Harper government reserves Gateway environmental decision for the cabinet, sets Dec. 31, 2013 deadline for JRP

The future of the Northern Gateway project is now completely in the hands of Prime Minister Stephen Harper’s cabinet.

Today, Friday, August 3, 2012, Environment Minister Peter Kent used the provisions of what the Harper government calls the Jobs, Growth and Long Term Prosperity Act (former Bill C-38) to set a final deadline for a report from the Northern Gateway Joint Review Panel  on December 31, 2013 and reserve the final environmental decision for the Governor-in-Council.

Today’s move, in effect, is the final gutting of the Joint Review Process, making it irrelevant, since, as long suspected, the government will now make the decision on its own.

The Joint Review Panel no longer has the power to reject the Northern Gateway on environmental grounds, that is now solely up to the Harper cabinet. Once the Gateway project is approved, as expected, the NEB has been ordered to issue the approval certificate within seven days.

By releasing the news on a Friday afternoon before a holiday weekend, the Harper government spin doctors through Environment Minister Peter Kent have also pulled the classic government move of releasing bad news when it will least be noticed.

There is also the new agreement between the Ministry of Environment and the National Energy Board. The revised memorandum of agreement says:

The Governor in Council will make the decision on the environmental assessment (whether the project is likely to cause significant adverse environmental effects and if, so whether such effects are justified in the circumstances). The Governor in Council will decide, by order, whether the board should issue a certificate and will give reasons for the order.

Under the act, the NEB now has to file its environmental assessments within 543 days of the act coming into force, hence the imposed deadline.

If there are no excluded periods this would mean that the environmental assessment and report must be submitted no later than Dec. 31, 2013.

The final paragraph of Kent’s letter also says

If the Project is approved by the Governor in Council, the NEB will issue the certificate of public convenience and necessity within seven days of the Governor in Council’s order.

That’s a clear indication that the Harper government still intends at this point to fast track the Northern Gateway project.

Apart from giving the most environment unfriendly cabinet in Canadian history the decision power, most of the memorandum of agreement are legalistic changes necessary to bring the former agreement into compliance with the new law.

The environmental sections of the agreement, based on the amendments to the Environmental Assessment act have a couple of interesting points

any change that the project may cause in the environment, including any change it may cause in listed wildlife species as critical habitat or residences of that species….

Although the memo goes on to say

any change to the project that may be caused by the environment whether such change or effect occurs within or outside Canada

While this may be simply legalistic language, given the overall tone of the Harper government’s policy, especially the changes in the Fisheries Act that only protects fish habitat when it affects  commercial species, one has to wonder if the emphasis on listed (that is threatened or endangered) species is again a narrowing of the criterion for approving the pipeline.

The second phrase is also ambiguous, seemingly to imply that the environment could be to blame  for any problems the project may face. Opponents have long pointed out that the environmental conditions and risks such as geologic instability along the pipeline route and the heavy weather in the waters off British Columbia are factors that increase the danger of an oil spill event whether on land or sea. However, the new agreement  presents an almost Orwellian scenario that would blame the environment, an “Act of God” in insurance terms, rather than the company or the government for any future disaster.

The main phrase in the agreement “whether such effects are justified in the circumstances” clearly indicates that the Harper government is fully prepared to ignore the environmental fallout of the Northern Gateway project and so the stage is set for a much wider political battle.

Peter Kent letter to JRP concerning the Northern Gateway Pipeline Project  (pdf)

Amendment to the Agreement concerning the Joint Review of the Northern Gateway Pipeline Project  (pdf)

 

 

 

Rolling Stone discovers Northern Gateway controversy, but gets lost on the way to Kitimat

Rolling Stone article on Canadian pipelines
A screen grab of the Rolling Stone article on the Canadian Northern Gateway and Keystone pipelines.

It’s every muscian’s dream to make it On the Cover of the Rolling Stone. (And when Rolling Stone does investigative journalism, every politician’s nightmare).

Now the venerable, storied music mag has discovered the Northern Gateway pipeline, running a story on August 2 on its website and slated to appear in the next dead tree issue on August 16.

