill, whether the hydrocarbons are released to land or directly to a watercourse, the size of the watercourse, slope and flow volumes, river bed substrate, the amount of suspended particulate in the water, environmental conditions (such as the time of year, temperature and wind speeds, precipitation, etc.), the types of shoreline soils and vegetative cover and most significantly, the type and volume of hydrocarbon released.

The highly technical study is Enbridge’s official response to those intervenors who have “requested additional ecological and human health risk assessment studies pertaining to pipeline spills” and a request from the Joint Review Panle for more information about “the long term effects of pipeline oil spills on aquatic organisms (including the sensitivity of the early life stages of the various salmon species), wildlife, and human health.”

The report presents modelling on the release of three hydrocarbons, diluted bitumen, synthetic oil and condensate at four river locations along the pipeline route for their potential ecological and human health effects, under two flow regimes (i.e., high and low flow), broadly representing summer and winter conditions.

Modelling was done for four areas:

• Chickadee Creek: a low gradient interior river tributary discharging to a large river system
located up-gradient from a populated centre within the Southern Alberta Uplands region
• Crooked River: a low gradient interior river with wetlands, entering a lake system within
the Interior Plateau Region of British Columbia
• Morice River: a high gradient river system along the western boundary of the Interior
Plateau Region of British Columbia
• Kitimat River near Hunter Creek: a high gradient coastal tributary discharging to a large
watercourse with sensitive fisheries resources, downstream human occupation, and discharging to the Kitimat River estuary

In one way, the study also appears to be a partial victory for the Kitimat group Douglas Channel Watch because the model for the Kitimat River is based on a spill at Hunter Creek, which has been the subject of extensive work by the environmental group, but the consulting study is markedly optimistic compared to the scenario painted by Douglas Channel Watch in its presentations to District of Kitimat council.

The study describes the Kitimat River:

The hypothetical release location near Hunter Creek is southwest of Mount Nimbus, in the upper Kitimat  River watershed, and flows into Kitimat River, then Kitimat Arm, approximately 65 km downstream. The area is in a remote location and maintains high wildlife and fisheries values. The pipeline crossing near Hunter Creek is expected to be a horizontal direction drilling (HDD) crossing. The release scenario
assumes a discharge directly into Kitimat River…

The streambed and banks are composed of coarse gravel, cobbles and boulders. Shoreline vegetation (scattered grasses and shrubs) occurs in the channel along the tops of bars. Vegetation is scattered on the channel banks below the seasonal high water mark and more developed (i.e., grasses, shrubs and trees) bove the seasonal high water mark.

Wildlife and fish values for the Kitimat River are high: it is important for salmon stocks, which also provide important forage for grizzly bears, bald eagles and osprey on the central coast. The Kitimat River estuary, at the north end of Kitimat Arm, also provides year-round habitat for some waterbirds and seasonal habitat for staging waterfowl.

There is considerable recreational fishing, both by local people and through fishing guides, on Kitimat River, its estuary and in Kitimat Arm. There is also likely to be a high amount of non-consumptive recreational activity in the area, including wildlife viewing, hiking and camping. The Kitimat River estuary, for example, is well known for waterbird viewing.

While no fish were captured at this location during the habitat survey, salmonoid fry and coho salmon were observed downstream. Previously recorded fish species in the area include chinook, coho and chum salmon, rainbow trout, Dolly Varden, and steelhead trout.

However, the next paragraph appears to show that a full bore rupture on the Kitimat River would have widespread consequences because it would cover a vast area of First Nations traditional territory, saying

Aboriginal groups with traditional territories within the vicinity of the Kitimat River hypothetical spill scenario site include the Haisla Nation, Kitselas First Nation, Kitsumkalum First Nation, Lax-Kw’alaams First Nation and Metlakatla First Nation.

It also acknowledges:

Oral testimony provided by Gitga’at First Nation and Gitxaala Nation was also reviewed in relation to this hypothetical spill scenario, although the traditional territories of these nations are well-removed from the hypothetical spill site.

The report then goes on to list “the continued importance of traditional resources” for the aboriginal people of northwestern BC.

especially marine resources. People hunt, fish, trap and gather foods and plants throughout the area and traditional foods are central to feasting and ceremonial systems. Food is often distributed to Elders or others in the community. Written evidence and oral testimony reported that Coho, sockeye, pink, and spring salmon remain staples for community members. Halibut, eulachon, herring and herring roe,
various species of cod, shellfish, seaweed, and other marine life are also regularly harvested and consumed, as are terrestrial resources, including moose, deer, beaver, muskrat and marten. Eulachon remains an important trade item. Written evidence provides some information on seasonality of use and modes of preparation. Seaweed is dried, packed and bundled and preserved for later use. Each species of
salmon has its own season and salmon and other fish are prepared by drying, smoking, freezing or canning. Salmon are highly valued and often distributed throughout the community…

Some areas used traditionally are not depicted geographically. Upper Kitimat River from the Wedeene River to the headwaters has long been used for trapping, hunting, fishing and gathering of various foods. Fishing, hunting and gathering activities take place along the lower Kitimat River and its tributaries. Marine resources are collected in Kitimat Arm, Douglas Channel, and Gardner Canal. Old village and
harvesting sites are located along the rivers and ocean channels in this vicinity.

Intertidal areas are important and highly sensitive harvesting sites that support a diversity of species. Many intertidal sites are already over harvested and are therefore vulnerable. Conservation of abalone has been undertaken to help the species recover. Some concern was expressed in oral testimony regarding the
potential for archaeological sites and the lack of site inventory in the area. Oral testimony made reference to the Queen of the North sinking and the potential for a similar accident to result in human health and environmental effects.

A spill at Hunter Creek

The model says that all three types of floating oil in Kitimat River under high-flow conditions would reach approximately 40 kilometres downstream from Hunter Creek while low-flow conditions showed variation.

Under what the study calls low flow conditions, most condensate would evaporate. The bitumen would cause “heavy shore-oiling” for the first 10 kilometres, with some oiling up to 40 kilometres downstream.

The most sedimentation would occur for synthetic oil, and the least for condensate. Synthetic oil under both flow conditions would have the largest amounts deposited to the sediments. This is because of the low viscosity of synthetic oil, which allows it to be readily entrained into the water where it may combine with suspended sediments and subsequently settle. Synthetic oil under high-flow conditions would result in the most entrained oil and so the most extensive deposition to the sediment. Diluted bitumen, for both flow conditions, would result in the most deposited on shorelines, with the remainder (except that which evaporated or degraded) depositing to the sediments.
The condensate also would also have significant entrainment, but higher winds prevailing in under low flow conditions would enhance evaporation and rapidly lower concentrations in the water as compared to high-flow conditions. In all scenarios, a large amount of entrained oil and high concentrations of dissolved aromatics would move down the entire stretch of Kitimat River and into Kitimat River estuary.

Long term scenario

The modelling appears to be extremely optimistic when it reaches four to six weeks after the pipeline breach, especially in light of the continued cleanup efforts in Michigan, estimating that the “fast-flowing” nature of the Kitimat River would disipate all the different forms of hydrocarbon in the study saying

 a fast-flowing coastal river like Kitimat River, with gravel or cobble bottom would be affected by a large volume of crude oil released in a short period of time.

Oiling of shoreline soils is heavy in the reaches between the release point and 10 km downstream, becoming lighter to negligible beyond 10 km. Deposition of hydrocarbons to river sediment is greatest for the synthetic oil and diluted bitumen (high flow) scenarios extending up to 40 kilometres downriver, with predicted hydrocarbon concentrations in sediment approaching 1,000 mg/kg dry weight. Deposition of hydrocarbons to river sediment is considerably lighter for the diluted bitumen (low flow) and condensate scenarios. In these scenarios, oiling of river sediment is negligible….

It says that within four weeks of the end of the acute phase of the spill scenarios, concentrations in river sediments and river water would decline becoming quite low at the end of two years.

As for the affects on plants and invertebrates:

Oiling of shorelines would be extensive, particularly at assessment locations within 10 kilometres of the pipeline break location, under both the high and low flow scenarios, for synthetic oil and condensate. High loadings occur as far as 25 kilometres downstream, again asusming that damage would begin to disipate after four weeks declining over the next one to two years. Predicted effects are generally less severe for the diluted bitumen spill scenarios, due to lower expected loading of oil onto shorelines. Low to negligible shoreline oiling would occur for Kitimat River under most of the scenarios at the 40 kilometres assessment location and points downstream. Based on this assessment, very little oiling of shorelines would extend to the estuary and the environmental effects would be minimal.

The study goes on to say that the “model suggests that there would be no significant risk to fish health based upon chronic exposure to petroleum hydrocarbons  for the oil spill scenarios in Kitimat River or the potentially affected areas within the estuary, either at four weeks or one to two years following the hypothetical spill events. Risk to developing fish eggs in Kitimat River and estuary at four weeks and one to two years again indicate no significant risk to developing fish eggs in spawning gravels.”

It also claims that “chronic risks” to wildlife would be minimal, with some elevated risk for “muskrat, belted kingfisher, mallard duck, spotted sandpiper and tree swallow,” if they were exposed to synthetic oil. The muskrat, mallard duck and spotted sandpiper
could be vulnerable to bitumen and diluted bitumen.

It then claims that “no significant effects of chronic exposure (to all hydrocarbons) would occur for grizzly bear, mink, moose, river otter, bald eagle, Canada goose, herring gull or great blue heron for the Kitimat River hydrocarbon spill scenarios.”

Again, it appears from the sutdy that the spotted sandpiper would be most vulnerable to “bulk weathered crude oil exposure” includingcondensate, diluted bitumen and synthetic oil.

For the Kitimat section it concludes:

In the unlikely event of an oil spill, recovery and mitigation as well as the physical
disturbance of habitat along the watercourse would be likely to substantially reduce the exposure of wildlife receptors to hydrocarbons as compared to the scenarios evaluated here.

Link to Volume One of the Enbridge Northern Gateway Report Ecological and Human Health Assessment for Pipeline Spills

Tiny amounts of copper in rivers endanger salmon by affecting sense of smell

Tiny amounts of copper in a river affect a salmon’s sense of smell, making it harder to avoid predators, according to a study at Washington State University.

Jenifer McIntyre says the copper means that a salmon can’t detect another compound that ordinarily alerts them to be still and wary.

The minute amounts of copper can come from mines and even the brake linings of cars.

“A copper-exposed fish is not getting the information it needs to make good decisions,” says McIntyre, a postdoctoral research associate in WSU’s Puyallup Research and Extension Center, whose study built on earlier work that showed that copper can affect a salmon’s sense of smell and thus changing its behavour.

McIntyre put the two together, exposing juvenile coho salmon to varying amounts of copper and placing them in tanks with cutthroat trout, a common predator.

Healthy salmon can smell compounds in the water that are released when another fish is damaged. That substance, called Schreckstoff, German meaning “scary stuff,” alerts fish to nearby predators.

In her experiments, conducted in a four-foot-diameter tank, fish that weren’t exposed to copper would freeze in the presence of Schreckstoff, making it harder for motion-sensitive predators to detect them. On average, half a minute would go by before they were attacked.

But salmon in water with just five parts of copper per billion failed to detect the Schreckstoff and kept swimming. They were attacked in about five seconds.

“It’s very simply and obviously because predators can see them more easily,” says McIntyre. “They’re not in lockdown mode.”

The unwary exposed fish were also more likely to be killed in the attack, being captured 30 percent of the time on the first strike. Unexposed fish managed to escape the first strike nearly nine times out of ten, most likely because they were already wary and poised to take evasive action.

McIntyre also noticed that the behavior of predators was the same whether or not they had been exposed to copper.

Copper finds its way into streams and marine waters from a variety of sources, including motor vehicle brake linings, pesticides, building materials and protective boat coatings. Actual amounts will vary from undetectable in rural or forested areas to elevated in urban areas, especially when runoff from a storm washes roads of accumulated brake dust and other contaminants.

With testimony from McIntyre’s NOAA colleagues and others, the Washington State legislature in 2010 started phasing out copper brake pads and linings over the next 15 to 20 years. According to the state Department of Ecology, brake pads are the source of up to half the copper in the state’s urban waterways.

McIntyre used concentrations of between 5 and 20 parts per billion but has sampled highway runoff with 60 times as much copper. Copper’s effect is mediated by organic matter, which can make the metal unavailable to living things.

“My scenarios are potentially more like a hard-rock copper mining situation than storm water runoff, which typically carries dissolved organic matter along with the copper and other contaminants,” McIntyre says.

A number of large copper mining projects are proposed for the northwest region including, the controversial Taseko’s Prosperity copper mine near Williams Lake which was stopped after the local First Nations and environmental groups opposed the use of one lake for a tailings pond. Taseko is now trying to revive the project. There area also a number of copper mine proposals for the both the northwest BC coast and the Sacred Headwaters region, source of the major salmon rivers, the Skeena, Nass and Stikine. There is also a proposed copper mine Pebble Mine, at Bristol Bay, Alaska, another prime area for sockeye salmon.

Environmental impact of the Canadian copper mine projects are likely to be affected by the provisions of Bill C-38 which speed up environmental assessment and essentially gut habitat protection for fisheries.

Her research, conducted for a University of Washington doctorate with colleagues at UW and the National Oceanic and Atmospheric Administration, appears in the latest issue of the journal Ecological Applications.

JRP denies most requests from Coastal First Nations to question BC on Northern Gateway

The Northern Gateway Joint Review Panel has denied four out of the five requests from Coastal First Nations to question the province of British Columbia about its position on the controversial pipeline and tanker project. A decision on the fifth request is reserved pending a response from the province and other parties.

So far, the province has not participated in the Joint Review hearings nor has it filed any evidence.

A five part motion by the Coastal First Nations was an attempt to compel the government of Premier Christy Clark to participate.

The motion requested

a) compel the Province of British Columbia (Province) to file a technical report that was reported on in the Globe and Mail on 3 June 2012;

b) compel the Province to file any other reports or assessments it has;

c) allow intervenors to file information requests on any evidence filed by the Province;

d) compel the Province to indicate whether or not it will issue a Certificate for the
Project pursuant to the BC Environmental Assessment Act; and

e) compel the Province to indicate whether it intends to consult with First Nations on the
Project, and if so, how and when.

The JRP reserved its judgement on the request on item (a) to release the report mentioned in the Globe and Mail. A few days after Coastal First Nations made the request, lawyers representing the province requested an extension to respond to the CFN motion. The JRP gave both BC and Northern Gateway until July 16 to respond and then the CFN has until July 20 to reply.

On item (b) forcing the province to release other assessments, the JRP ruled that the information requested was “unclear and excessively broad” and so the request was denied.

On item (c) allowing intervenors to question on evidence from the province, the JRP ruled that Coastal First Nations had requested “a blanket right for parties to ask information
requests on evidence that is not yet filed.” The JRP said “ not persuaded that all parties ought to be given a blanket right to ask information requests on evidence that is not yet filed” and denied the request. The JRP added: “If a party believes it needs to ask a late information
request (as opposed to asking a hearing question) on specific evidence, the Panel will consider
that request.”

On items (d) and (e) the panel cited constitutional concerns, saying it related to authorizations in provincial jurisdiction and ruled “No justification is provided as to why this
information would be relevant to the federal review….” The JRP said it was “persuaded that it has any legal authority over these areas of provincial jurisdiction, or that it would be appropriate or relevant to the federal review, to obtain information about provincial affairs.”

JRP Ruling No 60 CFN Notice of Motion

US National Transportation Safety Board summary report on Marshall, MI, Enbridge oil spill incident blames deficient management and training

The United States National Transportation Safety Board has issued a summary report on the rupture of the the Enbridge pipeline and subsequent oil spill at Marshall, Michigan, in 2010.

The report says that the probable cause of the oil spill  included deficient integrity management at Enbridge, which allowed previously known crack defects in corroded areas to spread until the pipeline failed; inadequate training of control center personnel by Enbridge, which allowed the rupture to remain undetected for 17 hours and insufficient public awareness and education, which allowed the release to continue for nearly 14 hours after the first notification of an odor to local emergency response agencies.

The full NTSB report will be issued in the coming weeks.

Enbridge responded in a news release that quoted outgoing Enbridge CEO Pat Daniel, who was in Washington for the release of the report:

“We very much appreciate the patience of residents in the communities who were affected by the Line 6B release,” said Patrick D. Daniel, Chief Executive Officer, Enbridge Inc. “Under the direction of the U.S. Environmental Protection Agency and local health authorities, the Kalamazoo River was re-opened last month for recreational use. We are also pleased to note that wildlife has returned to the area.”

“We believe that the experienced personnel involved in the decisions made at the time of the release were trying to do the right thing. As with most such incidents, a series of unfortunate events and circumstances resulted in an outcome no one wanted,” said Mr. Daniel.

Skeena Bulkley Valley Member of Parliament and NDP House Leader, Nathan Cullen, issued his own news release, saying, “Today’s report by the US National Transportation Safety Board (NTSB) into the deadly July 2010 Enbridge spill in Michigan identifies ‘a complete breakdown of safety at Enbridge’ and notes the company knowingly ‘failed to accurately assess the structural integrity of the pipeline.'”

“The findings are actually worse than we feared,” Cullen said. “They are a body blow of breathtaking proportions to Enbridge and yet another wake-up call to the Northwest of the dangers of allowing big oil to run a pipeline through our Northwest watersheds.”

Cullen commended NTSB chair Deborah Hersman for her frankness in terming Enbridge’s Michigan spill “”an accident that is a wake-up call to the industry, the regulator, and the public.”

Here is the complete summary as posted on the NTSB website

Enbridge, Inc. Hazardous Liquid Pipeline Rupture

July 25, 2010
Marshall, MI

NATIONAL TRANSPORTATION SAFETY BOARD
Public Meeting of July 10, 2012
(Information subject to editing)
NTSB/PAR-12/01

This is a synopsis from the National Transportation Safety Board’s report and does not include the NTSB’s rationale for the conclusions, probable cause, and safety recommendations. Safety Board staff is currently making final revisions to the report from which the attached conclusions and safety recommendations have been extracted. The final report and pertinent safety recommendation letters will be distributed to recommendation recipients as soon as possible. The attached information is subject to further review and editing.

Executive Summary

On Sunday, July 25, 2010, at 5:58 p.m., eastern daylight time, a segment of a 30-inch-diameter pipeline (Line 6B), owned and operated by Enbridge Incorporated (Enbridge) ruptured in a wetland in Marshall, Michigan. The rupture occurred during the last stages of a planned shutdown and was not discovered or addressed for over 17 hours. During the time lapse, Enbridge twice pumped additional oil (81 percent of the total release) into Line 6B during two startups; the total release was estimated to be 843,444 gallons of crude oil. The oil saturated the surrounding wetlands and flowed into the Talmadge Creek and the Kalamazoo River. Local residents self-evacuated from their houses, and the environment was negatively affected. Cleanup efforts continue as of the adoption date of this report, with continuing costs exceeding $767 million. About 320 people reported symptoms consistent with crude oil exposure. No fatalities were reported.

Conclusions

1. The following were not factors in this accident: cathodic protection, microbial corrosion, internal corrosion, transportation-induced metal fatigue, third-party damage, and pipe manufacturing defects.

2. Insufficient information was available from the postaccident alcohol testing; however, the postaccident drug testing showed that use of illegal drugs was not a factor in the accident.