The article by Jeff Goodell is a sort of a primer for hip but not yet clued in Americans on the controversies over Canadian pipelines. It features the usual nasty depiction of the bitumen sands with a file photo from the Washington Post via Getty.

But does Kitimat rate a mention in the magazine that has celebrated the Beatles, the Beach Boys, the (original and real) Rolling Stones, Bob Dylan, the Police, Nirvana, Justin Bieber and The Sheepdogs?

Nope.  Imagine that, an entire article on the Northern Gateway Pipeline and not one mention of Kitimat. Instead Goddell says:

Canada is pushing for a new route called the Northern Gateway, which would cut through three major watersheds in western Canada and turn the fragile coast of British Columbia into a bustling tanker port.

 

In one way Kitimat is in good company, for when the band that originated the “Cover” song, Dr. Hook & the Medicine Show, did make Rolling Stone, the magazine cover had “What’s-Their-Names Make the Cover.”

It’s one thing not to get any respect for Kitimat from the Alberta media, but at least Albertans spell Kitimat right (most of the time–although sometimes they get Kitamaat Village wrong). Here in the northwest we’re used to being dissed by Albertans.

Of course, while the entire coast is endangered by increased traffic in supertankers, it’s Kitimat that is the perhaps maybe, perhaps sometime, perhaps inevitable, perhaps never “bustling tanker port.”

So what could Kitimat do  to make it up from being ignored on the back pages of Rolling Stone to make it to the famous and proverbial cover?

My first idea was a vision of the District of Kitimat Council forming themselves into a rock band.

Joanne and the……  you can come up with an idea for a name, but I am not sure that would work.

Or maybe if we had a Justin Bieber concert at Riverlodge? That might keep young people from leaving Kitimat at least for a while.

Seriously. We’ve been ignored by Rolling Stone up until now. Now we’re that close to being   equal to What’s-Their-Names.

Maybe Kitimat can change that.

So now the people of Kitimat have a new challenge, beyond dealing with Enbridge, the JRP, the province and the feds,  beyond spending those long months clearing snow and those brief summer days of fishing, and that challenge is: get Kitimat on the cover of the Rolling Stone.

 

NEB conducting safety audit of Enbridge

The National Energy Board is following up a highly critical report by the US National Transportation Safety Board on the Marshall, Michigan spill by conducting an overall safety audit of Enbridge pipeline management and practices.  The NEB says the review began even before the NTSB report was released:

even prior to the release of the final report, we have been reviewing Enbridge’s management practices. In the next weeks and months, we will be conducting safety audits to review and confirm that improvements, particularly to their control room practices in Edmonton, are satisfactory.

In a letter to the public from NEB chair, Gaétan Caron, posted on the NEB website, the agency says: “Pipeline safety is and always has been of paramount concern to the National Energy Board and we recognize it is of growing concern to Canadians.”

The letter goes on to say:

Given recent events, it is important that Canadians understand how we hold companies accountable for public safety and protection of the environment and take swift and appropriate action when they do not.

The Board takes a proactive approach to preventing spills and releases, with the ultimate goal of seeing none at all. We require pipeline companies to anticipate, prevent, manage and mitigate potentially dangerous conditions associated with their pipelines.

To do this, we conduct compliance verification activities which include things such as inspections, compliance meetings, emergency exercises, audits and investigations on a regular basis with all companies we regulate. In the specific case of Enbridge, in recent years the NEB has conducted approximately 25 compliance verification activities per year, focusing on every aspect of their management system. In addition, the NEB imposed two precautionary pressure restrictions on Enbridge pipelines, one in 2010 and another in 2011, which remain in effect.

When the NEB identifies deficiencies in a company’s systems, projects or programs, we require the company to immediately implement changes to correct those deficiencies or to develop a corrective action plan for NEB approval. It is important to note that we aim to prevent incidents from occurring in the first place and we will take all available actions at our disposal to protect the environment and the public. The NEB may revoke authorizations, impose safety orders that restrict operations, issue stop-work orders and monetary penalties as well as pursue criminal prosecution.