3. Had the firefighters discovered the ruptured segment of Line 6B and called Enbridge, the two startups of the pipeline might not have occurred and the additional volume might not have been pumped.

4. The Line 6B segment ruptured under normal operating pressure due to corrosion fatigue cracks that grew and coalesced from multiple stress corrosion cracks, which had initiated in areas of external of corrosion beneath the disbonded polyethylene tape coating.

5. Title 49 Code of Federal Regulations 195.452(h) does not provide clear requirements regarding when to repair and when to remediate pipeline defects and inadequately defines the requirements for assessing the effect on pipeline integrity when either crack defects or cracks and corrosion are simultaneously present in the pipeline.

6. The Pipeline and Hazardous Materials Safety Administration (PHMSA) failed to pursue findings from previous inspections and did not require Enbridge Incorporated (Enbridge) to excavate pipe segments with injurious crack defects.

7. Enbridge’s delayed reporting of the “discovery of condition” by more than 460 days indicates that Enbridge’s interpretation of the current regulation delayed the repair of the pipeline.

8. Enbridge’s integrity management program was inadequate because it did not consider the following: a sufficient margin of safety, appropriate wall thickness, tool tolerances, use of a continuous reassessment approach to incorporate lessons learned, the effects of corrosion on crack depth sizing, and accelerated crack growth rates due to corrosion fatigue on corroded pipe with a failed coating.

9. To improve pipeline safety, a uniform and systematic approach in evaluating data for various types of in-line inspection tools is necessary to determine the effect of the interaction of various threats to a pipeline.

10. Pipeline operators should not wait until PHMSA promulgates revisions to 49 Code of Federal Regulations 195.452 before taking action to improve pipeline safety.

11. PII Pipeline Solutions’ analysis of the 2005 in-line inspection data for the Line 6B segment that ruptured mischaracterized crack defects, which resulted in Enbridge not evaluating them as crack-field defects.

12. The ineffective performance of control center staff led them to misinterpret the rupture as a column separation, which led them to attempt two subsequent startups of the line.

13. Enbridge failed to train control center staff in team performance, thereby inadequately preparing the control center staff to perform effectively as a team when effective team performance was most needed.

14. Enbridge failed to ensure that all control center staff had adequate knowledge, skills, and abilities to recognize and address pipeline leaks, and their limited exposure to meaningful leak recognition training diminished their ability to correctly identify the cause of the Material Balance System (MBS) alarms.

15. The Enbridge control center and MBS procedures for leak detection alarms and identification did not fully address the potential for leaks during shutdown and startup, and Enbridge management did not prohibit control center staff from using unapproved procedures.

16. Enbridge’s control center staff placed a greater emphasis on the MBS analyst’s flawed interpretation of the leak detection system’s alarms than it did on reliable indications of a leak, such as zero pressure, despite known limitations of the leak detection system.

17. Enbridge control center staff misinterpreted the absence of external notifications as evidence that Line 6B had not ruptured.

18. Although Enbridge had procedures that required a pipeline shutdown after 10 minutes of uncertain operational status, Enbridge control center staff had developed a culture that accepted not adhering to the procedures.

19. Enbridge’s review of its public awareness program was ineffective in identifying and correcting deficiencies.

20. Had Enbridge operated an effective public awareness program, local emergency response agencies would have been better prepared to respond to early indications of the rupture and may have been able to locate the crude oil and notify Enbridge before control center staff tried to start the line.

21. Although Enbridge quickly isolated the ruptured segment of Line 6B after receiving a telephone call about the release, Enbridge’s emergency response actions during the initial hours following the release were not sufficiently focused on source control and demonstrated a lack of awareness and training in the use of effective containment methods.

22. Had Enbridge implemented effective oil containment measures for fast-flowing waters, the amount of oil that reached Talmadge Creek and the Kalamazoo River could have been reduced.

23. PHMSA’s regulatory requirements for response capability planning do not ensure a high level of preparedness equivalent to the more stringent requirements of the U.S. Coast Guard and the U.S. Environmental Protection Agency.

24. Without specific Federal spill response preparedness standards, pipeline operators do not have response planning guidance for a worst-case discharge.

25. The Enbridge facility response plan did not identify and ensure sufficient resources were available for the response to the pipeline release in this accident.

26. If PHMSA had dedicated the resources necessary and conducted a thorough review of the Enbridge facility response plan, it would have disapproved the plan because it did not adequately provide for response to a worst-case discharge.

27. Enbridge’s failure to exercise effective oversight of pipeline integrity and control center operations, implement an effective public awareness program, and implement an adequate postaccident response were organizational failures that resulted in the accident and increased its severity.

28. Pipeline safety would be enhanced if pipeline companies implemented safety management systems.

Probable Cause

The National Transportation Safety Board (NTSB) determines that the probable cause of the pipeline rupture was corrosion fatigue cracks that grew and coalesced from crack and corrosion defects under disbonded polyethylene tape coating, producing a substantial crude oil release that went undetected by the control center for over 17 hours. The rupture and prolonged release were made possible by pervasive organizational failures at Enbridge Incorporated (Enbridge) that included the following:

  • Deficient integrity management procedures, which allowed well-documented crack defects in corroded areas to propagate until the pipeline failed.
  • Inadequate training of control center personnel, which allowed the rupture to remain undetected for 17 hours and through two startups of the pipeline.
  • Insufficient public awareness and education, which allowed the release to continue for nearly 14 hours after the first notification of an odor to local emergency response agencies.

 

Contributing to the accident was the Pipeline and Hazardous Materials Safety Administration’s (PHMSA) weak regulation for assessing and repairing crack indications, as well as PHMSA’s ineffective oversight of pipeline integrity management programs, control center procedures, and public awareness.

Contributing to the severity of the environmental consequences were (1) Enbridge’s failure to identify and ensure the availability of well-trained emergency responders with sufficient response resources, (2) PHMSA’s lack of regulatory guidance for pipeline facility response planning, and (3) PHMSA’s limited oversight of pipeline emergency preparedness that led to the approval of a deficient facility response plan.

Recommendations

To the U.S. Secretary of Transportation:

1. Audit the Pipeline and Hazardous Materials Safety Administration’s onshore pipeline facility response plan program’s business practices, including reviews of response plans and drill programs, and take appropriate action to correct deficiencies.

2. Allocate sufficient resources as necessary to ensure that the Pipeline and Hazardous Materials Safety Administration’s onshore pipeline facility response plan program meets all of the requirements of the Oil Pollution Act of 1990.

To the Pipeline and Hazardous Materials Safety Administration:

3. Revise Title 49 Code of Federal Regulations 195.452 to clearly state (1) when an engineering assessment of crack defects, including environmentally assisted cracks, must be performed; (2) the acceptable methods for performing these engineering assessments, including the assessment of cracks coinciding with corrosion with a safety factor that considers the uncertainties associated with sizing of crack defects; (3) criteria for determining when a probable crack defect in a pipeline segment must be excavated and time limits for completing those excavations; (4) pressure restriction limits for crack defects that are not excavated by the required date; and (5) acceptable methods for determining crack growth for any cracks allowed to remain in the pipe, including growth caused by fatigue, corrosion fatigue, or stress corrosion cracking as applicable.

4. Revise Title 49 Code of Federal Regulations 195.452(h)(2), the “discovery of condition,” to require, in cases where a determination about pipeline threats has not been obtained within 180 days following the date of inspection, that pipeline operators notify the Pipeline and Hazardous Materials Safety Administration and provide an expected date when adequate information will become available.

5. Conduct a comprehensive inspection of Enbridge Incorporated’s integrity management program after it is revised in accordance with Safety Recommendation (11).

6. Issue an advisory to all hazardous liquid and natural gas pipeline operators describing the circumstances of the accident in Marshall, Michigan—including the deficiencies observed in Enbridge Incorporated’s integrity management program—and ask them to take appropriate action to eliminate similar deficiencies.

7. Develop requirements for team training of control center staff involved in pipeline operations similar to those used in other transportation modes.

8. Extend operator qualification requirements in Title 49 Code of Federal Regulations 195 Subpart G to all hazardous liquid and gas transmission control center staff involved in pipeline operational decisions.

9. Amend Title 49 Code of Federal Regulations Part 194 to harmonize onshore oil pipeline response planning requirements with those of the U.S. Coast Guard and the U.S. Environmental Protection Agency for facilities that handle and transport oil and petroleum products to ensure that pipeline operators have adequate resources available to respond to worst-case discharges.

10. Issue an advisory bulletin to notify pipeline operators (1) of the circumstances of the Marshall, Michigan, pipeline accident, and (2) of the need to identify deficiencies in facility response plans and to update these plans as necessary to conform with the nonmandatory guidance for determining and evaluating required response resources as provided in Appendix A of Title 49 Code of Federal Regulations 194, “Guidelines for the Preparation of Response Plans.”

To Enbridge Incorporated:

11. Revise your integrity management program to ensure the integrity of your hazardous liquid pipelines as follows: (1) implement, as part of the excavation selection process, a safety margin that conservatively takes into account the uncertainties associated with the sizing of crack defects from in-line inspections; (2) implement procedures that apply a continuous reassessment approach to immediately incorporate any new relevant information as it becomes available and reevaluate the integrity of all pipelines within the program; (3) develop and implement a methodology that includes local corrosion wall loss in addition to the crack depth when performing engineering assessments of crack defects coincident with areas of corrosion; and (4) develop and implement a corrosion fatigue model for pipelines under cyclic loading that estimates growth rates for cracks that coincide with areas of corrosion when determining reinspection intervals.

12. Establish a program to train control center staff as teams, semiannually, in the recognition of and response to emergency and unexpected conditions that includes supervisory control and data acquisition system indications and Material Balance System software.