The NEB has also reviewed the synopsis of the National Transportation Safety Board’s report on Enbridge’s Line 6B rupture in Michigan in 2010 to see what we can learn in the interests of public safety and environmental protection. A thorough review of the final report will be conducted in order to identify all lessons that may be applied to pipelines and companies under the Board’s jurisdiction, however even prior to the release of the final report, we have been reviewing Enbridge’s management practices. In the next weeks and months, we will be conducting safety audits to review and confirm that improvements, particularly to their control room practices in Edmonton, are satisfactory.

The NEB goes on to stay that Jobs, Growth and Long-term Prosperity Act (formerly Bill C-38) is giving the agency more bight:

 the Government of Canada will be adding another tool to our compliance and enforcement toolkit: administrative monetary penalties (AMPs). The new AMP sections in the NEB Act set out the maximum daily penalties for both individuals and companies. For individuals the maximum daily penalty is $25,000 for each violation and for companies the maximum daily penalty is $100,000 per violation.

The Act stipulates that each day a violation continues is considered to be a separate violation. This means that separate penalties could be issued per infraction, per day with no maximum total financial penalty.

Some of the details of the AMPs design are described in the government amendments to the NEB Act, but other details, such as what activities will be considered violations, will be written in a new regulation. We have committed to have these new regulations ready to use by July 6, 2013.

The NEB says it will continue to make public any enforcement measures it takes.

As a part of our Action Plan on Safety and Environmental Protection, we began posting all documents related to Board-initiated safety and environmental compliance actions to our website in fall of 2011.

The Board is committed to continually improving the way we do business and we welcome any opportunity that allows us to do so in the interests of pipeline safety and environmental protection.

Enbridge has not yet responded to the NEB release.

Haisla ask Gateway JRP to force Enbridge to release more Kalamazoo spill information

The Haisla Nation have asked the Northern Gateway Joint Review panel to force Enbridge to reveal more information about the pipeline rupture and oil spill near Kalamazoo, Michigan, in July 2010. The Haisla are also asking for more and better information about the $500 million project upgrades that Enbridge announced last month.

In a notice of motion filed July 30, with the JRP, lawyers representing the Haisla Nation note that they had previously asked Enbridge “a number of questions relating to Enbridge’s spill of 3,785,000 litres of diluted bitumen into the Kalamazoo River at Marshall, Michigan (the ‘Kalamazoo Spill’).”

The notice then notes that “Northern Gateway refused to reply as the matter was under investigation by the United States National Transportation Safety Board… The NTSB’s Accident Report was adopted on July 10, 2012 and has now been released to the public. The basis for Northern Gateway’s refusal to answer the Haisla Nation’s information requests is, therefore, no longer present.”

The Haisla are asking the JRP

that Northern Gateway is required to file evidence relating to the Kalamazoo Spill
which identifies the cause of the pipeline rupture and the extent to which
Enbridge’s pipeline maintenance, monitoring and response approach caused and
contributed to the volume of the spill by a date to be fixed by the Panel;

As for the upgrades, the Haisla notice of motion notes

Northern Gateway has identified additional design features, which it states will “enhance the safety and reliability of the pipelines over and above standard industry practice”. The design features identified in the Reply Evidence include increased wall thickness of the pipeline, additional increases in pipe thickness for crossings at major tributaries to the Fraser, Skeena and Kitimat River, the placement of remotely operated isolation valves on each side of major tributaries of the Fraser,Skeena and Kitimat Rivers, and dual remote monitoring systems ….
Northern Gateway has not provided any details relating to these proposed design
features. Their relevance and suitability to enhancing safety and reliability of the
pipelines cannot, therefore, be assessed.

The motion asks

that Northern Gateway is required to provide details of its proposed additional
design features for thicker pipes for the pipeline generally and at identified
watercourse crossings, for additional valve placements, and for additional remote
monitoring, as well as all studies and reports that support how these additional
design features enhance pipeline safety, by a date to be fixed by the Panel.

The Haisla motion also asks for more details on various environmental and other questions.

The Joint Review Panel has not yet ruled on the Haisla motion.