13. Incorporate changes to your leak detection processes to ensure that accurate leak detection coverage is maintained during transient operations, including pipeline shutdown, pipeline startup, and column separation.

14. Provide additional training to first responders to ensure that they (1) are aware of the best response practices and the potential consequences of oil releases and (2) receive practical training in the use of appropriate oil-containment and -recovery methods for all potential environmental conditions in the response zones.

15. Review and update your oil pipeline emergency response procedures and equipment resources to ensure that appropriate containment equipment and methods are available to respond to all environments and at all locations along the pipeline to minimize the spread of oil from a pipeline rupture.

16. Update your facility response plan to identify adequate resources to respond to and mitigate a worst-case discharge for all weather conditions and for all your pipeline locations before the required resubmittal in 2015.

To the American Petroleum Institute:

17. Facilitate the development of a safety management system standard specific to the pipeline industry that is similar in scope to your Recommended Practice 750, Management of Process Hazards. The development should follow established American National Standards Institute requirements for standard development.

To the Pipeline Research Council International, Inc.:

18. Conduct a review of various in-line inspection tools and technologies—including, but not limited to: tool tolerance, the probability of detection, and the probability of identification—and provide a model with detailed step-by-step procedures to pipeline operators for evaluating the effect of interacting corrosion and crack threats on the integrity of pipelines.

To the International Association of Fire Chiefs and the National Emergency Number Association:

19. Inform your members about the circumstances of the Marshall, Michigan, pipeline accident and urge your members to aggressively and diligently gather from pipeline operators system-specific information about the pipeline systems in their communities and jurisdictions.

Previous Recommendation Reiterated in this Report

To the Pipeline and Hazardous Materials Safety Administration:

Require operators of natural gas transmission and distribution pipelines and hazardous liquid pipelines to provide system-specific information about their pipeline systems to the emergency response agencies of the communities and jurisdictions in which those pipelines are located. This information should include pipe diameter, operating pressure, product transported, and potential impact radius. (P-11-8)

A live and archived webcast of the proceedings will be available at http://www.capitolconnection.net/capcon/ntsb/ntsb.htm. To report any difficulties viewing the webcast, please call 703-993-3100 and ask for webcast technical support.

The complete report will appear on ntsb.gov in several weeks.

In its response, Enbridge went on to say:

“Safety has always been core to our operations. Our intent from the beginning of this incident has been to learn from it so we can prevent it from happening again, and to also share what we have learned with other pipeline operators,” said Stephen J. Wuori, President, Liquids Pipelines, Enbridge Inc. “Enbridge and EEP conducted a detailed internal investigation of this incident in the months following the release and have made numerous enhancements to their processes, procedures and training as a result of the findings of the investigation, including in the control center. Incident prevention, detection and response have also been enhanced. We will carefully examine the findings in the NTSB report to determine whether any further adjustments are appropriate.”

Enbridge  says it has e worked closely and cooperatively with the NTSB throughout its investigation.  The company isnow reviewing the summary report and  will not comment specifically on the contents of the Final Report until it is released by the NTSB Board and analysis of the report has been completed.

Enbridge question on “marine vessel activity” on Douglas Channel gets obvious answer from the Haisla

Fog shrouds Kitimat harbour
Fog and low clouds shroud Kitimat harbour on the morning of June 27, 2012. (Robin Rowland/Northwest Coast Energy News)

If there is a major disconnect between the people who live in the Kitimat region and the rest of Canada, it is the question of vessel traffic on the Douglas Channel, with Enbridge spinning that there is already major tanker traffic on the Channel.

This section from the Northern Gateway website, is often quoted by Enbridge supporters, the vast majority of whom live in Alberta, thousands of kilometres away, have never been to Kitimat, but, somehow from Calgary or Fort McMurray,  claim to know more about the Douglas Channel than people who live in Kitimat, including those who have sailed Douglas Channel for decades.

On its website Northern Gateway claims

According to numbers from the Port of Kitimat, not only have vessels carrying industrial products been travelling the channels safely for some 35 years, but so too have ships carrying petroleum products—like the one featured arriving in the Port of Kitimat through the Douglas Channel in the picture above.
In fact, some 1,560 vessels carrying methanol and condensate called on Kitimat port from 1982 to 2009 – that’s over 3,100 transits of vessels dedicated to the transport of petroleum products.
When you add vessel traffic of all industrial activity into Kitimat port, the number jumps to 6,112.
To be clear…the number of ships servicing industry arriving at Kitimat port between 1978 and 2009 is 6,112. That’s 12,224 transits!

So in its questions to the Haisla, Enbridge asked:

c) Please confirm that the Haisla Nation is aware of existing and proposed
marine vessel activity within its Traditional Territory, including:

(i) fuel barges

(ii) cargo/container ships

(iii) commercial fishing vessels

(iv) condensate tankers

(v) liquefied natural gas tankers

 

Enbridge’s question was an obvious attempt to enhance their spin on vessel traffic on the Douglas Channel, by fishing for an admission that large vessels already ply the Channel, something the residents of the Kitimat, both First Nations and non-aboriginal already know well.

In its response, the Haisla Nation replies:

The Haisla Nation is aware of the existing and proposed marine vessel activity within its Territory, including fuel barges, cargo/container ships, commercial fishing vessels, condensate tankers, and liquefied natural gas tankers.

The Haisla Nation is also aware of the increased cumulative effect of additional marine vessel activity as projects are approved. The presence of this shipping increases the significance of the potential impacts of the project on Haisla Nation aboriginal title and rights, through cumulative impacts.

The Haisla Nation is responsible for some of the vessel traffic within its Territory, with modern forms of transportation having replaced canoes. Until legal developments in the early 2000s which have defined the content of the honour of the Crown with respect resource decisions and potential impacts on First Nations, the Haisla Nation had little say about the projects with associated vessel traffic in its Territory.

While standard petroleum product tankers, many carrying condensate, a natural gas product, have been visiting Kitimat for years, there have. so far, been no supertankers, much less Very Large Crude Carriers. No bitumen carrying tankers have visited Kitimat, a fact always ignored by the region’s critics in Alberta and by Enbridge on its website.

Not only the filing by the Haisla Nation but most of the testimony at the recent public comment hearings in at Kitamaat Village, were about the fear of the growing cumulative effect of greatly increased tanker traffic on the Channel.

Haisla Nation, in JRP filing, “take offence” at implication of Enbridge’s funding questions

Haisla NationThe Haisla Nation, in its response to a series of questions about funding posed by Enbridge through the Joint Review process, has replied that it “ takes offence at the implication that its participation in the Joint Review Panel process is strictly to oppose the Northern Gateway Project.”

The funding questions by Enbridge were, in effect, a political fishing expedition by the energy company, because in one question Enbridge was asking about money that may have come from the charity Tides Canada, which is now subject a concerted attack by the Conservative government and right-wing  columnists in the business media.

In its response to Enbridge, the Haisla Nation says it has received no funding from Tides Canada.

The Haisla Nation, however, does detail what funding it has received, including some from Enbridge, and then counters that with details of just how expensive it is to participate in the Joint Review Process.

The Haisla say that in December, 2009, the First Nation asked the Canadian Environmental Assessment Agency for $1,593,900 for participating in the Joint Review Panel process over the next two years.

According to the document filed with the JRP, the Haisla Nation says the Canadian Environmental Assessment Agency offered $371,500, leaving a shortfall of $1,222,400.

The Haisla say that they have now reviewed that original application and the First Nation “notes that even the $1,593,900 sought in the original application for participant funding would not be enough to cover these costs.”

The Haisla acknowledge that they did receive funding from Enbridge Northern Gateway The Haisla Nation has received funding from the Northern Gateway “to prepare and provide a traditional use study in relation to the proposed project,” without stating the actual amount, adding that participating in the JRP has created a deficit “costing the Haisla Nation funds that will need to be diverted from other pressing projects and issues.”

Enbridge’s next question asked if the Haisla Nation was a member of the Turning Point/Great Bear Initiative and therefore had received funding for “opposing the Northern Gateway Project?”
The Haisla reply that:

The Haisla Nation takes offence at the implication that its participation in the Joint Review Panel process is strictly to oppose the Northern Gateway Project. As set out above, the Haisla Nation is participating in the Joint Review Panel process as it is currently the only process for assessing the proposed project. This process has been imposed without meaningful consideration of Haisla Nation concerns, and the Haisla Nation is participating despite an unlevel playing field.

The Haisla Nation has not received funding from the Turning Point/Great Bear Initiative to participate in the Joint Review Panel proceedings, to oppose the Northern Gateway Project, or for any other purpose regarding the Northern Gateway Project.

The Haisla then emphasize:

The Haisla Nation has not received funding from Tides Canada or similar organizations, either directly or indirectly, to participate in the Joint Review Panel proceedings, to oppose the Northern Gateway Project, or for any other purpose regarding the Northern Gateway Project.

The next question from Enbridge not only asked about the personal finances of members of the Haisla Nation council, but also showed that even after years of involvement with First Nations, Enbridge still hasn’t done its homework and can’t even spell “Kitamaat.”

Enbridge asked:

Have any members of the Kitimaat Village Council received funding from Tides Canada or similar organizations to participate in this proceeding or to otherwise oppose the Northern Gateway Project, either directly or indirectly? If so, how much funding was received and by whom?

The Haisla reply by saying

This question is beyond the scope of matters currently before the Joint Review
Panel. Nevertheless, the Haisla Nation offers the following information:

“Kitimaat Village Council” is a misspelling of the former name of the Haisla
Nation Council. The Haisla Nation Council is the elected government of the
Haisla Nation.

The document then lists the names of the current members of the Haisla Nation Council (which are available to Enbridge and everyone else on the Haisla Nation website) and goes on to say:

The Haisla Nation Council is governed by rules and a code of ethics that require disclosure of any potential conflicts of interest. If any member of Haisla Nation Council had received funding from Tides Canada or similar organizations in their personal capacity, they would have had to disclose this to Council.