Haisla Nation Notice of Motion  (pdf)

Alison Redford accuses BC of “dividing Canada” with pipeline conditions

The premier of Alberta, Alison Redford, has released a stinging news release on the conditions outlined by British Columbia for pipelines crossing the province and tanker traffic on the coast.

A key phrase in the release says:

Leadership is not about dividing Canadians and pitting one province against another—leadership is about working together. That’s when our country benefits—that’s when Canada leads. Through a Canadian Energy Strategy, the provinces and territories together will reach their full energy potential and contribute to increased prosperity and a higher standard of living for all Canadians.”

Political analysts are interpreting Redford’s statement with its references to “free trade” as meaning that Alberta has rejected BC’s demand for a “fair share” of energy revenue.

The Globe and Mail quotes Alberta’s Official Opposition leader, Danielle Smith of the Wildrose party, as saying  BC . should be looking for more money from the federal government.

In Ottawa, the pro-pipeline Minister of Natural Resource, Joe Oliver, issued an unremarkable statement promoting  responsible resource development that managed to avoid mentioning the BC announcement; a statement that could be regarded as a classical press release that says absolutely nothing.
 

 

Here is the complete news release as posted on the premier’s website:

Premier Alison Redford issued the following statement following the Government of British Columbia’s announcement regarding the Northern Gateway Pipeline:

Alberta is committed to building our country and cementing Canada’s position as a global energy superpower. Leadership is about working together, and that’s when our country benefits from our energy economy.

Today, the Government of British Columbia released a list of requirements to be met to satisfy their concerns about the perceived environmental risks associated with the Northern Gateway Pipeline. Every Canadian, no matter what province they call home, expects that energy development is done with a high degree of environmental safeguards. This is why a rigorous environmental review is underway by the National Energy Board. It is why the company involved has committed an additional $500 million for increased monitoring and safety measures. These efforts, combined with the fact that pipelines are still by far the safest means by which to transport oil, significantly mitigate the environmental risk and weaken the BC government’s argument for compensation based on potential risk.

As Alberta has said repeatedly, and as we saw in the recent report from the Senate’s Energy, Environment and Natural Resources Committee, accessing new energy markets is a national imperative. It is essential for the economic benefit of Canada.

Our confederation works as well as it does because of the free flow of goods and products through provinces and territories—including forest products, oil, liquefied natural gas, potash, uranium, grain and manufactured goods.

We’ve worked very hard through our New West Partnership to ensure free trade across the BC/Alberta/Saskatchewan borders and the shared economic rewards have been great for our citizens.

Leadership is not about dividing Canadians and pitting one province against another—leadership is about working together. That’s when our country benefits—that’s when Canada leads. Through a Canadian Energy Strategy, the provinces and territories together will reach their full energy potential and contribute to increased prosperity and a higher standard of living for all Canadians.”

New US report slams Enbridge for spill record, as scientific investigation opens into diluted bitumen

A new US report is slamming Enbridge for its record on oil spills, just as the BC government set out strict new conditions for building pipelines and tanker traffic in the province.

The United States National Wildlife Association issued a report today called Importing Disaster, The Anatomy of Once and Future Oil Spills. (pdf of report at the bottom of this page)

At the same time,  the US Academy of Sciences has opened a new investigation into diluted bitumen.

 

 

 

A letter critical of Enbridge, previously overlooked by the US media is getting new traction, as the anniversary of the Marshall, Michigan, Kalamazoo River spill approaches on July 25.

Enbridge, so far, has not responded to the National Wildlife Federation report.

The environmental group opens the report by saying:

As the biggest transporter of Canadian tarsands oil into the U.S., Enbridge has aresponsibility to the American public to manage their operations in a manner that protects our comm unities and natural resources. But tarsands oil is a very different beast than conventional crude oil, and it is difficult to transport the former safely through pipelines that were designed for the latter. That’s because tarsands oil is more corrosive(due to its chemical mixture)and abrasive(due to high-gritminerals), weakening the pipes to the point  that they are more susceptible t oleaks and ruptures. Remarkably, there are no standards in place to ensure that new pipelines are built, maintained and operated with this fact in mind.