None of these members have received funding from Tides Canada or similar organizations, either directly or indirectly, to participate in the Joint Review Panel proceedings, to oppose the Northern Gateway Project, or for any other purpose regarding the Northern Gateway Project.

The final question from Enbridge asked the Haisla, in the financial disclosure to
“include funding received by the Headwaters Initiative.”

The Haisla reply:

Headwaters Initiative has no affiliation with the Haisla Nation Council. The Haisla Nation Council has no information about funding received by Headwaters Initiative.

That question again shows again that despite years of involvement in northwestern British Columbia, Enbridge hasn’t done its homework, since the Headwaters Initiative is an environmental organization with members from not only the Haisla Nation but also non-aboriginal residents of both Kitimat and Terrace.

It appears that Enbridge was asking those questions as part of a preparation for a “follow the money” spin campaign building on the work of blogger Vivian Krause and her right-wing supporters in the business media. If so, so far,  it hasn’t worked out very well for Enbridge.
Haisla Nation Response to NGP Information Request  (pdf)

Haisla outline where they believe Enbridge Gateway plans are inadequate

Haisla NationIn their filing with the Joint Review Panel, the Haisla Nation point to what they say is inadequate information provided by Enbridge on the Northern Gateway project, including:

To date the material provided by Northern Gateway does not adequately explain the known risks inherent to the proposed project and lacks significant detail with  respect to the extent and degree of potential effects. The material provided by  Northern Gateway does not provide sufficient information to determine how the  risks inherent to the proposed project will be minimized, nor how the potential for  significant adverse effects will be avoided.

There are a number of areas where the Haisla Nation has identified inadequateinformation, including but not limited to:

.
Design: there is a lack of information about detailed design  considerations and monitoring procedures for pipeline integrity to avoid  accidents and malfunctions due to corrosion, seismic events, and terrain  instability. A notable example of this problem is in the Kitimat River  Valley, where Northern Gateway has identified a high level of risk but has  not offered any solutions. Another is the concern about the corrosive nature of the material to be transported. Northern Gateway denies that  this is a problem, yet the US Department of Transportation Pipeline and
Hazardous Material Safety Administration (PHMSA) has commissioned a  major study to investigate the corrosive nature of diluted bitumen in pipelines.

Materials to be transported: there is a lack of information about the fate, behaviour and effects of diluted bitumen, synthetic crude and condensate in the cold water marine and freshwater environment. This concern has been identified by federal government participants as well as by numerous intervenors, and Northern Gateway has acknowledged the need for more research and information. Yet, Northern Gateway has not agreed to undertake this work so that it is available for review in this process.

Volume of material to be transported: Northern Gateway’s application is for a pipeline that will transport 525,000 barrels of diluted bitumen per day. Yet the pipeline will be built to have a capacity of up to 850,000 barrels per day, and Northern Gateway’s application materials identifies future phases with increased volumes up to this amount. The risk assessments conducted by Northern Gateway are premised on 525,000 barrels per day, and fail to contemplate higher volumes which would affect a number of matters, including but not limited to: pipeline risk; volume of potential spills; and tanker traffic volume. The risk assessment needs to be revised, to address the risks associated with the pipeline transporting 850,000 barrels of diluted bitumen per day. Without this revision, Northern Gateway is asking the JRP to conduct its assessment on incomplete information that, by definition, understates the true potential risk of the proposed project.

.Baseline information: Northern Gateway has not undertaken the studies necessary to generate baseline ecosystem assessments for the Kitimat River drainage and Kitimat Arm, including seasonal habitat utilization by species and life stages throughout the watershed. This information is necessary to determine both stream crossing construction strategy and to assess the potential impacts of a spill, as well as to determine how to respond to a spill and when. A ‘one-size fits all’ approach to stream crossings during construction and spill response, when adequateinformation about seasonal habitat utilization by species and life stages throughout the watershed is lacking, is not adequate. This information is needed to determine when construction can proceed and what timeframe limitations there are for activities, to ensure that adverse effects to fish and wildlife are avoided. This information is also required, should a spill occur, to enable a proper assessment of the extent and degree of adverse effects as well as to provide a proper basis for restoration of affected habitat.

Past spills: there is a lack of information about the cause, effects, emerging information and lessons learned as a result of Enbridge’s large diluted bitumen spill into the Kalamazoo River. We know that 3,785,400 liters of diluted bitumen were pumped out of the pipeline, with a largeportion of that ending up in to the Kalamazoo River. We know the large volume of the spill was the result of numerous attempts to re-pressurize the pipeline despite repeated spill alarms being triggered. We know that government agencies stepped in to manage the spill because Enbridge’s response was not swift enough. We know that Enbridge’s clean-up costs to date exceed insurance coverage. We know that two years later Enbridge is still under a clean-up mandate from the US Environmental Protection Agency and the Michigan Department of Environmental Quality, and that portions of the Kalamazoo River are still closed to recreational use. What we do not know, however, is what the cause of the pipeline rupture was, what Enbridge has learned about how diluted bitumen behaves once it is released into the environment, or how a local population that relies on the river for fishing, for traditional harvesting and gathering of foods and medicines would have been affected.

Oil spill response: there is a lack of information about oil spill response and planning, including best practices, best available technology and the local on-site equipment and personnel required full-time to respond properly to a spill. This is largely due to the lack of adequate baseline information on which to base response planning. Further, Northern Gateway has demonstrated an unwillingness to fully consider how spill response would be carried out until it receives a certificate for its project.

Yet Northern Gateway seeks to rely on spill response as a mitigation strategy. If Northern Gateway seeks to rely on spill response as a mitigation strategy, it should provide in detail, prior to project approval, what its oil spill response would include and demonstrate that it is logistically, technologically and economically feasible. Northern Gateway has not done this.

.Mitigation measures: there is a lack of information about existing proven mitigation measures and their effectiveness in cleaning up an oil spill, restoring habitat and regenerating the species dependent on the affected habitat. This should be evaluated as part of project review, prior to project approval. Where Northern Gateway seeks to rely on a mitigation measure as a basis for project approval, it must demonstrate that the proposed mitigation will actually work.

Avoidance of any significant adverse effects must be the primary goal and dictate the design and location of the proposed project. Mitigation (e.g. complete resolution) of any potential environmental effects should be the preferred option, when all efforts to avoid such effects fail. Compensation for environmental effects must be a last resort and relied on only when best efforts have been made to avoid or mitigate effects. Unfortunately, the material submitted by Northern Gateway suggests that compensation is the primary option and lack of evidence on project design and procedures makes it impossible to evaluate how potential effects could be avoided or mitigated.

For example, Northern Gateway proposes to have spill interception points (river control points) along the Kitimat River Valley as part of its mitigation, but has no realistic plan in place that takes into consideration response delay times, rates of transportation, access issues or baseline ecosystem, fish and wildlife information for the receiving environment.

 

 

Main story Haisla Nation confirms it opposes Northern Gateway, demands Ottawa veto Enbridge pipeline; First Nation also outlines “minimum conditions” if Ottawa approves the project

Haisla Nation Response to NGP Information Request  (pdf)

Haisla outline conditions, concerns for Northern Gateway project

Haisla NationIn its extensive document filed with the Northern Gateway Joint Review panel, the Haisla Nation emphasize their opposition to the project.

However, the Haisla are anticipating that the project will be approved and  therefore submitted a lengthy series of conditions for that project, should it be imposed on the northwest by the federal government.

Nevertheless, if the project were to be approved AFTER the Crown meaningfully consulted and accommodated the Haisla Nation with respect to the impacts of the proposed project on its aboriginal title and rights, and if that consultation were meaningful yet did not result in changes to the proposed project, the following conditions would, at a minimum, have to be attached to the project.

 

1. Conditions Precedent: The following conditions precedent should be met prior to any field investigations, pre-construction activities or construction activities as well as during and subsequent to such investigations or activities. These conditions are necessary to ensure that potential effects of the project can be avoided or mitigated to reduce the likelihood of habitat damage or destruction:

Comprehensive seasonal water quality monitoring throughout the Kitimat River watershed, Kitimat Arm and Douglas Channel that account for seasonal variations in flow, tidal cycles, snowmelt, rainfall, etc.

Parameters for measurement would be have to be agreed upon by the
Haisla Nation prior to certification of the project;

Comprehensive seasonal fisheries surveys of fish habitat utilization  throughout the Kitimat River watershed, Kitimat Arm and Douglas Channel that account for where species and life stages are at different times of the year and accurately define sensitive habitats;

Comprehensive seasonal wildlife and bird surveys of habitat utilization throughout the Kitimat River watershed, Kitimat Arm and Douglas Channel that account for where species and life stages are at different times of the year and accurately define sensitive habitats;

Comprehensive seasonal vegetation surveys of habitat utilization throughout the Kitimat River watershed, Kitimat Arm and Douglas Channel that accounts for the distribution of species and life stages at different times of the year and accurately define sensitive habitats;

Development of comprehensive spill response capability based on a realistic assessment of spill containment, spill response and spill capacity requirements throughout the Kitimat River Valley, Kitmat Arm and Douglas Channel. The Haisla Nation’s past experience has shown that relying onpromises is not good enough. This spill response capability must be demonstrated prior to project approval;

Verification that the proposed project would result in real benefits, economic or otherwise, that would flow to the Haisla Nation, to other First Nations, and to British Columbia.

Whenever any field investigations or activities are proposed, the proposal or permit application would have to include the following environmental protections:

Soil and erosion control plans;

Surface water management and treatment plans;

Groundwater monitoring plans;

Control and storage plans for fuels, lubricants and other potential contaminants;

Equipment deployment, access and use plans;

Habitat reclamation of disturbed or cleared areas.