The National Wildlife Association goes on to say:

 fossil fuel companies have a ‘stranglehold’ on our political establishment, preventing even modest initiatives that could make our energy safer and cleaner. That lobby strategy keeps in place a system that’s led to 804 spills by Enbridge alone in the last decade, and a total of 6,781,950 gallons of oil spilled in the U.S. and Canada.

“Rather than focus on safety and cleanup, Enbridge is recklessly moving ahead with plans to expand their pipeline network in the Great Lakes region and the Northeast, and to double down on high carbon fuel that is proving nearly impossible to clean from Michigan’s waters,” said Beth Wallace, NWF’s Great Lakes outreach advisor.

NWF’s report recommends comprehensive reforms to break the cycle of spills and pollution that continue to threaten communities and speed global warming.  Among them, the report calls for stronger safety standards that account for increased dangers associated with heavy tar sands oil, increasing investment in clean energy and efficiency, and campaign and lobbying reforms that would put impacted citizens on a level playing field with Big Oil in the halls of Congress.

The NWF report then says:

 The Kalamazoo spill may have been a poster child for corporate negligence but it is far from the company’s only black mark. According to Enbridge’s own reports, between 1999 and 2010, they have been responsible for at least 800 spills that have released close to seven million gallons of heavy crude oil into the environment — or approximately half the amount of oil that spilled from the Exxon Valdez in 1989.

Canada has seen its own share of Enbridge heartache, including a 61,000 gallon spill earlier this summer near Elk Point, Alberta.

The National Wildlife Federation report is calling for  stronger pipeline safety standards that account for the dangers of transporting bitumen sands oil from Canada amd wants more rigorous reviews of all pipeline projects. The report calls bitumen sands oil “the planet’s dirtiest oil.”

US media covering the National Wildlife release and looking to the anniversary of the Kalamazoo disaster, are now quoting an overlooked letter from the US advocacy group Public Citizen issued on June 25.  

Concerned about Keystone XL pipeline, the advocacy group sent a letter to the Texas House of Representatives, recommending that the state should not wait for US federal rules to prevent tar sands pipeline spills. Public Citizen called the industry’s track record “troubled” and asked the committee to take up legislation that would give Texas broader authority over pipelines.

The committee will examine state regulations governing oil and gas well construction and integrity, as well as pipeline safety and construction, to determine what changes should be made to ensure that the regulations adequately protect the public. Public Citizen will testify in support of stronger rules for the Seaway pipeline (an existing line repurposed to carry tar sands instead of crude oil), the Keystone pipeline (whose southern leg is not yet built) and proposed future tar sands pipelines.

“These companies keep calling it petroleum, but it’s not – these are pipelines of poison,” said Tom “Smitty” Smith, director of Public Citizen’s Texas office.

The media reports on the NWF release are pointing to a new investigation by the US National Academy of Sciences on the safety of diluted bitmenl safety in the United States, that will be part of a report to the US Congress

 An ad hoc committee will analyze whether transportation of diluted bitumen (dilbit) by transmission pipeline has an increased risk of release compared with pipeline transportation of other liquid petroleum products.  Should the committee determine that increased risk exists, it will complete a comprehensive review of federal hazardous liquid pipeline facility regulations to determine whether they are sufficient to mitigate the increased risk.

On June 25, the committee added three industry experts to the panel as there is growing scrutiny over dilbit in the US, which could become an issue in the presidential race.

NWF Enbridge Oil Spill (PDF)

Enbridge files thousands of pages in document dump reply evidence to Northern Gateway JRP

Enbridge Northern Gateway has filed thousands of pages of “reply evidence” to the Northern Gateway Joint Review panel, responding to questions from the panel, from government participants like DFO, and intervenors.

Enbridge also used the filing to issue a news release saying it is adding $500 million in new safety features for its pipeline plans.

Northern Gateway Pipelines Reply_Evidence_  (summary of filings PDF)

Link to 43 item  reply filing on JRP website.

In the introduction to the summary of the evidence the JRP asks

Should the fact that Northern Gateway does not respond to all points in a particular intervenor’s evidence or to all intervenor evidence be taken as acceptance by
Northern Gateway of any of the positions of intervenors?