Prior to any pre-construction or construction activities the following detailed studies would have to be undertaken and provided to the Haisla Nation for review and approval, to ensure that the best design and construction approaches are being used, so that potential effects of the project can be avoided or mitigated to reduce the likelihood of habitat damage or destruction:

Detailed analysis of terrain stability and slide potential throughout the pipeline corridor and at the storage tank and terminal site;

Detailed engineering design to mitigate seismic risk and local weather extremes;

.Development of pipeline integrity specifications and procedures including
best practices for leak detection;

Development of storage tank integrity specifications and maintenance and monitoring procedures;

Assessment of spill containment, spill response and spill capacity requirements throughout the Kitimat River watershed, Kitimat Arm and Douglas Channel;

.Development of detailed tanker acceptance program specifications and
procedures;

Development of detailed tanker and tug traffic management specifications and procedures;

Development of detailed port management specifications and procedures including operating limits for tanker operation, movement and docking.

2. Ongoing Consultation: A commitment to ongoing consultation with and accommodation of the Haisla Nation on all of the activities set out above.

3. Ongoing process for variance, waiver or discharge of conditions: A commitment to ongoing meaningful involvement of the Haisla Nation by the National Energy Board prior to any decision on any changes to or sign off on conditions and commitments to any certificate that is issued.

4. Third Party Oversight of Construction: A requirement that NorthernGateway fund a third party oversight committee, which should include a Haisla Nation representative, to monitor certificate compliance during construction of the marine terminal and the pipeline. This committee would have the ability to monitor and inspect construction and should be provided with copies of allcompliance documents submitted by Northern Gateway to the National Energy Board.

5. Operational Conditions: A number of operational conditions should beincorporated into the certificate, including but not limited to:

The requirement to monitor terrain along the pipeline so that breaches based on earth movements can be anticipated and prevented;

The requirement to implement automatic pipeline shutdown whenever a leak detection alarm occurs;

Conditions on the disposal of any contamination that must be removed as a result of an accident or malfunction resulting in a spill that will minimize additional habitat destruction and maximize the potential for regeneration of habitat and resources damaged by the spill;

Parameters for terminal and tanker operations (including standards for tankers allowed to transport cargo; tanker inspection requirements and schedules; escort tug specifications, standards, maintenance and inspection; pilotage protocols and procedures; environmental conditions and operating limits; etc.) as well as other parameters set out in and reliedon for the TERMPOL review to become conditions of any certificate issued by the National Energy Board, with a provision that the Haisla Nation’s approval of any changes to these conditions is required.

Answering the questions from Enbridge Northern Gateway, the Haisla also outline a long series of concerns.

1. Physical and Jurisdictional Impacts

1.1 Construction

The Haisla Nation is concerned about the direct physical and jurisdictional impacts that the construction of the proposed project will have. These concerns are set out for each of the marine terminal, the pipeline, and tanker traffic, below:

Marine Terminal:

a. The proposed marine terminal will require the alienation of 220-275
hectares (554-680 acres) of land from Haisla Nation Territory, land
to which the Haisla Nation claims aboriginal title.

b. The terminal will require the additional alienation of land for
ancillary infrastructure and development, including:

i. road upgrades,

ii. perimeter access roads and roads within the terminal area,

iii. a potential public bypass road,

iv. an impoundment reservoir,

v. a disposal site for excess cut material outside the terminal
area,

vi. a new 10km long transmission powerline, and

vii. a 100-m waterlot with a 150-m “safety zone”.

c. The terminal proposes to use Haisla Nation aboriginal title land,
including foreshore and waters, in a way that is inconsistent with
Haisla Nation stewardship of its lands, waters and resources and
with the Haisla Nation’s own aspirations for the use of this land.
Since aboriginal title is a constitutionally protected right to use the
aboriginal title land for the purposes the Haisla Nation sees fit, this
adverse use would fundamentally infringe the aboriginal title of the
Haisla Nation.

d. The terminal will require the destruction and removal of
documented culturally modified trees, some with modifications
dating back to 1754. These culturally modified trees are living
monuments to the history of the Haisla people.

e. The terminal will expose two Haisla Nation cultural heritage sites to
increased risk of vandalism and chemical weathering.

f. The terminal will result in the direct loss of 4.85 hectares (11.98
acres) of freshwater fish habitat (harmful alteration, disruption or
destruction (HADD) under the Fisheries Act).

g. The terminal will require dredging, underwater blasting, and
placement of piles and berthing foundations, resulting in an as yet
un-quantified loss of intertidal and subtidal marine habitat.

Pipeline:

a. The proposed pipeline construction right-of-way will require the
alienation of 9,200 hectares (22,734 acres) of Haisla Nation
Territory – land to which the Haisla Nation claims aboriginal title –
and will put this land to a use that is inconsistent with Haisla Nation
stewardship of its lands, waters and resources and with the Haisla
Nation’s own aspirations for the use of this land.

b. The pipeline will require 127 watercourse crossings in Haisla Nation
Territory. Seven of these are categorized as high risk, 5 as
medium high risk, and 7 are medium or medium low risk for harmful
alternation, disruption or destruction (HADD) of fish habitat. This
risk is just from pipeline construction and does not address the
issue of spills.

c. The pipeline is estimated to result in temporary or permanent
destruction of freshwater fish habitat of 3.1 hectares (7.68 acres) in
Haisla Nation Territory.

d. The pipeline will require the clearing of land and vegetation and the
destruction of wetlands. The extent of this is yet to be quantified.

Tanker Traffic:

a. Although Northern Gateway has not made any submission on this
point, it is clear that having adequate spill response capability at
Kitimat will require additional infrastructure upgrades in and around
Kitimat, as well as potential spill response equipment cache sites.
None of this has been considered or addressed in Northern
Gateway’s application material – as such the material is
incomplete.

b. The construction for this additional infrastructure could result
impacts to ecosystems, plants, wildlife and fish, and in additional
HADD or fish mortality from accidents.

All of the land alienations required for the proposed project would profoundly
infringe Haisla Nation aboriginal title which is, in effect, a constitutionally
protected ownership right. The proposed project would use Haisla Nation
aboriginal title land in a way that is inconsistent with Haisla Nation stewardship of
its lands, waters and resources and with the Haisla Nation’s own aspirations for
the use of this land. Since aboriginal title is a constitutionally protected right to
use the aboriginal title land for the purposes the Haisla Nation sees fit, this
adverse use would fundamentally infringe the aboriginal title of the Haisla Nation.

The Haisla Nation is also concerned about the socio-economic and health
impacts of the proposed project. Northern Gateway has yet to file its Human
Health and Ecological Risk Assessment. Further, the socio-economic impact
analysis submitted as part of the application provides only a limited assessment
of the potential impacts of the project on the Haisla Nation at a socio-economic
level.

Haisla Nation society and economy must be understood within the cultural
context of a people who have lived off the lands, waters and resources of their
Territory since long before European arrival. To limit a socio-economic impact
assessment to direct impacts and to ignore consequential impacts flowing from
those impacts fails to capture the potential impacts of the proposed project on the
Haisla Nation at a socio-economic level.

1.2 Operation

The proposed marine terminal, pipeline corridor and shipping lanes will be
located in highly sensitive habitats for fish, wildlife and plants. Any accident of
malfunction at the wrong time in the wrong place can be devastating ecologically.
The Haisla Nation has identified the following concerns relating to physical
impacts from the operation of the proposed project:

Marine Terminal:

a. Intertidal and subtidal marine habitat impacts as a result of marine
vessels.
b. The likelihood of spills from the marine terminal as a result of operational
mistakes or geohazards.

c. The effects and consequences of a spill from the marine terminal. This
includes impacts on the terrestrial and intertidal and subtidal marine
environment and fish, marine mammals, birds, and other wildlife, as well
as impacts on Haisla Nation culture and cultural heritage that could result
from such impacts.

d. Response to a spill from the marine terminal, including concerns about
spill response knowledge, planning and capability, as well as impacts
flowing from response measures themselves.

Pipeline:

a. The likelihood of spills from the pipeline as a result of pipeline failure,
resulting from inherent pipeline integrity issues or external risks to pipeline
integrity, such as geohazards.

b. The effects and consequences of a spill from the pipelines. This includes
impacts on the terrestrial environment and freshwater environment, and
on plants, fish, birds, and other wildlife, as well as impacts on Haisla
Nation culture and cultural heritage that could result from such impacts.

c. Response to a spill from the pipelines, including concerns about spill
response knowledge, planning and capability, as well as impacts flowing
from response measures themselves.

Tanker Traffic:

a. Increased vessel traffic in waters used by Haisla Nation members for
commercial fishing and for traditional fishing, hunting and food gathering.

b. The likelihood of spills, including condensate, diluted bitumen, synthetic
crude, and bunker C fuel and other service fuels, from the tankers at sea
and at the marine terminal.

c. The effects and consequences of a spill. This includes impacts on the
marine environment and fish, marine mammals, birds, and other wildlife,
as well as impacts on Haisla Nation culture and cultural heritage that could
result from such impacts.

d. Response to a spill, including concerns about spill response knowledge,
planning and capability, as well as impacts flowing from response
measures themselves.

e. Potential releases of bilge water, with concerns about oily product and
foreign organisms.
These issues are important. They go to the very heart of Haisla Nation culture.
They go to the Haisla Nation relationship with the lands, waters, and resources of
its Territory. A major spill from the pipeline at the marine terminal or from a
tanker threatens to sever us from or damage our lifestyle built on harvesting and
gathering seafood and resources throughout our Territory.

Northern Gateway proposes a pipeline across numerous tributaries to the Kitimat
River. A spill into these watercourses is likely to eventually occur. The evidence
before the Panel shows that pipeline leaks or spills occur with depressing
regularity.