To which Enbridge replies:

No. Northern Gateway does not accept any of the intervenor positions that are contrary tothe Application or additional material filed by Northern Gateway. Some of those  positions will be dealt with by Northern Gateway in cross examination and argument rather than reply evidence, and others will simply be left to the JRP to determine on the basis of the filed evidence alone.

Related: Vancouver Sun: Christy Clark toughens pipeline stance as Enbridge announces safety upgrades

 

The reply covers a multitude of topics including

  • Economic Need and the Public Interest
  • Engineering
  • Avalanche Risk and Groundwater Concerns
  • Corrosivity of Diluted Bitumen
  • Improvements Since the Marshall Incident
  • Geotechnical Concerns
  • Geohazards Issues
  • Seismic Design Concerns
  • Recovery of Biophysical and Human Environment from Oil Spills
  • Corrosion, Inspection and Maintenance of Oil Tankers
  • Design and Construction of Oil Tankers
  • Pilotage

In response to numerous questions about the Marshall, Michigan, oil spill, Enbridge repeats what it said in an e-mail to “community leaders” earlier this week and in this morning’s news release, saying: “Enbridge has made a number of improvements since the Marshall incident.”

As part of the filing Enbridge has also filed an update on its aboriginal engagement program.

There are also detailed and updated reports on the company’s plans for the Kitimat valley region.

Enbridge files upgraded pipeline and marine safety plans with Northern Gateway Joint Review

Enbridge Northern Gateway today issued a news release saying that it has filed “Reply Evidence” to the Northern Gateway Joint Review panel that contains details of further enhancements in pipeline design and operations. Enbridge says the upgrades will add $500 million to the cost of the $5.5 billion project.

Enbridge has also filed updated plans for marine mammal protection.

The Enbridge news release is a summary of a 43-item filing of the reply evidence with the Joint Review Panel covering a vast number of topics from the pipeline projection to the possibility of earthquakes.

Related: Enbridge files thousands of pages in document dump reply evidence to Northern Gateway JRP

Northern Gateway Pipelines Reply_Evidence  (summary of filings PDF)

Link to 43 item  reply filing  on JRP website

Framework for Marine Mammal Protection Plan  (pdf)

According to the filing, the Marine Mammal Protection plan includes plans by Enbridge to fund research:

Northern Gateway has committed to funding a Marine Research Chair at a university in British Columbia.

Where it is agreed upon by the Marine Research Chair and Northern Gateway, programs and information from the MMPP will be integrated into research undertaken by the Marine Research Chair. Information from the Marine Research Chair may also be of value to the MMPP.

 

A spokesman for the University of British Columbia told Northwest Coast Energy News that no one from Enbridge has, so far, approached UBC about a Marine Research Chair.  A spokesperson at the University of Victoria also said there had been no contact from Enbridge.

On the pipeline plan, Enbridge says “These extra measures build on the plan in the application presently before federal regulators that already far surpasses industry codes and standards.”

“We recognize that there are concerns among Aboriginal groups and the public around pipeline safety and integrity. We had already planned to build a state-of-the-art project, using the most advanced technology, safety measures and procedures in the industry today,” said Janet Holder, Executive Vice President, Western Access, Enbridge Inc. “With these enhanced measures, we will make what is already a very safe project even safer in order to provide further comfort to people who are concerned about the safety of sensitive habitats in remote areas.”

Enbridge and the Northern Gateway project team have worked hard to ensure this unique project would be built and operated to the highest standards. The measures contained in the Reply Evidence go above and beyond anything that has ever been done before in the industry.

The extra measures include:

Increasing pipeline wall thickness of the oil pipeline
Additional pipeline wall thickness for water crossings such as major tributaries to the Fraser, Skeena and Kitimat Rivers
Increasing the number of remotely-operated isolation valves. This would increase the number of isolation valves in BC by 50%
Increasing frequency of in-line inspection surveys across entire pipeline system by a minimum 50% over and above current standards
Installing dual leak detection systems
Staff pump stations in remote locations on a 24/7 basis for on-site monitoring, heightened security, and rapid response to abnormal conditions
Enbridge expects these extra measures will carry an additional cost of approximately $400 million – $500 million.