One of Enbridge’s own experiences, when it dumped 3,785,400 liters of diluted
bitumen into the Kalamazoo River, shows that the concern of a spill is real and
not hypothetical. A thorough understanding of this incident is critical to the
current environmental assessment since diluted bitumen is what Northern
Gateway proposes to transport. However, nothing was provided in the application
materials to address the scope of impact, the level of effort required for cleanup
and the prolonged effort required to restore the river. An analysis of this incident
would provide a basis for determining what should be in place to maintain
pipeline integrity as well as what should be in place locally to respond to any spill.

The Kalamazoo spill was aggravated by an inability to detect the spill, by an
inability to respond quickly and effectively, and by an inability to predict the fate
of the diluted bitumen in the environment. As a result, the Kalamazoo River has
suffered significant environmental damage. The long-term cumulative
environmental damage from this spill is yet to be determined.

Further, the Haisla Nation is also concerned about health impacts of the
proposed project and awaits the Human Health and Ecological Risk Assessment
which Northern Gateway has promised to provide.

1.3 Decommissioning

Northern Gateway has not provided information on decommissioning that is detailed enough to allow the Haisla Nation to set out all its concerns about the potential impacts from decommissioning at this point in time. This is not good enough. The Haisla Nation needs to know how Northern Gateway proposes to undertake decommissioning, what the impacts will be, and that there will be financial security in place to ensure this is done properly.

2. Lack of Consultation

 

Broadly, the Haisla Nation has concerns about all three physical aspects of the
proposed project – the pipeline, the marine terminal and tanker traffic – during all
three phases of the project – construction, operation and decommissioning.
These concerns have not been captured or addressed by Northern Gateway’s
proposed mitigation. The Haisla Nation acknowledges that a number of these
concerns can only be addressed through meaningful consultation with the
Crown. The Haisla Nation has therefore repeatedly asked federal decision-
makers to commit to the joint development of a meaningful consultation process
with the Haisla Nation. The federal Crown decision-makers have made it very
clear that they have no intention of meeting with the Haisla Nation until the Joint
Review Panel’s review of the proposed project is complete.

The federal Crown has also stated that it is relying on consultation by NorthernGateway to the extent possible. The federal Crown has failed to provide anyclarity, however, about what procedural aspects of consultation it has delegated to Northern Gateway. Northern Gateway has not consulted with the Haisla Nation and has not advised the Haisla Nation that Canada has delegated any aspects of the consultation process.

The Haisla Nation asserts aboriginal title to its Territory. Since the essence of

aboriginal title is the right of the aboriginal title holder to use land according to its
own discretion, Haisla Nation aboriginal title entails a constitutionally protected
ability of the Haisla Nation to make decisions concerning land and resource use
within Haisla Nation Territory. Any government decision concerning lands,
waters, and resource use within Haisla Nation Territory that conflicts with a
Haisla lands, waters or resources use decision is only valid to the extent that the
government can justify this infringement of Haisla Nation aboriginal title.

The Supreme Court of Canada has established that infringements of aboriginal
title can only be justified if there has been, in the case of relatively minor
infringements, consultation with the First Nation. Most infringements will require
something much deeper than consultation if the infringement is to be justified.
The Supreme Court has noted that in certain circumstances the consent of the
aboriginal nation may be required. Further, compensation will ordinarily be
required if an infringement of aboriginal title is to be justified [Delgamuukw].

The Haisla Nation has a chosen use for the proposed terminal site. This land
was selected in the Haisla Nation’s treaty land offer submitted to British Columbia
and Canada in 2005, as part of the BC Treaty Negotiation process, as lands
earmarked for Haisla Nation economic development.

The Haisla Nation has had discussions with the provincial Crown seeking to
acquire these lands for economic development purposes for a liquefied natural
gas project. The Haisla Nation has had discussions with potential partners about
locating a liquefied natural gas facility on the site that Northern Gateway
proposes to acquire for the marine terminal. The Haisla Nation sees these lands
as appropriate for a liquefied natural gas project as such a project is not nearly
as detrimental to the environment as a diluted bitumen export project. This use,
therefore, is far more compatible with Haisla Nation stewardship of its lands,
waters and resources.

By proposing to use Haisla Nation aboriginal title land in a manner that is
inconsistent with Haisla Nation stewardship of its lands, waters and resources,
and that interferes with the Haisla Nation’s own proposed reasonable economic
development aspirations for the land, the proposed project would result in a
fundamental breach of the Haisla Nation’s constitutionally protected aboriginal
title.

Similarly, Haisla Nation aboriginal rights are constitutionally protected rights to
engage in certain activities (e.g. hunting, fishing, gathering) within Haisla Nation
Territory. Government decisions that infringe Haisla Nation aboriginal rights will
be illegal unless the Crown can meet the stringent test for justifying an
infringement.
Main story Haisla Nation confirms it opposes Northern Gateway, demands Ottawa veto Enbridge pipeline; First Nation also outlines “minimum conditions” if Ottawa approves the project

Haisla Nation Response to NGP Information Request  (pdf)

Haisla Nation confirms it opposes Northern Gateway, demands Ottawa veto Enbridge pipeline; First Nation also outlines “minimum conditions” if Ottawa approves the project

Haisla NationThe Haisla Nation has confirmed in a filing with the Northern Gateway Joint Review Panel that it opposes the Enbridge Northern Gateway project.

The document, filed June 29, 2012, is one of the most significant filed with the JRP during all the years of the debate over the controversial Northern Gateway, setting out a three stage process that will govern, whether Enbridge or the federal government like it or not, the future of the Northern Gateway pipeline project.

First, the Haisla Nation affirms that it opposes the Northern Gateway project

Second, the Haisla Nation is demanding that the federal government, in recognition of aboriginal rights and title, reject the Northern Gateway project on Haisla traditional territory.

Third, probably anticipating that Stephen Harper and his government will attempt to force the Northern Gateway on British Columbia, the Haisla are demanding meaningful consultation and set out a stringent set of minimum conditions for the project on Haisla traditional territory.

The Haisla Nation’s lawyers filed the document today late today, June 29, in response to a series of questions posed to the First Nation by Enbridge through the Joint Review process.

The Haisla also say that there already projects that are better suited to their traditional territory, the liquified natural gas projects.

The Haisla position that Ottawa must reject the pipeline if First Nations oppose it is the opening round in the constitutional battle over not just the pipeline, but entire question of aboriginal rights and title. So far the government of Stephen Harper has said that First Nations do not have a “veto” on the pipeline and terminal project.

The Haisla also refuse to answer questions that Enbridge posed on the liquified natural gas projects because the filing argues, the questions are beyond the scope of the current Joint Review inquiry.


Detailed excerpts

Haisla outline where they believe Enbridge Gateway plans are inadequate

Haisla outline conditions, concerns for Northern Gateway project

 


 

Why the Haisla oppose Northern Gateway

In the filing with the Joint Review panel, the Haisla outline nine reasons for opposition to the Northern Gateway project:

1. Northern Gateway is proposing to site its project in a location that places at risk the ecological integrity of a large portion and significant aspects of Haisla Nation Territory and resources.

2. All three aspects of the proposed project – the pipelines, the marine terminal and tankers – have the potential to impact Haisla Nation lands, waters and resources.

3. Northern Gateway has neither conducted sufficient due diligence nor provided sufficient information with respect to the assessment of a number of critical aspects of the proposed project, including but not limited to project design, impacts, risks, accidents and malfunctions, spill response, potential spill consequences and the extent, degree and duration of any significant adverse environmental effects.

4. There are significant risks of spills of diluted bitumen, synthetic crude, and condensate from corrosion, landslide hazards, seismic events along the pipeline route and at the terminal site; as well asloss of cargo or service fuels from tanker accidents, with no realistic plan provided for spill containment, cleanup, habitat restoration or regeneration of species dependent on the affected habitat.

5. Diluted bitumen, synthetic crude and condensate are all highly toxic to the environment and living systems and the consequences and effects of a spill could be devastating on the resources that support the Haisla Nation way of life, and would therefore have significant adverse effects on Haisla Nation culture and cultural heritage and aboriginal rights.

6. Risk assessments and technology have not overcome the potential for human error, wherein it is well established that 80% of oil tanker accidents that cause oil spills at sea are a result of human errors: badly handled manoeuvres, neglected maintenance, insufficient checking of systems, lack of communication between crew members, fatigue, or an inadequate response to a minor incident
causing it to escalate into a major accident often resulting in groundings and collisions (http://www.black-tides.com/uk/source/oil-tanker-accidents/causes-accidents.php). It has also become increasingly obvious that maintenance of pipeline integrity and the remote detection of pipeline ruptures is inadequate as exemplified by major environmental damage from recent pipeline ruptures in Michigan and Alberta.

7. The proposed project requires the alienation of Haisla Nation aboriginal title land, and the federal government has refused to engage in consultation with the Haisla Nation about the potential impacts of the proposed project on Haisla Nation aboriginal rights, including aboriginal title.

8. The proposed project would require the use of Haisla Nation aboriginal title land for a purpose that is inconsistent with Haisla Nation stewardship principles and with the Haisla Nation’s own aspirations for this land.

9. For the reasons set out above, the proposed project would constitute an unjustified infringement of Haisla Nation aboriginal title and rights. It would therefore be illegal for the Crown to authorize the project.

Canada is obliged to decline approval of the project

Up until now, the federal government has refused to engage First Nations in the northwestern region over the issue of the Northern Gateway pipeline and terminal, saying that the constitutionally mandated consultation will take place after the Joint Review Panel has released its report. However, the government’s Bill C-38, which gives the federal cabinet (actually the prime minister) the power to decide the pipeline means that the JRP report will be less significant than it would have been before the Conservatives gained a majority government in May, 2010.

The Haisla say the nation has “repeatedly requested early engagement by federal government decision-makers to develop, together with the Haisla Nation, a meaningful process for consultation and accommodation in relation to the proposed project.”

The filing says JRP and “the federal government’s ‘Aboriginal Consultation Framework’ have been imposed on the Haisla Nation and other First Nations, with significant aspects of the concerns expressed by the Haisla Nation about this approach being ignored.”

The Haisla says it “continues to seek a commitment from the federal government to the joint development of a meaningful process to assess the proposed project and its potential impacts on Haisla Nation aboriginal rights, including aboriginal title.”

Later in the filing the Haisla say:

The Haisla Nation has…  repeatedly asked federal decision-makers to commit to the joint development of a meaningful consultation process with the Haisla Nation. The federal Crown decision-makers have made it very clear that they have no intention of meeting with the Haisla Nation until the Joint Review Panel’s review of the proposed project is complete…

The federal Crown has failed to provide any clarity, however, about what procedural aspects of consultation it has delegated to Northern Gateway. Northern Gateway has not consulted with the Haisla Nation and has not advised the Haisla Nation that Canada has delegated any aspects of the consultation process.

The Haisla then go on to say:

Canada is legally required to work with the Haisla Nation to develop and follow such a process. If the process establishes that the approval of the proposed project would constitute an unjustified infringement of Haisla Nation aboriginal rights or aboriginal title, then Canada would be legally obliged to decline approval.

Deficiencies and Conditions

Enbridge asked the Haisla that if there are conditions of approval that would nonetheless
address, in whole or in part, the Nation’s concerns; and then asked for details “on the nature of any conditions that the Haisla Nation would suggest be imposed on the Project, should it be approved.”

The Haisla reply that because there are “significant deficiencies in the evidence provided by Northern Gateway to date.” The nation goes on to say that “the acknowledged risks that have not been adequately addressed in the proposed project.” The Haisla Nation then says it “does not foresee any conditions that could be attached to the project as currently conceived and presented that would eliminate the Haisla Nation’s concerns.”

The Haisla then repeat that Enbridge has not provided sufficient information so that

it is difficult for the Haisla Nation to identify conditions to attach to the proposed project as it is still trying to fully understand the potential impacts of the project and the proposed mitigation. This is primarily because there is insufficient information provided by Northern Gateway in its application material.

Although we have attempted to elicit additional information through the JRP’s information request process, Northern Gateway has not provide adequate and complete answers to the questions posed.

The Haisla then anticipate that Stephen Harper will force the pipeline and terminal on British Columbia and say:

Nevertheless, if the project were to be approved AFTER the Crown meaningfully
consulted and accommodated the Haisla Nation with respect to the impacts of
the proposed project on its aboriginal title and rights, and if that consultation were
meaningful yet did not result in changes to the proposed project, the following
conditions would, at a minimum, have to be attached to the project.

The emphasis of the word “after” is in the original document.

The document that then goes on to present an extensive list of list of conditions the Haisla believe should be imposed on the Enbridge Northern Gateway if the project goes ahead.

The conditions include comprehensive monitoring of water quality, fisheries, wildlife and birds, vegetation throughout the Kitimat River watershed, Kitimat Arm and Douglas Channel; development of comprehensive spill response capability throughout the Kitimat River Valley, Kitmat Arm and Douglas Channel.

The Haisla also want soil and erosion control plans; water management plans; control and storage plans for fuels, lubricants and other potential contaminants; detailed plans for equipment deployment and habitat reclamation of disturbed or cleared areas.

The Haisla also want much more detailed studies before any construction, including analysis of terrain stability and slide potential throughout the pipeline corridor and at the storage tank and terminal site; engineering designs to mitigate seismic risk and local weather extremes; development of pipeline integrity specifications and procedures including best practices for leak detection; storage tank integrity specifications, maintenance and monitoring; assessment of spill containment, spill response and spill capacity requirements throughout the Kitimat River watershed, Kitimat Arm and Douglas Channel.

On tankers the Haisla want more details beyond the plans already filed by Enbridge including
detailed tanker specifications, detailed tanker and tug traffic management procedures; detailed port management specifications and procedures including operating limits for tanker operation, movement and docking.

The Haisla are also demanding “on going consultation” on all issues involved by the National Energy Board prior to any decision on any changes to or sign off on conditions and commitments to any certificate that is issued.

The Haisla want an independent third party be part of a committee to oversee the construction proecess to monitor certificate compliance during construction of the marine terminal and the pipeline.

Once the pipeline and terminal operational, the Haisla want conditions imposed on the project that include ongoing monitoring of the terrain along the pipeline, a system that would automatically shut down the pipeline shutdown whenever a leak detection alarm occurs.

The Hasila want conditions “on the disposal of any contamination that must be removed as
a result of an accident or malfunction resulting in a spill that will minimize additional habitat destruction and maximize the potential for regeneration of habitat and resources damaged by the spill.”

As well as more detailed parameters for the tankers, tugs, and pilotage procedures, the Haisla want approval of any future changes in those procedures.

The Haisla are also concerned about the “alienation” of a large area of their traditional territory by the construction of the Northern Gateway project as well as the “additional infrastructure” required by adequate spill response capability and spill response equipment cache sites.

The Haisla say “all of the land alienations required for the proposed project would profoundly
infringe Haisla Nation aboriginal title which is, in effect, a constitutionally protected ownership right” and goes on to say “proposed project would use Haisla Nation aboriginal title land in a way that is inconsistent with Haisla Nation stewardship of its lands, waters and resources and with the Haisla Nation’s own aspirations for the use of this land.”

The Haisla filing then goes on to say:

Since aboriginal title is a constitutionally protected right to use the aboriginal title land for the purposes the Haisla Nation sees fit, this adverse use would fundamentally infringe the aboriginal title of the Haisla Nation.

The report also expresses concerns about the ongoing socio-economic affects of such a large project.

It concludes by saying:

These issues are important. They go to the very heart of Haisla Nation culture.
They go to the Haisla Nation relationship with the lands, waters, and resources of
its Territory. A major spill from the pipeline at the marine terminal or from a
tanker threatens to sever us from or damage our lifestyle built on harvesting and
gathering seafood and resources throughout our Territory.

Northern Gateway proposes a pipeline across numerous tributaries to the Kitimat
River. A spill into these watercourses is likely to eventually occur. The evidence
before the Panel shows that pipeline leaks or spills occur with depressing
regularity.

One of Enbridge’s own experiences, when it dumped 3,785,400 liters of diluted
bitumen into the Kalamazoo River, shows that the concern of a spill is real and
not hypothetical. A thorough understanding of this incident is critical to the
current environmental assessment since diluted bitumen is what Northern
Gateway proposes to transport. However, nothing was provided in the application
materials to address the scope of impact, the level of effort required for cleanup
and the prolonged effort required to restore the river. An analysis of this incident
would provide a basis for determining what should be in place to maintain
pipeline integrity as well as what should be in place locally to respond to any spill.

The Kalamazoo spill was aggravated by an inability to detect the spill, by an
inability to respond quickly and effectively, and by an inability to predict the fate
of the diluted bitumen in the environment. As a result, the Kalamazoo River has
suffered significant environmental damage. The long-term cumulative
environmental damage from this spill is yet to be determined.

Looking to the future, the Haisla are also asking for a plan for the eventual decommissioning of the project, pointing out that “ Northern Gateway has not provided information on decommissioning that is
detailed enough to allow the Haisla Nation to set out all its concerns about the
potential impacts from decommissioning at this point in time.”

Haisla leaders have already expressed concern about the legacy of the Eurocan paper plant. Now it tells Enbridge

This is not good enough. The Haisla Nation needs to know how Northern Gateway proposes to undertake decommissioning, what the impacts will be, and that there will be financial security in place to ensure this is done properly.

Asserts aboriginal title

The section of the report concludes by saying:

The Haisla Nation asserts aboriginal title to its Territory. Since the essence of
aboriginal title is the right of the aboriginal title holder to use land according to its
own discretion, Haisla Nation aboriginal title entails a constitutionally protected
ability of the Haisla Nation to make decisions concerning land and resource use
within Haisla Nation Territory. Any government decision concerning lands,
waters, and resource use within Haisla Nation Territory that conflicts with a
Haisla lands, waters or resources use decision is only valid to the extent that the
government can justify this infringement of Haisla Nation aboriginal title.

The Supreme Court of Canada has established that infringements of aboriginal
title can only be justified if there has been, in the case of relatively minor
infringements, consultation with the First Nation. Most infringements will require
something much deeper than consultation if the infringement is to be justified.
The Supreme Court has noted that in certain circumstances the consent of the
aboriginal nation may be required. Further, compensation will ordinarily be
required if an infringement of aboriginal title is to be justified [Delgamuukw].

The Haisla then go on to say that the preferred use of the land in question is for the liquified natural gas projects:

The Haisla Nation has a chosen use for the proposed terminal site. This land
was selected in the Haisla Nation’s treaty land offer submitted to British Columbia
and Canada in 2005, as part of the BC Treaty Negotiation process, as lands
earmarked for Haisla Nation economic development.

The Haisla Nation has had discussions with the provincial Crown seeking to
acquire these lands for economic development purposes for a liquefied natural
gas project. The Haisla Nation has had discussions with potential partners about
locating a liquefied natural gas facility on the site that Northern Gateway
proposes to acquire for the marine terminal. The Haisla Nation sees these lands
as appropriate for a liquefied natural gas project as such a project is not nearly
as detrimental to the environment as a diluted bitumen export project.

Northwest Coast Energy News is attempting to contact Enbridge Northern Gateway for comment on the Haisla filing. Response may be delayed by the Canada Day holiday.

 

Haisla Nation Response to NGP Information Request  (pdf)