“After years of consultation with stakeholders and after personally attending many regulatory hearings for Northern Gateway, it has become clear – we have to do everything we can to ensure confidence in the project,” said Ms. Holder. “We’ve listened. We have often been asked if we could guarantee that we would never have a significant pipeline failure over the years on Northern Gateway. These initiatives will put the project closer than any pipeline system in the world to providing that guarantee.”

Marine Mammal Protection Plan

In the filing, created by Stantec Consulting, Enbridge says the plan will address all marine mammal species that could be directly or indirectly affected  the Northern Gateway project, adding: “Attention will be given to species of cultural importance or heightened sensitivity to potential Project effects.”

The filing says Northern Gateway’s “commitment to a focused marine mammal monitoring and survey program is unprecedented for a marine project in Canada.”

It says that monitoring of marine mammals and “additional cooperative research initiatives” will also be of value to other organizations focused on supporting the recovery strategies for species of conservation concern.”

The report adds a caveat:

It is important to note ….it would be impractical to do a complete assessment of more than 30 different marine mammal species. Going forward, monitoring conducted in the CCAA will include additional marine mammal species For example, during marine mammal surveys, sightings of all marine mammal species would be recorded. In some cases, species-specific research initiatives (e.g., for northern resident (NR) killer whales) may also be implemented. Results from marine mammal monitoring surveys and research initiatives are expected to improve the regional understanding of all marine mammal species’ timing and distribution…

 

The report says the MMPP will include details on such measures as:

• low-noise propulsion systems on purpose built Project-related vessels (e.g., tug escorts and support
vessels for the marine terminal)
• reduced vessel speeds in the CCAA and in the “CCAA approaches”
• attempting to better understand the behavioural responses of NR killer whales to tankers and tugs
• identifying important habitat for NR killer whales and other cetaceans, as well as seasonal use of these habitats
• use of the results of a science-based quantitative vessel–marine mammal strike risk analysis
• to the extent practicable, allowing for tanker route adjustments (taking into account navigational andhuman safety) to avoid sensitive cetacean habitat during important seasonal periods
• undertaking a cooperative research initiative with other participating organizations to determine
potential effects on marine mammals and to develop industry protocols to limit these effects

Enbridge responds to NTSB criticism in e-mail to northwest BC “community leaders”

Enbridge Northern Gateway has issued a detailed reply to the criticism of its operations contained in a preliminary report from the US National Transportation Safety Board to the 2010 oil spill at Marshall, Michigan, which called the company’s response like the silent movie era “Keystone cops.”

The note from Michele Parrett,  Senior Manager, Community and Municipal Relations for Northern Gateway was sent to members of the District of Kitimat Council and presumably other politicians and community leaders along the proposed pipeline route.

The document was among those routinely released to the public at the regular council meeting on Monday, July 16, 2012 and is a much more detailed defence of Enbridge’s position than the news release issued after the NTSB report.

In the e-mail, Enbridge says it has updated its safety and response procedures and its corporate culture since the Michigan incident.

Despite widespread criticism of Enbridge from all sides of the political spectrum, that NTSB report does not seem to have had any impact on federal Environment Minister Peter Kent, who told The Canadian Press had had not yet read the NTSB report. Kent also said that unread report will not change the Conservative government’s mind about the Northern Gateway pipeline project, adding “Pipelines are still, by far, the safest way to transport petrochemicals in any form.”

 


 Overview of NTSB Report  into Line 6B  incident at Marshall, Michigan

July 12, 2012

Dear Community Leader,

I’m writing you today to provide information regarding the United States’ National Transportation Safety Board’s (NTSB) release of its conclusions and recommendations yesterday, with regard to the Enbridge pipeline leak in Marshall, Michigan in July 2010.

Enbridge has not been waiting for the NTSB’s report before furthering to improve our safety standards. Since the incident we have undertaken our own internal investigation and incorporated the findings of that investigation into new practices and processes to improve our safety and reliability.

Enbridge and Enbridge Energy Partners has been working with the NTSB and other regulators throughout the course of the investigation so that we can take the necessary steps to prevent such an accident from occurring again. We are now reviewing the NTSB reports in detail to determine whether any further changes are required.

Enbridge has already implemented, in 2010 and 2011, appropriate operational and procedural changes based on its own detailed internal investigation. Enbridge’s overarching objective and business priority is to ensure the safety and reliability of our delivery systems for the people who live and work near our pipeline systems across North America, our employees and our customers.

In direct response to the Marshall accident, or as part of our ongoing improvement initiatives and activities, Enbridge has taken the following steps:

Pipeline and Facility Integrity

· Further heightened the importance of our pipeline and facility integrity program.

· Re-organized the functional areas that are responsible for pipeline and facility integrity.

· Substantially increased capital and operating budgets associated with maintenance and integrity programs.

· Undertook hundreds of internal inspections and thousands of investigative digs.

· Placed a renewed emphasis on the safety of our overall system.

Leak Detection

· Established the Pipeline Control Systems and Leak Detection department, doubling the number of employees and contractors dedicated to leak detection and pipeline control.

· Enhanced procedures for leak detection analysis.

· Updated control room management procedures.

· Implemented a Leak Detection Instrumentation Improvement Program to add and upgrade instrumentation across our system.

Pipeline Control and Control Centre Operations (CCO)

· Developed a Control Room Management (CRM) plan based on the U.S. Code of Federal Regulations and implemented a number of the sections, October 1, 2011, remaining sections implemented by August 1, 2012.

· Revised and enhanced all procedures pertaining to decision making, handling pipeline start-ups and shutdowns, leak detection system alarms, communication protocols, and suspected column separations.

· Changed organizational structures to better align, focus and manage employees’ span of control and workloads.

· Augmented CCO (Control Centre Operations) staff, adding training, engineering and operator positions.

· We also completed the design and construction of a new, world-class CCO in Edmonton, Alberta which was underway at the time of the accident.

Public Awareness

· Reviewed and strengthened Public Awareness Programs in the U.S. and Canada.

· Developing an industry-leading online and in-person training tool to provide Enbridge-specific information to emergency responders.

· In the U.S, we:

o Formalized the U.S. Public Awareness Committee.

o Improved the Program Effectiveness Evaluation process.

o Provided annual employee training for field employees across the company’s U.S. operations.

o Created a Public Awareness Hotline.

· In Canada, we:

o Formalized the Canadian Public Awareness Committee.

o Are creating a Canadian Public Awareness Database.

o Improved the landowner/tenant database.

o Developed a landowner newsletter.

o Established Community Relations positions in each region.

Emergency Response

· $50 million spent between 2012 and 2013 (projected) to improve our equipment, training and capabilities.

· Develop better tools for waterborne spills.

· In 2011, a cross-business unit response team was created for large-scale events requiring more resources that a single region could provide.

· In 2011, created a dedicated Emergency Response group in Operation Services for increased regional support.

· Conducting an Emergency Response preparedness assessment to enhance abilities to more rapidly respond and contain a significant release.

Safety Culture

· Reinforced a high level of safety and operational integrity across Enbridge in integrity management, third-party damage avoidance and detection, leak detection, incident response capacity, worker and contractor occupational safety, public safety and environmental protection.

· Implemented “Lifesaving Rules” and training for all Enbridge employees and contractors. The Lifesaving Rules are applicable to all employees and contractors, and are communicated, clarified and reinforced across all business units at Enbridge.

· Introduced new Safety Culture training sessions for all employees.

Over the past two years we have made significant improvements in the above areas. The NTSB’s findings will provide us with regulatory guidance and important information to help improve our performance and achieve our goal of zero spills.

We remain committed to a respectful, open and transparent review and discussion of the Northern Gateway Project. Should you have any questions, please do not hesitate to contact me or a member of the Northern Gateway team at the information provided below.

Sincerely,

Michele Perret

Senior Manager, Community and Municipal Relations

Enbridge Northern Gateway Pipelines